During the first half of December at ISF-2 construction site the following works were carried out:

Spent Fuel Processing Facility (SFPF):
- Startup finishing operations (plastering) in premises at elevation +21.300;
- Installation of external fire ladders;
- Cladding of rooms 111А, 111В, 305;
- Installation of transformers in electrical rooms;
- Installation of embedded parts of penetrations in ISFPS room 501 – 50 of 57 parts were installed and embedded in concrete;
- Air ducts installation of CCA ventilation system (intake and exhaust) of non-attended and periodically attended CAVS-S-1 rooms at elev. +0.000;
- Major repair of external fire stairway P2, except the upper stairway;
- Installation of hot water supply system equipment in room 133 was completed;
- Installation of lightning protection;
- Facades installation works.

Gate house (GH):
- Repair and finishing of premises;
- Installation of air-handling unit was completed.

Physical Protection System (PPS):
- Arrangement of security patrol route –foundation, slabs placement;
- Restoration of fences (installation of new posts) of PPS perimeter.

Installation of equipment (pumps, filters) of the sewage treatment facility.

Installation of cable structures in pits and installation of grounding.

The general Сontractor of the project is Holtec Company. Works at the site are performed by Holtec subcontractors: CDI, UTEM, UTB, ZEM, EPI, BEM, Promkomplekt, UTEM-Kranservis, Konditsioner. 244 people at the total were engaged in work performance. 11 units of excavation and lifting equipment were also used for implementing tasks at the site.

17 грудня 2015 року
17 грудня 2015 року
17 грудня 2015 року
17 грудня 2015 року
17 грудня 2015 року
17 грудня 2015 року

Select another date

During the second half of November at ISF-2 construction site the following works were carried out:

Spent Fuel Processing Facility (SFPF):
- Startup finishing operations (plastering) in premises at elevations +17.000; +21.300;
- Installation of embedded element of guiding pipe for canisters transportation double cover system;
- Installation of external fire ladders;
- Installation of temporary roof structures for mounting holes was completed;
- St.steel cladding (t=8mm) of protective channel IS102D1 (elev. +16.450);
- Cladding of rooms 111А, 111В, 305;
- Installation of transformers in electrical rooms;
- Installation of embedded elements of penetrations in ISFPS room 501 – 23 of 57 elements were installed and embedded in concrete;
- Installation of embedded elements of crane MIS-CR-220 in room 504;
- Air ducts installation of CCA ventilation system (inflow) of non-attended and periodically attended CAVS-S-1 rooms at elev. +0.000;
- Major repair of external fire stairway P2;
- Installation of water supply systems pipelines B1, T3, T4 was completed.

Gate house:
- Repair and finishing of premises;
- Installation of cable structures of power supply systems of the 1st floor;
- Installation of facades of buildings;
- Installation of lighting system of the 1st floor.

Physical Protection System (PPS):
- Installation of operating and backup power supply system (in ducts, in trench) for security lighting of the site perimeter;
- Restoration of fences (installation of new posts) of PPS perimeter;

The general Сontractor of the project is Holtec Company. Works are performed at the site by Holtec subcontractors: CDI, UTEM, UTB, ZEM, EPI, BEM, Promkomplekt, UTEM-KRANSERVIS. 222 people at the total were engaged in work performance. 11 units of excavation and lifting equipment were used for implementing the tasks at the site.

December 03, 2015
December 03, 2015
December 03, 2015
December 03, 2015
December 03, 2015
December 03, 2015

Select another date

During the first half of November the following works were performed at ISF-2 construction site:

Spent Fuel Processing Facility (SFPF):
-Startup finishing operations (plastering) in premises at elevations +17.000; +21.000;
-Installation of the slab MS6-2 at elevation +26.000 (over rooms 706; 704);
-Installation of external fire ladders and staircases;
-Cladding of rooms -106, -105 at elevation -3.400 was completed;
-Cladding works of rooms 111А, 111В, 305;
-Installation of brick partition walls at elevation +17.000;
-Installation of penetrations embedded elements in room 501;
-Drilling of holes for penetrations in room IS102C6;
-Air ducts installation of CCA ventilation systems (inflow) of non attended and periodically attended rooms CAVS-S-1 at elev. +2.800;
-Installation of the vent stack lower part was completed;
-Installation of pipelines of water supply systems B1, T3, T4;

Gate house:
-Repair and finishing of premises;
-Installation of cable structures of power supply systems of the 1st floor;
-Works on arrangement of lighting system of the 1st floor.

Physical Protection System (PPS):
-Power supply unit for PPS equipment – installation of cable pits, pipes for cable ducts, except for the parking areas of KB-408 tower crane and DEC, was completed;
-Installation of operating and backup power supply system (in ducts, in trench) for security lighting of the site perimeter;
-Installation and connection of lighting posts, lamps;
-Restoration of fences (installation of new posts) of PPS perimeter;
-Installation of shields SHAVR1-5 was completed;
-Road 2 construction work was completed.

The general Сontractor of the project is Holtec Company. Works are carried out at the site by Holtec subcontractors: CDI, UTEM, UTB, ZEM, EPI, BEM, Promkomplekt, UTEM-KRANSERVIS. 234 people at the total were engaged in work performance. To perform tasks at the site, 10 units of earthmoving and lifting equipment were also used.

19 листопада 2015 року
19 листопада 2015 року
19 листопада 2015 року
19 листопада 2015 року
19 листопада 2015 року
19 листопада 2015 року
19 листопада 2015 року
19 листопада 2015 року
19 листопада 2015 року

Page 9 of 9