ISF-2 construction progress as of September 6, 2017

Select another date

Spent Fuel Processing Facility (SFPF):

- Installation of the crane SFP-CR-01 encoder support is completed.
- Installation of sensors and supports for video cameras at SFP-CR-07 is completed.
- Installation of inserts for manipulators and protective manipulators covers.
- Confirmation of acceptance of the machine installation for cutting machine discs replacement has been obtained. Welding of welding joints is completed.
- Distribution and adjusting  of CMDA automation panels of FGDS equipment.
- Installation of IAEA cabinet’s equipment is underway.
- Top coating of the premises.
- Marking of technological pipelines.
- Installation of primary fire extinguishing tools.

The following activities were also performed at the facility:

- Routine work on the construction site arrangement, such as: weeding of gravel coatings, grass cutting, watering, maintaining the cleanliness of asphalt coatings.
- Compilation of executive and hand-over documents.
- Development of test programs for technological units and systems.
- Development of training programs for ChNPP staff.
- Pre-commissioning works on the main technological equipment and auxiliary systems.
- Individual testing of video surveillance for the technological process.
- Individual testing of flow and exhaust general exchange ventilation systems.
- Preliminary autonomous testing of STPCM  of SRW, TP, DWSC management system.
- Individual testing of the 119 MIS-LD-04 lifting room gates.
- Individual (separate) testing of physical and radiation control systems is underway.

The general Contractor of the project is Holtec. Works at the site are being performed by Holtec subcontractors: CDI, UTEM, UTB, ZEM, EPI, BEM, Kranservis, Konditsioner. In total 197 persons were engaged in the works. 1 unit of lorry-loading, earth-moving and lifting machines were also used for fulfilling tasks at the site.