Select another date

Spent Fuel Processing Facility (SFPF):

- Project works performance development (technological layouts) for fire protection closure of penetrations.
- Unloading of the equipment and materials, equipment transfer into the installation area.
- Works on the bridge crane SFP-CR-11 modification in prem. 501 are underway in terms of the electrical part.
- Works on the bridge crane SFP-CR-01 modification in prem. 119 are underway in terms of the electrical part.
- Works on the gantry crane SFP-CR-08 modification in prem. 305 are underway in terms of software and preparation for testing.
- Bridge crane SWP-CR-206 in prem. 403 adjustment and preparation for testing.
- Installation of concrete insert for arm hoist.
- Installation of main process equipment:
   * Electrical and installation work to install automation boards and FFS equipment sensors.
- Installation of BNG equipment power cables has been completed.
- BNG lighting cable laying and termination has been completed.

The following activities were also performed at the facility:

- Finishing of the SFPF building.
- Work on arrangement of the loading roof covering of the SFPF building with a pebble.
- Installation of steel structures  of the structural addition for balloons — arrangement of pavement, electrical works.
- Installation of sliding plates in CSM modules.
- Сompilation of executive and hand-over documents.
- Development of test programs for technological units and systems.
- Development of a training program for Chornobyl Nuclear Power Plant personnel.
- Work on commissioning and adjustment of the main process equipment and auxiliary systems.
- Individual tests of protective sliding doors SFP-SD-03 and SFP-SD-04 have been completed.
- Individual testing of 200-liter drums transportation system SWP-CR-222 (prem. IS102C7 / IS102C2) has been completed.
- Individual tests of the security windows SFP-SW-05 and SFP-SW-06 (premises 504/501) have been completed.
- Individual test of the indoor lighting system have been completed.
- Individual (independent) tests of FPS systems — central and back-up panels are underway.
- Individual tests of hot cells HCVS-S and HCVS-E ventilation system have been started.
- Individual tests of protective sliding doors SFP-SD-07 and SFP-SD-08 have been started.

The general Contractor of the project is Holtec. Works at the site are being performed by Holtec subcontractors: CDI, UTEM, UTB, ZEM, EPI, BEM, Kranservis, Konditsioner. In total 271 persons were engaged in the works. 4 units of lorry-loading, earth-moving and lifting machines were also used for fulfilling tasks at the site.

July 06, 2017
July 06, 2017
July 06, 2017
July 06, 2017
July 06, 2017
July 06, 2017

Select another date

Spent Fuel Processing Facility (SFPF):

- Development of work performance projects (technological sheets) for fire retention sealing of the penetrations.
- Unloading of the equipment and materials, equipment delivery into the installation area.
- Modification of the bridge crane SFP-CR-11 in the prem. 501 — installation of the electrical part is underway.
- Modification of the bridge crane SFP-CR-07 in the prem. 305 — installation of the electrical part completed.
- Modification of the gantry crane SFP-CR-08 in the prem. 305 — installation of the electrical part is underway.
- Electrical installation work on crane SWP-CR-206 in the prem. 403 and cables disconnection.
- Installation of electrical part — bridge crane MIS-CR-221 (prem 603).
- Installation of embedded parts for manual lifting tackles in SFPF building.
- Installation of main process equipment:
   * Installation of refrigeration supply system in the caisson 107c (connetion to CAV-RS-13, CAV-RS-14, CAV-RS-01).
   * Installation of pipelines of the technological blowdowns system in SFPF.
   * Installation and wiring work on SFPF equipment pinout.
   * Installation of a stationary high-pressure apparatus Kärcher is completed.
   * Modification of the mounting seat for the protective lid of the canister manipulation and transportation (CMTS) system — manufacturing of the components for modification, dismantling of the existing metal structures.
   * Installation of power and control cables of BNG equipment.
- Laying and pinout of BNG lighting cables in the SFPF premises.
- Works on the installation openings closing in prem. 603 — roof arrangement.

