ISF-2 construction progress as of July 06, 2017

Select another date

Spent Fuel Processing Facility (SFPF):

- Project works performance development (technological layouts) for fire protection closure of penetrations.
- Unloading of the equipment and materials, equipment transfer into the installation area.
- Works on the bridge crane SFP-CR-11 modification in prem. 501 are underway in terms of the electrical part.
- Works on the bridge crane SFP-CR-01 modification in prem. 119 are underway in terms of the electrical part.
- Works on the gantry crane SFP-CR-08 modification in prem. 305 are underway in terms of software and preparation for testing.
- Bridge crane SWP-CR-206 in prem. 403 adjustment and preparation for testing.
- Installation of concrete insert for arm hoist.
- Installation of main process equipment:
   * Electrical and installation work to install automation boards and FFS equipment sensors.
- Installation of BNG equipment power cables has been completed.
- BNG lighting cable laying and termination has been completed.

The following activities were also performed at the facility:

- Finishing of the SFPF building.
- Work on arrangement of the loading roof covering of the SFPF building with a pebble.
- Installation of steel structures  of the structural addition for balloons — arrangement of pavement, electrical works.
- Installation of sliding plates in CSM modules.
- Сompilation of executive and hand-over documents.
- Development of test programs for technological units and systems.
- Development of a training program for Chornobyl Nuclear Power Plant personnel.
- Work on commissioning and adjustment of the main process equipment and auxiliary systems.
- Individual tests of protective sliding doors SFP-SD-03 and SFP-SD-04 have been completed.
- Individual testing of 200-liter drums transportation system SWP-CR-222 (prem. IS102C7 / IS102C2) has been completed.
- Individual tests of the security windows SFP-SW-05 and SFP-SW-06 (premises 504/501) have been completed.
- Individual test of the indoor lighting system have been completed.
- Individual (independent) tests of FPS systems — central and back-up panels are underway.
- Individual tests of hot cells HCVS-S and HCVS-E ventilation system have been started.
- Individual tests of protective sliding doors SFP-SD-07 and SFP-SD-08 have been started.

The general Contractor of the project is Holtec. Works at the site are being performed by Holtec subcontractors: CDI, UTEM, UTB, ZEM, EPI, BEM, Kranservis, Konditsioner. In total 271 persons were engaged in the works. 4 units of lorry-loading, earth-moving and lifting machines were also used for fulfilling tasks at the site.