ISF-2 construction progress as of November 15, 2017

Select another date

Spent Fuel Processing Facility (SFPF):

- Receipt  inspection of structures for mounting the IAEA cabinet in 107с.
- Finished backfilling of lead shot protective door SFP-SD-06.
- Marking of technological pipelines in the building of SFPF.

The following activities were also performed at the facility:

- Regular works on the construction site arrangement.
- Completing of executive & acceptance documentation according to the Contract.
- Development of test programs for technological units and systems.
- Development of a training program for Chornobyl Nuclear Power Plant personnel.
- Commissioning on main technological equipment and auxiliary.
- Finished Individual tests of the  ventilation and air conditioning system of the Gate House.
- Functional tests of crane SFP-CR-01 room. 119.
- Individual (Autonomous) tests of PCMS DWC Handling System, FT Handling System, SRW Management System.
- Individual tests of the security door SWP-SD-01.
- Finished Individual tests of the autonomous power supply system;
- Integrated testing of the Sewerage and Sewage Systems (Removing Remarks);
- Individual tests of the Cutting Machine SFA SFP-CS-205;
- Individual tests of the Removable Platforms SFP-PL-01;
- Finished Individual and Integrated testing of ISF-2 Fire Alarm and Personnel Evacuation Control System;
- Finished Individual and complex testing of the fire alarm warning system of Gate House;
- Finished Tests in accordance with Ukrainian Labor Service hoist MIS-CR-250, MIS-CR-15, KLE500GCL
- Individual Test of Canister Handling and Transport System CHT TD 02
- Functional tests of the crane SWP-CR-206 in room 403.

The general Contractor of the project is Holtec. Works at the site are being performed by Holtec subcontractors: CDI, UTEM, UTB, ZEM, EPI, BEM, Kranservis, Konditsioner. In total 189 persons were engaged in the works. 1 unit of lorry-loading, earth-moving and lifting machines were also used for fulfilling tasks at the site.