In late March and early April at ISF-2 construction site the following works were carried out:

Spent Fuel Processing Facility (SFPF):
- Installation of air ducts for PPS CAVS-3 air supply ventilation system at elev. +11.700;
- Installation of cable routes in premises of the facility;
- Installation of lighting system;
- Finishing of the premises;
- Installation of the cooling system pipelines;
- Installation of pipelines for LRW treatment system special drainage;
- Installation of compressed air system pipelines;
- Installation of pipelines for chemically demineralized water system.

CSM:
- Installation of lightning protection on the modules.

Gate house:
- Electric installation works.

The following works were also performed:
- Laying of power distribution network from automatic throw-over circuit-breaker cabinets to consumers of security equipment;
- Reinstallation of PPS safety gates;
- Installation of ARMS station equipment.

The general Сontractor of the project is Holtec Company. Works at the site are being performed by Holtec subcontractors: CDI, UTEM, UTB, ZEM, EPI, BEM, Kranservis, Konditsioner. 205 people at the total were engaged in work performance. 9 units of earth-moving machinery, lorry, and lifting machines were also used for implementing tasks at the site.

May 19, 2016
May 19, 2016
May 19, 2016
May 19, 2016
May 19, 2016
May 19, 2016
May 19, 2016
May 19, 2016
May 19, 2016

Select another date

In late March and early April at ISF-2 construction site the following works were carried out:

Spent Fuel Processing Facility (SFPF):

- Air ducts installation of CCA ventilation system (intake) of non-attended and periodically attended CAVS-S-1 rooms at elev. +17.000;

- Air ducts installation of CCA ventilation system (exhaust) of non-attended and periodically attended CAVS-E-1 rooms at elev. +17.000;

- Installation of main cable routes structures at elev. +11.700 of rooms 502, 504;

- Installation of cable routes structures at elev. +5.600 of rooms 303, 304;

- Installation of lighting system at elev. +5.600;

- Installation of lighting system at elev. +11.700;

- Installation of lighting system at elev. +0.000;

- Installation of the cooling system pipelines;

- SFPS facades installation works, i.e. plinth installation;

- Finishing of the premises;

- Installation of LRW treatment system equipment – corrective actions on drainage water tanks installation in rooms -103, -104;

- Installation of pipelines for LRW treatment system special drainage;

- Installation of compressed air system pipelines;

- Installation of chemically demineralized water system pipelines.

 

CSM:

- Installation of parts of pos. 5 and pos. 6; 

- Installation of cable routes structures.

 

Gate house:

- Electric installation works.

 

Additional works:

- Laying of crushed stone base in PPS protected zone; 

- Placement of security patrol route slabs; 

- ISF site improvement works; 

- Construction of Road 3.

 

The general Сontractor of the project is Holtec Company. Works at the site are performed by Holtec subcontractors: CDI, UTEM, UTB, ZEM, EPI, BEM, Kranservis, Konditsioner. 256 people at the total were engaged in work performance. 12 units of earth-moving machinery, lorry, and lifting machines were also used for implementing tasks at the site.

April 08, 2016
April 08, 2016
April 08, 2016
April 08, 2016
April 08, 2016
April 08, 2016

Select another date

During the second half of January at ISF-2 construction site the following works were carried out:

Spent Fuel Processing Facility (SFPF):
- Installation of embedded plates for equipment in room 501;
- Mounting of st.steel cladding sheets on walls in room 501;
- Mounting of st.steel cladding sheets on the floor in room 501;
- Installation of embedded parts for crane MIS-CR-221 (elev. +28.140) in room 603 was completed;
- Air ducts installation of CCA ventilation system (intake) of attended CAVS-S-2 rooms at elev. +8.650 was completed;
- Air ducts installation of CCA ventilation system (exhaust) of attended CAVS-E-2 rooms at elev. +8.650;
- Air ducts installation of CCA ventilation system (intake) of non-attended and periodically attended CAVS-S-1 rooms at elev. +11.700;
- Air ducts installation of CCA ventilation system (exhaust) of non-attended and periodically attended CAVS-E-1 rooms at elev. +11.700;
- Installation of main cable routes structures at elev. +0.000 of rooms 102-103 was completed;
- Installation of main cable routes structures at elev. +0.000 of room 107, electrical room and N.C.A. Ladder;
- Installation of main cable routes structures at elev. +2.800/3.400 of utility and attended rooms 201-210 was completed;
- Installation of cable routes structures at elev. +2.800/3.400 of rooms 214-215;
- Installation of cable routes structures at elev. +5.600 of changing facility rooms 302, 310, room 308, 308A;
- Painting (fire-retardant treatment) of the floor slab reinforcement structures metal beams at elev. +21.300 was completed;
- Facades installation works;
- Finish coating at elev. 5.600, 1 layer.

Repair and finishing of Gate house premises.

