Select another date

Spent Fuel Processing Facility (SFPF):

- Receipt  inspection of structures for mounting the IAEA cabinet in 107с.
- Finished backfilling of lead shot protective door SFP-SD-06.
- Marking of technological pipelines in the building of SFPF.

The following activities were also performed at the facility:

- Regular works on the construction site arrangement.
- Completing of executive & acceptance documentation according to the Contract.
- Development of test programs for technological units and systems.
- Development of a training program for Chornobyl Nuclear Power Plant personnel.
- Commissioning on main technological equipment and auxiliary.
- Finished Individual tests of the  ventilation and air conditioning system of the Gate House.
- Functional tests of crane SFP-CR-01 room. 119.
- Individual (Autonomous) tests of PCMS DWC Handling System, FT Handling System, SRW Management System.
- Individual tests of the security door SWP-SD-01.
- Finished Individual tests of the autonomous power supply system;
- Integrated testing of the Sewerage and Sewage Systems (Removing Remarks);
- Individual tests of the Cutting Machine SFA SFP-CS-205;
- Individual tests of the Removable Platforms SFP-PL-01;
- Finished Individual and Integrated testing of ISF-2 Fire Alarm and Personnel Evacuation Control System;
- Finished Individual and complex testing of the fire alarm warning system of Gate House;
- Finished Tests in accordance with Ukrainian Labor Service hoist MIS-CR-250, MIS-CR-15, KLE500GCL
- Individual Test of Canister Handling and Transport System CHT TD 02
- Functional tests of the crane SWP-CR-206 in room 403.

The general Contractor of the project is Holtec. Works at the site are being performed by Holtec subcontractors: CDI, UTEM, UTB, ZEM, EPI, BEM, Kranservis, Konditsioner. In total 189 persons were engaged in the works. 1 unit of lorry-loading, earth-moving and lifting machines were also used for fulfilling tasks at the site.

 

Select another date

Spent Fuel Processing Facility (SFPF):

- The installation of the IAEA shield equipment continues.
- Backfilling of lead shot protective door SFP-SD-06.
- Re-install the valves of LRW pipelines.
- Marking of technological pipelines in the building of SFPF.
- Work continues on assembling the electrical cabinet of the crane CR-04. Launching of cable lines.
- Finished installation of the crosshead on the crane SFP-CR-01.
- Finished installation of local fire-extinguishing means in electrical cabinets.
- Work continues on fire protection of cable lines.

The following activities were also performed at the facility:

- Regular works on the construction site arrangement, such as: weeding of gravel coatings, grass cutting, irrigation, maintaining clean asphalt coverings.
- Compilation of executive and hand-over documents.
- Development of test programs for technological units and systems.
- Development of a training program for Chornobyl Nuclear Power Plant personnel.
- Commissioning on main technological equipment and auxiliary.
- Finished individual tests of baskets in the room 109B/111B.
- Finished functional tests of hoists MIS-CR 14, MIS-CR-06 SFP-CR-301, PWS-CR-301\1, PWS-CR-301\2.
- Individual (Autonomous) tests of PCMS DWC Handling System, FT Handling System, SRW Management System.
- Individual tests of the security door SWP-SD-01.
- Individual tests of the ISNT-2 autonomous power supply system;
- Individual tests of the system "Emergency lighting of SFPF";
- Integrated testing on PPS have been started;
- Individual and complex testing of outdoor lighting PSC;
- Integrated testing tests of RMS;
- Integrated testing of the Sewerage and Sewage Systems (Removing Remarks);
- Test Barrel monitoring station (CBC), Sub-Canberra.

The general Contractor of the project is Holtec. Works at the site are being performed by Holtec subcontractors: CDI, UTEM, UTB, ZEM, EPI, BEM, Kranservis, Konditsioner. In total 192 persons were engaged in the works. 1 unit of lorry-loading, earth-moving and lifting machines were also used for fulfilling tasks at the site.

October 17, 2017
October 17, 2017
October 17, 2017
October 17, 2017
October 17, 2017
October 17, 2017

Select another date

Spent Fuel Processing Facility (SFPF):

- Installation of the crane SFP-CR-01 encoder support is completed.
- Installation of sensors and supports for video cameras at SFP-CR-07 is completed.
- Installation of inserts for manipulators and protective manipulators covers.
- Confirmation of acceptance of the machine installation for cutting machine discs replacement has been obtained. Welding of welding joints is completed.
- Distribution and adjusting  of CMDA automation panels of FGDS equipment.
- Installation of IAEA cabinet’s equipment is underway.
- Top coating of the premises.
- Marking of technological pipelines.
- Installation of primary fire extinguishing tools.

The following activities were also performed at the facility:

- Routine work on the construction site arrangement, such as: weeding of gravel coatings, grass cutting, watering, maintaining the cleanliness of asphalt coatings.
- Compilation of executive and hand-over documents.
- Development of test programs for technological units and systems.
- Development of training programs for ChNPP staff.
- Pre-commissioning works on the main technological equipment and auxiliary systems.
- Individual testing of video surveillance for the technological process.
- Individual testing of flow and exhaust general exchange ventilation systems.
- Preliminary autonomous testing of STPCM  of SRW, TP, DWSC management system.
- Individual testing of the 119 MIS-LD-04 lifting room gates.
- Individual (separate) testing of physical and radiation control systems is underway.

