Spent Fuel Processing Facility (SFPF):

- Mounting of cable routing structures within the SFPF building premises.
- Cable routing within the SFPF building premises.
- Installation of SFPF building lighting system – modification of cable routing at stair flights according to the fire safety requirements.
- Installation of self-leveling floors in premises.
- Installation of main process equipment:
     * Installation of Caisson 501A MIS-CE-213 (welding works).
     * Installation of SWP-TD-222 transport trolley rails into the design position (prem. IS102C6 / 403) was completed. Handed over for concreting.
     * Installation of security door SFP SD 210 (prem. 501А/IS102c2).
- Installation of internal protective grounding of SFPF building.
- Installation of radiation monitoring system — mounting of cable routing and earthquake-resistant supporting brackets for equipment, installation of devices into the SFPF premises.
- Installation of spill-over tanks.
- Preparatory works for installation of forced gas dehydration (FGD) pipelines.

Concrete storage modules (CSM):

- Installation of embedded items for the CSM temperature control was completed.
- Drilling of holes for boroscopes at the CSM modules (drilled 364 out of 464 holes).

The following activities were also performed at the facility:

- Development of work execution plans (process charts) for installation of equipment and systems.
- Construction of foundations for supports of physical protection system (PPS) video cameras was completed.
- Installation of racks (supports) for the PPS video cameras.
- Installation of tube protection blocks along the PPS perimeter.
- Installation of sensors along the PPS perimeter.
- Installation of PPS security gate near the Check Point (ChP).
- Repair of corrosion-resistant coating of PPS gate.
- Installation of portal monitors for dosimetry control system.
- Installation of access control system (turnstile) at the ChP gatehouse.
- Packing up a set of as-built documents and deliverables to deliver the relevant phases in accordance with the Contract.
- Development of testing programs for process units and systems.
- Development of training programs for the Client’s personnel.


The general Contractor of the project is Holtec. Works at the site are being performed by Holtec subcontractors: CDI, UTEM, UTB, ZEM, EPI, BEM, Kranservis, Konditsioner. In total 178 persons were engaged in the works, as well as 4 units of lorry and lifting machines.

Select another date

Spent Fuel Processing Facility (SFPF):

- Mounting of cable routing structures within the SFPF building premises.
- Cable routing within the SFPF building premises.
- Installation of SFPF building lighting system.
- Installation of self-leveling floors in the SFPF premises.
- Installation of pipelines for LRW active drain system.
- Installation of pipelines for nitrogen supply system.
- Installation of pipelines for argon supply system.
- Installation of pipelines for helium supply system.
- Installation of main process equipment:
     * Installation of lifting device system for ТП SFP-TD-211 was completed, the equipment is ready for individual tests.
     * Installation of air-tight door SFP SD 240 (prem. 501/503) was completed.
     * Installation of Caisson 501A MIS-CE-213 upper part.
     * Installation of transport trolley rails SWP-TD-222 into the design position (prem. IS102C6 / 403).
Installation of cold supply control system units – prem. 405 (connection to system CAVS-S-1).
Installation of internal protective grounding of SFPF building.
Installation of radiation monitoring system – drilling of holes for installation of devices, mounting of cable routing and earthquake-resistant supporting brackets for equipment.

Concrete storage modules (CSM):

- Installation of embedded items for the CSM temperature control was completed.
- Drilling of holes for boroscopes at the CSM modules (drilled 220 out of 464 holes).

The following activities were also performed at the facility:

- Laying of optic cable along the PPS perimeter.
- Construction of foundations for PPS video cameras supports.
- Concreting of joining along guard duty paths.
-  Development of work execution plans (process charts) for installation of equipment and systems.
- Packing up a set of as-built documents and deliverables to deliver the relevant phases in accordance with the Contract.
- Development of testing programs for process units and systems.
- Tests of process units and systems – hydraulic tests of chemically demineralized water system.
- Development of training programs for the Client’s personnel.

The general Contractor of the project is Holtec. Works at the site are being performed by Holtec subcontractors: CDI, UTEM, UTB, ZEM, EPI, BEM, Kranservis, Konditsioner. In total 193 persons were engaged in the works. 4 units of earth-moving machinery, lorry and lifting machines were used for implementing the tasks at the site.

September 29, 2016
September 29, 2016
September 29, 2016
September 29, 2016
September 29, 2016
September 29, 2016

Select another date

Spent Fuel Processing Facility (SFPF):

- Development of work execution plans (process charts) for installation of equipment and systems.
- Mounting of cable routing structures within the SFPF building premises.
- Cable routing within the SFPF building premises.
- Installation of SFPF building lighting system.
- Installation of self-leveling floors in the SFPF premises.
- Installation of pipelines for LRW active drain system.
- Installation of pipelines for nitrogen supply system.
- Installation of pipelines for argon supply system.
- Installation of pipelines for helium supply system.
- Gate MIS-LD-04 was installed in the prem. 114/119 of SFPF building.
- Gate MIS-LD-0 was installed in prem. 107 of SFPF building.
- Doors Tornado was installed in the SFPF building.
- Installation of pipelines (pipework) for compressors of compressed air system.
- Installation of main process equipment – welding works on a lifting device for SFP TP-TD-211.
- Installation of main process equipment – welding works on a slide holder supporting frame SFP-CR-220.
- Installation of main process equipment – installation of a sliding door leaf safety SFP-SD-212 in the prem. 111B/312 into the design position.
- Installation of main process equipment – a sliding safety door leaf SFP-SD-211 was installed in the prem. 307B/305 into the design position, installation of drive system and other small elements.
- Installation of main process equipment – preparation of an air-tight door frame SFP SD 240 for installation (prem. 501/503).
- Installation of main process equipment – installation of floor (Rased Floor) of Caisson 501A MIS-CE-213.
- Installation of main process equipment – installation of transport trolley rails SWP-TD-222 into the design position (prem. IS102C6 / 403).
- Installation of equipment – prem. 705, level 21,300. Ventilation systems CAVS-S-CAVS 1 and-2.
- Installation of air ducts, level 21,300. Ventilation systems CAVS-S-CAVS 1 and-2.
- Installation of cold supply control system units – prem. 405 (connection to system CAVS-S-1).
- Installation of internal protective grounding of SFPF building.
- Making a wider door opening of the prem. 132 of SFPF building.
- Brickwork of partition in the prem. 105/137 of SFPF building.
- Electrical installation works on a diesel power plant (DPP) – installation of control cables.Concrete storage modules (CSM):
- Installation of imbedded items for CSM temperature monitoring.

