Within the project the following activity was performed at the construction site:

- Reconfiguration of fire protection valves of the ventilation system;
- Fire retardant sealing of penetrations of process pipelines;
- Calibration of the load cells and adjustment of crane positioning CR-07 and CR-08 room 305;
- Replacement of bolts on crane coupling CR-01;
- Manufacture of cable support models for organizing (ordering) cable routes BNG;
- Soldering cable penetrations (outside) BNG;
- Repairs and preventive works of SMTP — oil change is completed, leaks are eliminated;
- Measurements of holes in concrete structures (Completed on 24 modules) CSM;
- Elimination of comments on rainwater wells — concreting of covers
- Completing of executive & acceptance documentation according to the Contract;
- The development of test programs of technological components and systems;
- Preparation of Employer’s personnel training programmers;
- Commissioning on main technological equipment and auxiliary;
- Individual (Autonomous) tests of the System for technological process monitoring and controlling at the — systems for fuel canisters, double-wall shielded canisters handling and solid radioactive waste management;
- The preliminary checks of the Sliding Holder will continue;
- Commissioning works on double cover system for 200 l drums - checked in manual and automatic mode;
- Elimination of remarks on the video surveillance system;
- Preliminary checks of Luke protective SWP-CG-02 in pom. IS 102C6;
- Preliminary tests of LRW valves;
- Elimination of comments on the results of the first phase of the trial operation of the PPS; Phase 2 started of the trial operation of PPS.

The Project General Contractor is Holtec. Works on the site are performed by the involved by Holtec subcontractors: CPI, UTEM, UTB, ZEM, EPI, BEM, “Kranservice”, “Conditioner”. In total 126 people were involved, as well as 1 units of transporting equipment.

 

Select another date

Within the project the following activity was performed at the construction site:

- The work electrical part of the crane SWP-CR-04 was resumed;
- Reconfiguration of fire protection valves of the ventilation system;
- Adjusting the gaps and scalding (welding) of the sleeves of the penetrations of process pipelines;
- Fire retardant sealing of penetrations of process pipelines;
- Modification (sealing) of IAEA passages;
- Calibration of the crane load cells CR-08 room 305;
- Completed work on timber load monitoring LD-04 room 119;
- Manufacture of cable support models for organizing (ordering) cable routes BNG;
- Soldering cable penetrations (outside) BNG;
- Completed drilling holes and tapping in the door of CSM;
- Completing of executive & acceptance documentation according to the Contract;
- The development of test programs of technological components and systems;
- Preparation of Employer’s personnel training programmers;
- Commissioning on main technological equipment and auxiliary;
- Individual (Autonomous) tests of the System for technological process monitoring and controlling at the — systems for fuel canisters, double-wall shielded canisters handling and solid radioactive waste management;
- Inspection of the representative of the manufacturer of parallel manipulators, removal of comments on the results of inspection;
- Preparation of simulator for SFA capture;
- Completed elimination of remarks and re-testing of the TD-05/06 trolley in room 119;
- Completed elimination of remarks and re-testing of the double cover system TP;
- Elimination of remarks on the Cutting Machine;
- The preliminary checks of the Sliding Holder will continue — the calibration of the load cell;
- Commissioning works on double cover system for 200 l drums — checked in manual and manual mode;
- Elimination of remarks on the video surveillance system;
- Elimination of comments on the results of the first phase of the trial operation of the PPS; Phase 2 started of the trial operation of PPS
- Completion of comments on the SFP-CR-304 crane, testing of the Gostrud.

The Project General Contractor is Holtec. Works on the site are performed by the involved by Holtec subcontractors: CPI, UTEM, UTB, ZEM, EPI, BEM, “Kranservice”, “Conditioner”. In total 143 people were involved, as well as 1 units of transporting equipment.

 

Select another date

Within the project the following activity was performed at the construction site:

- works on insulation of pipelines and forced gas drying system heaters;
- sealing of IAEA equipment, installation of locks;
- cable laying, installation of sockets;
- drilling of holes and screw cutting in the concrete storage modules doors;
- electrical works at the SWP-CR-04 crane;
- installation of electronic key system;
- reconfiguration of the Ventilation System fire protection valves;
- adjustment of gaps and welding of the sleeves of technological pipelines penetrations;
- fire retardant sealing of technological pipelines penetrations of process pipelines;
- scheduled works for the construction site improvement;
- compilation of the executive and hand-over documentation;
- development of technological units and systems testing programs;
- development of Customer's personnel training programs;
- pre-commissioning activity at the basic technological equipment and auxiliary systems;
- individual testing of the System for technological process monitoring and controlling at the - systems for fuel canisters, double-wall shielded canisters handling and solid radioactive waste management;
- software finalization and adjustment of the temperature control system for concrete storage modules;
- loading of double-wall shielded canister in the System of canisters manipulation and transportation and trial delivery into the concrete storage module;
- elimination of comments based on the results of individual tests of the device for spent fuel assemblies cutting SFP-CS-205;
- individual testing Systems for the canister CHT-TD-02 handling and transporting;
- elimination of comments based on the results of the trolley TD-05/06 individual testing;
- individual testing of the system of the fuel canister double lid;
- individual tests of protective lids SHIELDING PLUGS 305 SFP-XP-210/211;
- pilot operation of the Physical Protection System.