Installation of parts of pos. 5 and pos. 6 on concrete storage modules.

Laying of crushed stones in PPS protected zone.

Arrangement of security patrol route slabs.

Preparatory works on public services and utilities.

Installation of PPS gates (near Gate house).

Post-completion and turn-over documentation selection for delivery of works of relevant stages according to the Contract.

Development of testing programs for process units and systems.

The general Сontractor of the project is Holtec Company. Works at the site are performed by Holtec subcontractors: CDI, UTEM, UTB, ZEM, EPI, BEM, Konditsioner. 227 people at the total were engaged in work performance. 10 units of loading, excavation and lifting equipment were also used for implementing tasks at the site.

 

Select another date

During the second half of January at ISF-2 construction site the following works were carried out:

Spent Fuel Processing Facility (SFPF) :
- Installation of frames for protective windows in room 501 was completed;
- Welding of embedded elements of penetrations for slave manipulators in room 501 was completed;
- Installation of embedded plates for equipment in room 501;
- Mounting of st.steel cladding sheets on walls in room 501;
- Mounting of st.steel cladding sheets on the floor in room 501;
- Construction of F1-xx foundations (axes 2С-2D; 205-206) in room 501 was completed;
- Installation of embedded parts for crane MIS-CR-221 (elev. +28.140) in room 603;
- Installation of crane embedded parts in room IS102C9;
- Erection of crane structural steelwork in room 505A was completed;
- Inspection of the existing fire line fixtures;
- Insulation of hot water supply system pipelines T3, T4 and drinking water pipeline B1 was completed;
- Air ducts installation of CCA ventilation system (intake) of non-attended and periodically attended CAVS-S-1 rooms at elev. +5.600;
- Air ducts installation of CCA ventilation system (exhaust) of non-attended and periodically attended CAVS-E-1 rooms at elev. +5.600;
- Mounting of ventilation systems fire retardant valves at elev. +5.600;
- Installation of chiller into the design position was completed;
- Installation of external fire ladders;
- Installation of lightning protection of the building;
- Facades installation works.

Repair and finishing of Gate house premises;

Installation of equipment (pumps, filters) and pipelines of the sewage treatment facility was completed;

Electric installation works (installation of electrical cabinets, sensors, floats, termination, and grounding) of the sewage treatment facility were completed;

Hydraulic testing of the sewage treatment facility pipelines was carried out;

Hydraulic testing of K1, K15 sewage systems, B1, B2, T3 and T4 pipelines systems was carried out.

Installation of parts of position 5 and position 6 on concrete storage modules. 

The general Сontractor of the project is Holtec Company. Works at the site are performed by Holtec subcontractors: CDI, UTEM, UTB, ZEM, EPI, BEM, Konditsioner. 196 people at the total were engaged in work performance. 6 units of excavation and lifting equipment were also used for implementing tasks at the site.

04 лютого 2016 року
04 лютого 2016 року
04 лютого 2016 року
04 лютого 2016 року
04 лютого 2016 року
04 лютого 2016 року

Select another date

During the first half of January at ISF-2 construction site the following works were carried out:

Spent Fuel Processing Facility (SFPF):
- Painting of walls in rooms at elev. +0.000; +2.800; +17.000; +21.300;
- Arrangement of accessories to install frames for protective windows in room 501;
- Welding of embedded elements of penetrations for slave manipulators in room 501;
- Installation of embedded plates for equipment in room 501;
- Construction of F1-xx foundations (axes 2С-2D; 205-206) in room 501;
- Installation of embedded parts for crane MIS-CR-221 (elev. +28.140) in room 603;
- Installation of crane embedded parts in room IS102C9;
- Erection of crane structural steelwork in room 505A;
- Installation and concreting of penetrations elements at elev. +8.500 (3 pcs.) and at elev. +11.700 (1 pcs.) was completed;
- Inspection of the existing fire line fixtures;
- Air ducts installation of CCA ventilation system (intake) of non-attended and periodically attended CAVS-S-1 rooms at elev. +5.600;
- Air ducts installation of CCA ventilation system (exhaust) of non-attended and periodically attended CAVS-E-1 rooms at elev. +5.600;
- Mounting of ventilation systems fire retardant valves at elev. +5.600;
- Installation of external fire ladders;
- Installation of lightning protection of the building;
- Facades installation works.

Gate house:
- Repair and finishing of premises;
- Facades installation works were completed.

Installation of equipment (pumps, filters) and pipelines of the sewage treatment facility.

Post-completion and turn-over documentation selection for delivery of works of relevant stages according to the Contract.

Development of testing programs for process units and systems.

The general Сontractor of the project is Holtec Company. Works at the site are performed by Holtec subcontractors: CDI, UTEM, UTB, ZEM, EPI, BEM, Konditsioner. 170 people at the total were engaged in work performance. 6 units of excavation and lifting equipment were also used for implementing tasks at the site.