ISF-2 construction progress as of April 13, 2017

Select another date

Spent Fuel Processing Facility (SFPF):

- Unloading of the equipment and materials, equipment transfer into the installation area.
- Installation of cable products of АC and RMS in SFPF building premises.
- Modification of the bridge crane SFP-CR-11 in the premise 501/603 — replacement of mechanical part and electrical works are underway.
- Modification of the bridge crane SFP-CR-01 in prem. 119 — replacement of the electrical components.
- Installation of SFP-CR-240 crane beams in the prem. IS 102c9.
- Works on installation of crane CR-220 in the prem. 504 of SFPF building.
- Modification of the protective hatch in the prem. IS102C6 of SFPF building is compleated.
- Installation of main process equipment:
     * Installation of the main process equipment — installation of the docking device TK-8 in the design position.
     * Installation of the main process equipment — installation of the SFP-TT-210 table in prem. 501 (the mechanical part) is completed, the electrical equipment installation is underway.
     * Installation of FFS equipment in premise 505 A in SFPF building.
     * Installation of FFS pipelines in premise 505 A and 505B in SFPF building.
     * Continuation of the LRW tanks assembly.
     * Installation of power and control cables of BNG equipment.
- Works on gas-aerosol control of RMS system in the SFPF building.
- Work on installation openings closure in the prem. 705 — roof arrangement.
- Work on installation openings closure in the prem. S102c9 — roof casing.
- Work on installation openings closure in the prem. 603 — preparatory work for a wall building up.

The following activities were also performed at the facility:

- Installation of PPS lightning protectors.
- Arrangement of fore-roof for balloons - cutting of compensation joint in a floor slab.
- Compilation of executive and hand-over documentation for the corresponding stages delivery according to the Contract.
- Development of testing programs for technological units and systems.
- Development of training programs for the Employer’s personnel.
- Pre-commissioning work at the cutting facility, RMS system are underway.

The general Contractor of the project is Holtec. Works at the site are being performed by Holtec subcontractors: CDI, UTEM, UTB, ZEM, EPI, BEM, Kranservis, Konditsioner. In total 280 persons were engaged in the works. 4 units of lorry-loading, earth-moving and lifting machines were also used for fulfilling tasks at the site.