The Project General Contractor is Holtec. Works on the site are performed by the involved by Holtec subcontractors: CPI, UTEM, UTB, ZEM, EPI, BEM, “Kranservice”, “Conditioner”. In total 141 people were involved, as well as 1 units of transporting equipment.

December 19, 2017
December 19, 2017
December 19, 2017
December 19, 2017
December 19, 2017
December 19, 2017

Select another date

Spent Fuel Processing Facility (SFPF):

- Installation of a platform for servicing the gate mechanisms MIS-LD-04 and MIS-LD-01.
- Works on insulation of pipelines and heaters.
- Stamped of IAEA equipment. Mounting locks.

The following activities were also performed at the facility:

- Drilling holes and threading in CSM doors.
- The work on the crane SWP-CR-04 was resumed.
- The video camera bracket is remounted.
- Regular works on the construction site arrangement.
- Completing of executive & acceptance documentation according to the Contract.
- Development of test programs for technological units and systems.
- Development of a training program for Chornobyl Nuclear Power Plant personnel.
- Commissioning on main technological equipment and auxiliary.
- Individual (Autonomous) tests of PCMS DWC Handling System, FT Handling System, SRW Management System.
- Individual tests of the Cutting Machine SFA SFP-CS-205.
- Individual Test of Canister Handling and Transport System CHT TD 02.
- Individual tests of the security door SWP-SD-01.
- Finished  Individual testing trolley TD-05 in room 119.
- Functional tests of the crane SFP-CR-08 in room. 305.
- Finished 3 items of hoists.
- Testing of the control systems of nitrogen supply systems, argon supply, helium supply.
- Elimination of comments after Individual Test.
- Trial operation of PPS continues.

The general Contractor of the project is Holtec. Works at the site are being performed by Holtec subcontractors: CDI, UTEM, UTB, ZEM, EPI, BEM, Kranservis, Konditsioner. In total 138 persons were engaged in the works. 1 unit of lorry-loading, earth-moving and lifting machines were also used for fulfilling tasks at the site.

Select another date

Spent Fuel Processing Facility (SFPF):

- Preparatory works on installation of structures the IAEA cabinet in 107с.
- The cable was replaced and the connection was disconnected from the transport trolley in p. 119.
- Installation of a platform for servicing the gate mechanisms MIS-LD-04 and MIS-LD-01.
- The water heaters are piped according to the issued changes in the working documentation.
- Works on insulation of pipelines and heaters.
- Installation of IAEA equipment in p. 307B, 109B, 109A, 603.
- Mounting of visors over RMS devices.

The following activities were also performed at the facility:

- Drilling holes and threading in CSM doors.
- Regular works on the construction site arrangement.
- Completing of executive & acceptance documentation according to the Contract.
- Development of test programs for technological units and systems.
- Development of a training program for Chornobyl Nuclear Power Plant personnel.
- Commissioning on main technological equipment and auxiliary.
- Finished Individual tests of the  ventilation and air conditioning system of the Gate House.
- Functional tests of crane SFP-CR-01 room. 119.
- Individual (Autonomous) tests of PCMS DWC Handling System, FT Handling System, SRW Management System.
- Individual tests of the security door SWP-SD-01.
- Finished Individual tests of autonomous power supply system.
- Finished Integrated testing of the Sewerage and Sewage Systems (Removing Remarks).
- Finished Individual tests of the working and emergency lighting systems of the SFPF.
- Finished Individual tests of the Removable Platforms SFP-PL-01.
- Individual tests of the Cutting Machine SFA SFP-CS-205.
- Individual testing Systems for manipulating and transporting a pencil case (CHTS) CHT-TD-02 (room 119).

The general Contractor of the project is Holtec. Works at the site are being performed by Holtec subcontractors: CDI, UTEM, UTB, ZEM, EPI, BEM, Kranservis, Konditsioner. In total 141 persons were engaged in the works. 1 unit of lorry-loading, earth-moving and lifting machines were also used for fulfilling tasks at the site.

 