Spent Fuel Processing Facility (SFPF):

- Development of work execution plans (flow sheets) for installation of equipment and systems.
- Installation of Technological Process Monitoring and Control System (TP MCS) cabinets.
- Mounting of cable routing structures for PPS, AMS and RMS
- Cable routing.
- Installation of main process equipment:
     * Works on modification of shielding door SFP-SD-08 in prem. 403/IS 102 C6.
     * Assembling of racks for 200-l drums.
     * Pit covers No.1 and No.3 SFP-XP-210/211, prem. 501 were installed
- Installation of extra embedded items for the docking device.
- Preparatory works for installation of the docking device TK-8 cup.
- Electrical installation works on gateways of small-sized elements, holder slide.
- Installation of control cabinets for ventilation system fire protection valves.
- Mounting of ducts, cable laying, connection of control cabinets for ventilation system fire protection valves.
- Installation of FGD pipelines.
- Fire protection of ventilation system air ducts.
- Filling of shielding door SFP-SD-02 with lead pellets, prem. 109А/111А.
- Works on RMS gas-aerosol monitoring systems.

The following activities were also performed at the facility:

- Soldering of optic cable from ZVSB to Control Panel 1 at the checkpoint.
- Completing of as-built documents and deliverables for handing-over the relevant stages in accordance with the Contract.
- Development of testing programs for process units and systems and training programs for the Client’s personnel.

The general Contractor of the project is Holtec. Works at the site are being performed by Holtec subcontractors: CDI, UTEM, UTB, ZEM, EPI, BEM, Kranservis, Konditsioner. In total 200 persons were engaged in the works. 5 units of lorry-loading, earth-moving and lifting machines were also used for fulfilling tasks at the site.

Select another date

Spent Fuel Processing Facility (SFPF):

- Installation of Technological Process Monitoring and Control System cabinets in the SFPF building — installation of AWS.
- Mounting of cable routing structures for PPS, AMS and RMS within the SFPF building premises.
- Installation of lighting system within prem.  -101, -103, -104 (level -3,000) at the SFPF
- Installation of main process equipment:
     * Works on modification of a protection hatch (ceiling gate) of prem. IS 102 C6.
     * Assembling of racks for 200-l drums.
     * Preparatory works for installation of transport container trolleys (prem. 114) SFP-TD-05; SFP-TD-06.
     * Installation of pit covers No. 1 and No. 3 SFP-XP-210/211, prem. 501.
- Drilling of holes at flooring 501/107 (installation of additional embedded items for a docking device).
- Electrical installation works on gateway of small-sized elements, holder slide.

The following activities were also performed at the facility:

- Installation of control cabinets for ventilation system fire protection valves.
- Mounting of ducts, cable laying, connection of control cabinets for ventilation system fire protection valves.
- Installation of FGD pipelines.
- Fire protection of ventilation system air ducts.
- Soldering of optic cable from ZVSB to Control Panel 1 at the checkpoint.
- Completing of as-built documents and deliverables for handing-over the relevant stages in accordance with the Contract.
- Development of testing programs for process units and systems and training programs for the Client’s personnel.

The general Contractor of the project is Holtec. Works at the site are being performed by Holtec subcontractors: CDI, UTEM, UTB, ZEM, EPI, BEM, Kranservis, Konditsioner. In total 193 persons were engaged in the works. 5 units of lorry-loading, earth-moving and lifting machines were also used for fulfilling tasks at the site.

December 21, 2016
December 21, 2016
December 21, 2016
December 21, 2016
December 21, 2016
December 21, 2016

 

Select another date

Spent Fuel Processing Facility (SFPF):

- Installation of Technological Process Monitoring and Control System (TP MCS) cabinets.
- Mounting of cable routing structures within the SFPF building premises.
- Cable routing within the SFPF building premises.
- Installation of lighting system of SFPF building.
- Installation of supports for lighting and video surveillance systems in “hot cell”, prem. 501.
- Delivery of main process equipment to the installation area – master-slave manipulators, double lid system for handling of 200-l drums, drum transportation systems, suction devices.
- Installation of main process equipment:
     * Installation of shielding door SFP SD 211 (prem. 307).
     * Gateways of small-sized elements SFP TD 220/221 were installed (welding works) into the design position (501/504).
     * Caisson MIS-CE-213 was installed (welding works) in prem. 501.
- Iinstallation of shielding windows SFP-SW-05, SFP-SW-06 and SFP-SW-07 in prem. 501.
- Refurbishment works for the existing equipment:
     * Shielding door SD-04 was painted in prem. 503/501.
     * Preparatory works for Canister Transport Handling System (CHTS).
- Installation of control cabinets for ventilation system fire protection valves.
- I
nstallation of internal protective grounding of SFPF building.
- I
nstallation of video cameras at the building.

