During the first half of August 04, 2016 at ISF-2 construction site the following works were carried out:

Spent Fuel Processing Facility (SFPF):
- Mounting of cable routing structures within SFPF building premises;
- Cable routing within SFPF building premises;
- Installation of SFPF building lighting system;
- Installation of self-leveling floors in SFPF premises;
- Laying of active drainage pipes of LRW system;
- Pipe laying of RAW level monitoring tanks;
- Installation of gates MIS-LD-04 in premise 114/119 of SFPF building;
- Installation of gates MIS-LD-0 in premise 107 of SFPF building;
- Installation of doors Tornado in SFPF building;
- Mounting of utility air compressors;
- Corrosion protection and pipe covering of cold supply system;
- Installation of diesel generators in the designed position;
- Electrical fitting works relating to DPP (cabinet wiring, power cabling).

Concrete storage modules (CSM):
- Installation of imbedded items for CSM temperature monitoring.

The following activities were also performed at the facility:
- Laying of distribution mains from automatic load transfer cabinets to technical security equipment consumers;
- Twisted pair cabling from transducer locations to physical protection system (PPS) cabinets;
- Remounting of physical protection system (PPS) safety gates – installation of new gate foundations from Check Point side.

The general Сontractor of the project is Holtec Company. Works at the site are being performed by Holtec subcontractors: CDI, UTEM, UTB, ZEM, EPI, BEM, Kranservis, Konditsioner. 186 people at the total were engaged in work performance.  6 units of earth-moving machinery, lorry, and lifting machines were used for implementing tasks at the site.

August 04, 2016
August 04, 2016
August 04, 2016
August 04, 2016
August 04, 2016
August 04, 2016

Select another date

During the first half of July 21, 2016 at ISF-2 construction site the following works were carried out:

Spent Fuel Processing Facility (SFPF):
- Cable routing within building premises;
- Installation of self-leveling floors;
- Installation of lighting system;
- Laying of active drainage pipes of LRW system;
- Pipe laying of RAW level monitoring tanks;
- Installation of basic process equipment – installation of sliding holder frame SFP CR 220 in the designed position is completed in premise 501 of SFPF building. Following the acceptance, the BNG representatives will restore mounting/installation activities;
- Installation of gates MIS-LD-04 in premise 114;
- Preparatory works for mounting of ventilation system equipment.

Concrete storage modules (CSM):

- Installation of lightning protection on modules;
- Installation of imbedded items for CSM temperature monitoring;
- Mounting of ventilation grills is completed.

The following activities were also performed at the facility:

- Laying of distribution mains from automatic load transfer cabinets to technical security equipment consumers;
- Remounting of physical protection system (PPS) safety gates – installation of new gate foundations from Check Point side;
- Twisted pair cabling from transducer locations to physical protection system (PPS) cabinets.

The general Сontractor of the project is Holtec Company. Works at the site are being performed by Holtec subcontractors: CDI, UTEM, UTB, ZEM, EPI, BEM, Kranservis, Konditsioner. 196 people at the total were engaged in work performance.  6 units of earth-moving machinery, lorry, and lifting machines were used for implementing tasks at the site.

July 21, 2016
July 21, 2016
July 21, 2016
July 21, 2016
July 21, 2016
July 21, 2016

Select another date

During the first half of July 07, 2016 at ISF-2 construction site the following works were carried out:

Spent Fuel Processing Facility (SFPF):
- Installation of cable routes in premises of the facility;
- Laying of cable products in premises of the facility;
- Arrangement of self-levelling floors;
- Arrangement of a new premise 410;
- Preparation of cold supply system pipelines for hydrotesting;
- Installation of pipelines for LRW special sewage system;
- Preparation of compressed air system pipelines for pneumatic testing;
- Installation of pipelines for chemically demineralized water system;
- Installation of pipelines for monitoring tanks;
- Installation of main process equipment – lifting device SFP-TD-211;
- Installation of gate MIS-LD-04 of premise 114.

Concrete storage modules (CSM):
-Installation of lightning protection on the modules;
- Installation of embedded items for CSMs temperature control;
- Installation of ventilation grids.

The following activities were also performed at the facility:
- Laying of power distribution network from automatic throw-over circuit-breaker cabinets to consumers of security equipment;
- Reinstallation of PPS security gates – construction of new foundations from the direction of Check Point.

The general Сontractor of the project is Holtec Company. Works at the site are being performed by Holtec subcontractors: CDI, UTEM, UTB, ZEM, EPI, BEM, Kranservis, Konditsioner. 219 people at the total were engaged in work performance.  6 units of earth-moving machinery, lorry, and lifting machines were used for implementing tasks at the site.

07 июля 2016 года
07 июля 2016 года
07 июля 2016 года
07 июля 2016 года
07 июля 2016 года
07 июля 2016 года

Select another date

During the first half of June 2016 at ISF-2 construction site the following works were carried out:

Spent Fuel Processing Facility (SFPF):

- Installation of air ducts for PPS CAVS-3 air supply ventilation system at elev. +11.700;
- Installation of cable routes in premises of the facility;
- Installation of lighting system;
- Finishing of the premises;
- Installation of the cooling system pipelines;
- Installation of pipelines for LRW treatment system special drainage;
- Installation of compressed air system pipelines;
- Installation of pipelines for chemically demineralized water system;

CSM:

- Installation of lightning protection on the modules.

Gate house:

- Electric installation works.

The following works were also performed:

- Laying of power distribution network from automatic throw-over circuit-breaker cabinets to consumers of security equipment;
- Reinstallation of PPS safety gates;
- Installation of ARMS station equipment.

The general Сontractor of the project is Holtec Company. Works at the site are being performed by Holtec subcontractors: CDI, UTEM, UTB, ZEM, EPI, BEM, Kranservis, Konditsioner. 179 people at the total were engaged in work performance.  6 units of earth-moving machinery, lorry, and lifting machines were used for implementing tasks at the site.

June 16, 2016
June 16, 2016
June 16, 2016
June 16, 2016
June 16, 2016
June 16, 2016

Select another date

 

During the period under review, at ISF-2 construction site the following works were carried out:

Spent Fuel Processing Facility (SFPF):

- Installation of cable routes in premises of the facility;
- Installation of lighting system;
- Finishing of the premises;
- Installation of the cooling system pipelines;
- Installation of pipelines for LRW treatment system special drainage;
- Installation of compressed air system pipelines;
- Installation of pipelines for chemically demineralized water system;
- Installation of pumps of auxiliary process systems;
- Installation of pipelines for RAW level monitoring tanks.

CSM:

- Installation of security lighting system;
- Installation of vent grilles;
- Installation of lightning protection on the modules.

Gate house:

- Electric installation works.

The following works were also performed:

- Laying of power distribution network from automatic throw-over circuit-breaker cabinets to consumers of security equipment;
- Reinstallation of PPS safety gates;
- Installation of ARMS station equipment.

The general Сontractor of the project is Holtec Company. Works at the site are being performed by Holtec subcontractors: CDI, UTEM, UTB, ZEM, EPI, BEM, Kranservis, Konditsioner. 181 people at the total were engaged in work performance.  6 units of earth-moving machinery, lorry, and lifting machines were used for implementing tasks at the site.