Spent Fuel Processing Facility (SFPF):
- Unloading of the equipment and materials, equipment transfer into the installation area.
- Installation of cable lines of Physical Protection System, Automated monitoring and Radiation monitoring System.
- Cable routing.
- Modification of bridge cranes in the prem. 305 SFP-CR-07 and 501/603 SFP-CR-11 — replacement of mechanical and electrical elements.
- Installation of main process equipment:
* Assembly (welding) of the crane for maintenance with loading capacity 5 t MIS-CR-240 in prem. IS102C9.
* Installation of duplicating manipulators SFP-TM- 221/222 in prem. 305 / 303A and SFP-TM-227/228 in prem. 501/506.
* Installation of the support ring for docking device TK-8 casing.
* Completed the installation of a protective lid SFP XP 210 is completed, concreting is under preparation.
* Completion of installation of the existing protective door SWP-SD-01, existing trolleys for the transport container.
- Installation of power and control cables, equipment of the power supply panels for BNG lighting system.
- Installation of ducts, cabling, connection of control boxes for fireproof ventilation valves, pipelines.
- Installation of LRW docking stations - in prem. 107 and under control tanks canopy.
- Works on gas-aerosol monitoring systems within RMS, equipment and cable lines of fire alarm system and evacuation control, mounting of installation openings.
- Arrangement of a new laboratory premise 211, arrangement of a new premise 409 - reinforcement of the walls.
- Finishing of floor coatings
The following activities were also performed at the facility:
- Connection of video cameras, soldering of fiber optic cable, assembly of Physical Protection System elements.
- Completing of the executive and handover documentation to delivery the relevant stages under the Contract.
- Development of tests programs for technological components and systems, customer's personnel training programs.
- Pre-commissioning on a sliding holder, cutting device and double lid system.
- Individual testing of the equipment - primary tests of SFP-CR-06 SFP-CR-04, SWP-CR-01 cranes is completed.
The general Contractor of the project is Holtec. Works at the site are being performed by Holtec subcontractors: CDI, UTEM, UTB, ZEM, EPI, BEM, Kranservis, Konditsioner. In total 267 persons were engaged in the works. 3 units of lorry-loading, earth-moving and lifting machines were also used for fulfilling tasks at the site.