Concrete storage modules (CSM):

- Lightning protection (lighting-conductor) was installed at CSM modules.
- Installation of embedded items for the CSM temperature control.
- Drilling holes for boroscopes at CSM modules.

The following activities were also performed at the facility:

- Laying of optic cable from the protective tube unit (PTU) to Control Panel 1 along the PPS perimeter.
- Construction of foundations for PPS video camera supports.
- Concreting of joining along guard duty paths.
- Packing up a set of as-built documents and deliverables for delivery of the relevant phases in accordance with the Contract.
- Development of testing programs for process units and systems.
- Tests of process units and systems – hydraulic tests of chemically demineralized water system.

The general Сontractor of the project is Holtec Company. Works at the site are being performed by Holtec subcontractors: CDI, UTEM, UTB, ZEM, EPI, BEM, Kranservis, Konditsioner. 167 people at the total were engaged in work performance.  6 units of earth-moving machinery, lorry, and lifting machines were used for implementing tasks at the site.

September 08, 2016
September 08, 2016
September 08, 2016
September 08, 2016
September 08, 2016
September 08, 2016

Select another date

During the first half of August 18, 2016 at ISF-2 construction site the following works were carried out:

Spent Fuel Processing Facility (SFPF):
- Development of work execution plans (flow diagrams) for installation of equipment and systems;
- Mounting of cable routing structures within SFPF building premises;
- Cable routing within SFPF building premises;
- Installation of SFPF building lighting system;
- Installation of self-leveling floors in SFPF premises;
- Laying of active drainage pipes of LRW system;
- Pipe laying of RAW level monitoring tanks;
- Installation of gates MIS-LD-04 in premise 114/119 of SFPF building;
- Installation of gates MIS-LD-0 in premise 107 of SFPF building;
- Installation of doors Tornado in SFPF building;
- Installation of pipelines (pipework) for compressors of compressed air system;
- Corrosion protection and pipe covering of cold supply system;
- Installation of equipment for ventilation systems;
- Installation of main process equipment – welding works on lifting device for SFP-TD-211S;
- Electrical fitting works relating to DPP (cabinet wiring, power cabling).

Concrete storage modules (CSM):
- Installation of imbedded items for CSM temperature monitoring.

The following activities were also performed at the facility:
- Twisted pair cabling from transducer locations to physical protection system (PPS) cabinets;
- Routing of optic cable along the perimeter of PPS;
- Reinstallation of PPS security gates – construction of new foundations from the direction of Gate House;
- Development of testing programs for process units and systems.

The general Сontractor of the project is Holtec Company. Works at the site are being performed by Holtec subcontractors: CDI, UTEM, UTB, ZEM, EPI, BEM, Kranservis, Konditsioner. 179 people at the total were engaged in work performance.  6 units of earth-moving machinery, lorry, and lifting machines were used for implementing tasks at the site.

Select another date

During the first half of August 11, 2016 at ISF-2 construction site the following works were carried out:

Spent Fuel Processing Facility (SFPF):
- Mounting of cable routing structures within SFPF building premises;
- Cable routing within SFPF building premises;
- Installation of SFPF building lighting system;
- Installation of self-leveling floors in SFPF premises;
- Laying of active drainage pipes of LRW system;
- Pipe laying of RAW level monitoring tanks;
- Installation of gates MIS-LD-04 in premise 114/119 of SFPF building;
- Installation of gates MIS-LD-0 in premise 107 of SFPF building;
- Installation of doors Tornado in SFPF building;
- Installation of pipelines (pipework) for compressors of compressed air system;
- Corrosion protection and pipe covering of cold supply system;
- Start of ventilation system equipment installation Renewal of installation of process equipment – welding activities on lifting device for SFP-TD-211;
- Electrical fitting works relating to DPP (cabinet wiring, power cabling).

Concrete storage modules (CSM):
- Installation of imbedded items for CSM temperature monitoring.

The following activities were also performed at the facility:
- Twisted pair cabling from transducer locations to physical protection system (PPS) cabinets;
- Routing of optic cable along the perimeter of PPS;
- Reinstallation of PPS security gates – construction of new foundations from the direction of Gate House;
- Development of testing programs for process units and systems.

The general Сontractor of the project is Holtec Company. Works at the site are being performed by Holtec subcontractors: CDI, UTEM, UTB, ZEM, EPI, BEM, Kranservis, Konditsioner. 186 people at the total were engaged in work performance.  6 units of earth-moving machinery, lorry, and lifting machines were used for implementing tasks at the site.