ISF-2 construction progress as of May 24, 2017

Select another date

Spent Fuel Processing Facility (SFPF):

- Unloading of the equipment and materials, equipment transfer into the installation area.
- The electrical installation work at the crane MIS-CR-240 in prem. IS102c9 are completed.
- Works on the bridge crane SFP-CR-01 modification in prem. 119 are underway in terms of the electrical part.
- Works on the bridge crane SFP-CR-07 modification in prem. 305 are underway in terms of the electrical part.
- Works on the gantry crane SFP-CR-08 modification in prem. 305 are underway in terms of the electrical part.
- Finishing (including the floor painting) in prem. 119 of the SFPF building is completed.
- Installation of main process equipment:
     * Installation of bottom frame of the caisson 107c.
     * Installation of FFS pipelines in prem. 505 A and 505 B of the SFPF building without the valve mounting has been completed (delivery is expected).
     * Re-tracing the fire-fighting pipeline inside the SFPF building.
     * Installation of power and control cables of BNG equipment.
- Works on the installation openings closing in prem. 603 — рarapet arrangement.

The following activities were also performed at the facility:

- Installation of the external fire escape stair P2 and the installation of the SG-5 ladders has been completed .
- Finishing of the SFPF building premises.
- Arrangement of the arms room in the checkpoint.
- Installation of fore-roof metal structures for pressure vessels.
- Extension of seismic restrains on CSM modules.
- Compilation of executive and hand-over documentation for the corresponding stages delivery according to the Contract.
- Development of testing programs for technological units and systems.
- Development of training programs for the Customer's personnel.
- Conducting of theoretical training for the Customer's personnel.
- Pre-commissioning work at the cutting facility, RMS system, chemically demineralized water system and ventilation system.
- Conducting of individual tests of the lock for small-sized elements (LSE).

The general Contractor of the project is Holtec. Works at the site are being performed by Holtec subcontractors: CDI, UTEM, UTB, ZEM, EPI, BEM, Kranservis, Konditsioner. In total 266 persons were engaged in the works. 3 units of lorry-loading, earth-moving and lifting machines were also used for fulfilling tasks at the site.