 

The following activities were also performed at the facility:

- Installation of supports for video cameras at the SFPF building.
- Installation of PPS security gate near the CSM — the gate leaf was installed into its design position.
- Works on construction of foundations for the PPS lightning protection stands.
- Soldering of optic cable from ZVSB to Control Panel 1 in the checkpoint prem. 203 and along the PPS perimeter
- Completing of as-built documents and deliverables for handing-over the relevant stages in accordance with the Contract.
- Development of testing programs for process units and systems and training programs for the Client’s personnel.
- Individual tests of FT lifting device SFP-TD-211 were completed.

The General Contractor of the project is Holtec. Works at the site are performed by Holtec subcontractors: CDI, UTEM, UTB, ZEM, EPI, BEM, “Kranservis”, “Konditsioner”. In total 198 persons were engaged in the works, as well as 7 units of lorry-loading, earth-moving and lifting machines.

 

Select another date

Spent Fuel Processing Facility (SFPF):

- Maintenance and cleanup of the construction site, cleaning and keeping of workplaces in accordance with the labour protection requirements.
- Development of work execution plans (flow sheets) for installation of equipment and systems.
- Installation of Technological Process Monitoring and Control System (TP MCS) cabinets.
- Mounting of cable routing structures within the SFPF building premises.
- Cable routing within the SFPF building premises.
- Installation of lighting system of SFPF building.
- Installation of main process equipment:
     * Installation of shielding door SFP SD 210 (prem. 501А/IS102c2).
     * Installation of shielding door SFP SD 211 (prem. 307).
     * Installation of SFA cutting machine SFP CS 205 into its design position.
     * Double lid system SFP CG 210 was installed into its design position (501/111A).
     * Gateways of small-sized elements were installed into the design position SFP TD 220/221 (501/504).
- Installation of shielding windows SFP-SW-05; SFP-SW-06 and SFP-SW-07 in prem. 501.
- Installation of control cabinets for ventilation system fire protection valves.
- Installation of internal protective grounding of SFPF building.
- S
tands for video cameras were installed along the PPS perimeter.

 

The following activities were also performed at the facility:

- Installation of supports for video cameras at the SFPF building.
- Installation of PPS security gate near the CSM — the gate leaf was installed into its design position.
- Earth works on construction of foundations for the PPS lightning protection stands.
- Completing of as-built documents and deliverables for handing-over the relevant stages in accordance with the Contract.
- Development of testing programs for process units and systems and training programs for the Client’s personnel.
- Individual tests of main equipment – lifting device for fuel tubes (FT).

The General Contractor of the project is Holtec. Works at the site are performed by Holtec subcontractors: CDI, UTEM, UTB, ZEM, EPI, BEM, “Kranservis”, “Konditsioner”. In total 198 persons were engaged in the works, as well as 6 units of lorry-loading, earth-moving and lifting machines.

Select another date

Spent Fuel Processing Facility (SFPF):

- Mounting of cable routing structures within the SFPF building premises.
- Cable routing within premises.
- Installation of SFPF building lighting system — modification of cable routing at stair flights according to the fire safety requirements.
- Installation of self-leveling floors in premises.
- Installation of main process equipment:
     * Installation of security door SFP SD 210 (prem. 501А/IS102c2).
     * Installation of security door SFP SD 212 (prem. 312B).
     * Installation of security door SFP SD 211 (prem. 307).
- Preparatory works for installation of shielding windows.
- Installation of internal protective grounding of SFPF building.
- Installation of radiation monitoring system — mounting of radiological monitors in the SFPF premises.

Concrete storage modules (CSM):

- Drilling of 464 holes for borescopes at the modules complete.
- Installation of embedded items for borescopes at the modules.

The following activities were also performed at the facility:

- Development of work execution plans (process charts) for installation of equipment and systems.
- Installation of tube protection blocks along the physical protection system (PPS) perimeter complete.
- Installation of sensors along the PPS perimeter.
- Installation of supports for the PPS video cameras at the SFPF building.
- Installation of PPS security gate near the Check Point (ChP) — installation of gate leaf into its design position.
- Installation of PPS security gate near the SFPF — installation of gate leaf into its design position.
- Repair of corrosion-resistant coating of PPS gate.
- Installation of portal monitors for dosimetry control system.
- Installation of access control system (turnstile) at the ChP gatehouse.
- Packing up a set of as-built documents and deliverables to deliver the relevant phases in accordance with the Contract.
- Development of testing programs for process units and systems.
- Development of training programs for the Client’s personnel.

The general Contractor of the project is Holtec. Works at the site are being performed by Holtec subcontractors: CDI, UTEM, UTB, ZEM, EPI, BEM, Kranservis, Konditsioner. In total 182 persons were engaged in the works, as well as 5 units of earth-moving, lorry and lifting machines.