The following activities were also performed at the facility:

- Finishing of the SFPF building premises.
- Installation of fore-roof metal structures for pressure vessels.
- Compilation of executive and hand-over documentation.
- Development of testing programs for technological units and systems.
- Development of training programs for the Customer's personnel.
- Theoretical training for the personnel.
- Pre-commissioning work on the cutting facility, RMS system, chemically demineralized water system and ventilation system.
- Completion of individual tests of the lock for small-sized elements (LSE) SWP-TD-221.
- Individual testing of the hot cell filters CAV-FR-213 and lids of wells No. 1 & 3 (SFP-CG-212, SFP-CG-213).

The general Contractor of the project is Holtec. Works at the site are being performed by Holtec subcontractors: CDI, UTEM, UTB, ZEM, EPI, BEM, Kranservis, Konditsioner. In total 268 persons were engaged in the works. 4 units of lorry-loading, earth-moving and lifting machines were also used for fulfilling tasks at the site.

June 08, 2017
June 08, 2017
June 08, 2017
June 08, 2017
June 08, 2017
June 08, 2017

Select another date

Spent Fuel Processing Facility (SFPF):

- Unloading of the equipment and materials, equipment transfer into the installation area.
- The electrical installation work at the crane MIS-CR-240 in prem. IS102c9 are completed.
- Works on the bridge crane SFP-CR-01 modification in prem. 119 are underway in terms of the electrical part.
- Works on the bridge crane SFP-CR-07 modification in prem. 305 are underway in terms of the electrical part.
- Works on the gantry crane SFP-CR-08 modification in prem. 305 are underway in terms of the electrical part.
- Finishing (including the floor painting) in prem. 119 of the SFPF building is completed.
- Installation of main process equipment:
     * Installation of bottom frame of the caisson 107c.
     * Installation of FFS pipelines in prem. 505 A and 505 B of the SFPF building without the valve mounting has been completed (delivery is expected).
     * Re-tracing the fire-fighting pipeline inside the SFPF building.
     * Installation of power and control cables of BNG equipment.
- Works on the installation openings closing in prem. 603 — рarapet arrangement.

The following activities were also performed at the facility:

- Installation of the external fire escape stair P2 and the installation of the SG-5 ladders has been completed .
- Finishing of the SFPF building premises.
- Arrangement of the arms room in the checkpoint.
- Installation of fore-roof metal structures for pressure vessels.
- Extension of seismic restrains on CSM modules.
- Compilation of executive and hand-over documentation for the corresponding stages delivery according to the Contract.
- Development of testing programs for technological units and systems.
- Development of training programs for the Customer's personnel.
- Conducting of theoretical training for the Customer's personnel.
- Pre-commissioning work at the cutting facility, RMS system, chemically demineralized water system and ventilation system.
- Conducting of individual tests of the lock for small-sized elements (LSE).

The general Contractor of the project is Holtec. Works at the site are being performed by Holtec subcontractors: CDI, UTEM, UTB, ZEM, EPI, BEM, Kranservis, Konditsioner. In total 266 persons were engaged in the works. 3 units of lorry-loading, earth-moving and lifting machines were also used for fulfilling tasks at the site.

May 24, 2017
May 24, 2017
May 24, 2017
May 24, 2017
May 24, 2017
May 24, 2017

Select another date

Spent Fuel Processing Facility (SFPF):