The general Contractor of the project is Holtec. Works at the site are being performed by Holtec subcontractors: CDI, UTEM, UTB, ZEM, EPI, BEM, Kranservis, Konditsioner. In total 197 persons were engaged in the works. 1 unit of lorry-loading, earth-moving and lifting machines were also used for fulfilling tasks at the site.

Select another date

Spent Fuel Processing Facility (SFPF):

- Installation of concrete insert for arm hoist.
- Re-installation of the rack in prem. 304 have been completed.
- Termination and adjustment of automation cabinets of CMDandA and FGDS equipment, disassembling metrological calibration detectors.
- Installation of cable routs for IAEA equipment, IAEA equipment installation is underway.
- Finishing of premises.
- Technological pipelines labeling.
- Installation of a new pump for chemically demineralised water (ChDW) has been completed.
- Checking of the spatial position of the sliding holder has been completed.
- The cutting machine positioning is checked.
- Installation of video surveillance system monitors has been completed.
- Installation of electromagnetic locks on the Tornado doors have been completed.
- Installation of security grids in air ducts.
- Installation of primary fire extinguishing equipment has started.

The following activities were also performed at the facility:

- Installation of sliding plates in CSM modules is underway.
- Regular works on the construction site arrangement, such as: weeding of gravel coatings, grass cutting, irrigation, maintaining clean asphalt coverings.
- Installation of scaffolding, electrical work at the structural addition for balloons.
- Compilation of executive and hand-over documents.
- Development of test programs for technological units and systems.
- Development of a training program for Chornobyl Nuclear Power Plant personnel.
- Pre-commissioning and adjustment works on the main technological equipment and auxiliary systems.
- Adjustment of the video observation system for the technological process.
- Functional tests of the bridge crane SFP-CR-04 in prem. 304.
- Functional tests of the console crane SFP-CR-06 in prem. 304.
- Individual tests of protective windows SW-03 and SW-04.
- Individual (independant) tests of physical and radiation control systems are underway.

The general Contractor of the project is Holtec. Works at the site are being performed by Holtec subcontractors: CDI, UTEM, UTB, ZEM, EPI, BEM, Kranservis, Konditsioner. In total 259 persons were engaged in the works. 1 unit of lorry-loading, earth-moving and lifting machines were also used for fulfilling tasks at the site.

Select another date

Spent Fuel Processing Facility (SFPF):

- Adjustment and preparation bridge crane SFP-CR-11 for functional tests.
- Installation of sub-crane  rail of arm hoist.
- Installation of arm hoist MIS-CR-250.
- Installation of concrete insert for arm hoists.
- Re-installation of the rack in prem. 304.
- Electrical and installation work to install automation boards and FFS equipment sensors, installation of cable tracks.
- Installation of cable routs for IAEA equipment.
- Finishing of premises.
- Technological pipelines labeling.
- Pre-commissioning works on the main technological equipment and auxiliary systems.
- Adjustment of the video observation system for the technological process of TK-8 system.
- Individual tests of the protective sliding door SFP-SD-212.
- Individual tests of the hot cell lighting system.
- Functional tests of SFP-CR-11 bridge crane.

The following activities were also performed at the facility:

- Installation of steel structures  of the structural addition for balloons.
- Installation of a round driveway (road covering) on the site of a tower crane.
- Laying a compressed air pipeline on the cartridges store.
- Regular works on the construction site arrangement, such as: weeding of gravel coatings, grass cutting, irrigation, maintaining clean asphalt coverings.
- Compilation of executive and hand-over documents.
- Development of test programs for technological units and systems.
- development of a training program for Chornobyl Nuclear Power Plant personnel.
- Individual (independent) tests of FPS systems.
- Individual tests of protective sliding doors SFP-SD-03 and SFP-SD-04 have been completed.
- Individual testing of 200-liter drums transportation system SWP-CR-222 (prem. IS102C7 / IS102C2) has been completed.
- Individual tests of the security windows SFP-SW-05 and SFP-SW-06 (premises 504/501) have been completed.
- Individual test of the indoor lighting system have been completed.
- Individual (independent) tests of FPS systems — central and back-up panels are underway.
- Individual tests of hot cells HCVS-S and HCVS-E ventilation system have been started.
- Individual tests of protective sliding doors SFP-SD-07 and SFP-SD-08 have been started.

The general Contractor of the project is Holtec. Works at the site are being performed by Holtec subcontractors: CDI, UTEM, UTB, ZEM, EPI, BEM, Kranservis, Konditsioner. In total 264 persons were engaged in the works. 5 units of lorry-loading, earth-moving and lifting machines were also used for fulfilling tasks at the site.

Page 2 of 9