ISF-2 construction progress as of June 16, 2016

Select another date

During the first half of June 2016 at ISF-2 construction site the following works were carried out:

Spent Fuel Processing Facility (SFPF):

- Installation of air ducts for PPS CAVS-3 air supply ventilation system at elev. +11.700;
- Installation of cable routes in premises of the facility;
- Installation of lighting system;
- Finishing of the premises;
- Installation of the cooling system pipelines;
- Installation of pipelines for LRW treatment system special drainage;
- Installation of compressed air system pipelines;
- Installation of pipelines for chemically demineralized water system;

CSM:

- Installation of lightning protection on the modules.

Gate house:

- Electric installation works.

The following works were also performed:

- Laying of power distribution network from automatic throw-over circuit-breaker cabinets to consumers of security equipment;
- Reinstallation of PPS safety gates;
- Installation of ARMS station equipment.

The general Сontractor of the project is Holtec Company. Works at the site are being performed by Holtec subcontractors: CDI, UTEM, UTB, ZEM, EPI, BEM, Kranservis, Konditsioner. 179 people at the total were engaged in work performance.  6 units of earth-moving machinery, lorry, and lifting machines were used for implementing tasks at the site.

June 16, 2016
June 16, 2016
June 16, 2016
June 16, 2016
June 16, 2016
June 16, 2016