- Unloading of the equipment and materials, equipment transfer into the installation area.
- Laying of cables of Radiation Control System system’s at rooms of the SFPF.
- Work on the modification of the bridge crane SFP-CR-01 in the room 119 — continue replacement of  electrical parts.
- Continue replacement of  electrical parts of Crane SFP-CR-220.
- Concreting of the protective hatch in room IS102C6 building.
- Works on installation of crane CR-220 in the prem. 504 of SFPF building.
- Completed restoring the cladding around the docking device to room 501.
- Installation of main process equipment:
     * Installation of bottom frame of the caisson 107c.
     * Installation of the main technological equipment — continue work on the electrical part of tableSFP-TT-210 in room 501.
     * Completed sealing of protective windows SFP-SW-03 room 111A / 307A and SWP-SW-02 room IS102C6 / IS102C5.
     * Completed reinstallation of the mechanism for opening the cover of the container CR-205.
     * Completed welding of plates of Drum Measurement Station SWP-GD-201.
     * Installation of equipment FGD in the room 505 A.
     * Installation of pipelines FGD in the rooms 505 A and 505 B.
     * Continued assembly of tanks.
     * Installation of power distributing nets and electric equipment BNG.
- Works on gas-aerosol control of RMS system in the SFPF building.
- Work on installation openings closure in the prem. 705 — completed roofing installation.
- Work on installation openings closure in the prem. S102c9 — construction of parapet.
- Work on installation openings closure in the prem. 603 — work by building walls.

The following activities were also performed at the facility:

- Restoration of the facade from the staircase C 3-1.
- Installation of lightning conductors of PPS.
- Construction of an armory room in the Gate House.
- Installation of embedded parts for Borescope.
- Completing of executive & acceptance documentation for the handover of relevant stages according to the Contract.
- The development of test programs of technological components and systems.
- Preparation of Employer’s personnel training programmers.
- Theoretical training of Employer’s personnel.
- Commissioning of the machine cutting, Radiation Control System.

The general Contractor of the project is Holtec. Works at the site are being performed by Holtec subcontractors: CDI, UTEM, UTB, ZEM, EPI, BEM, Kranservis, Konditsioner. In total 273 persons were engaged in the works. 4 units of lorry-loading, earth-moving and lifting machines were also used for fulfilling tasks at the site.

Select another date

Spent Fuel Processing Facility (SFPF):

- Unloading of the equipment and materials, equipment transfer into the installation area.
- Installation of cable products of АC and RMS in SFPF building premises.
- Modification of the bridge crane SFP-CR-11 in the premise 501/603 — replacement of mechanical part and electrical works are underway.
- Modification of the bridge crane SFP-CR-01 in prem. 119 — replacement of the electrical components.
- Installation of SFP-CR-240 crane beams in the prem. IS 102c9.
- Works on installation of crane CR-220 in the prem. 504 of SFPF building.
- Modification of the protective hatch in the prem. IS102C6 of SFPF building is compleated.
- Installation of main process equipment:
     * Installation of the main process equipment — installation of the docking device TK-8 in the design position.
     * Installation of the main process equipment — installation of the SFP-TT-210 table in prem. 501 (the mechanical part) is completed, the electrical equipment installation is underway.
     * Installation of FFS equipment in premise 505 A in SFPF building.
     * Installation of FFS pipelines in premise 505 A and 505B in SFPF building.
     * Continuation of the LRW tanks assembly.
     * Installation of power and control cables of BNG equipment.
- Works on gas-aerosol control of RMS system in the SFPF building.
- Work on installation openings closure in the prem. 705 — roof arrangement.
- Work on installation openings closure in the prem. S102c9 — roof casing.
- Work on installation openings closure in the prem. 603 — preparatory work for a wall building up.

The following activities were also performed at the facility:

- Installation of PPS lightning protectors.
- Arrangement of fore-roof for balloons - cutting of compensation joint in a floor slab.
- Compilation of executive and hand-over documentation for the corresponding stages delivery according to the Contract.
- Development of testing programs for technological units and systems.
- Development of training programs for the Employer’s personnel.
- Pre-commissioning work at the cutting facility, RMS system are underway.

The general Contractor of the project is Holtec. Works at the site are being performed by Holtec subcontractors: CDI, UTEM, UTB, ZEM, EPI, BEM, Kranservis, Konditsioner. In total 280 persons were engaged in the works. 4 units of lorry-loading, earth-moving and lifting machines were also used for fulfilling tasks at the site.

Page 3 of 9