ISF-2 construction progress as of June 09, 2016

Select another date

 

During the period under review, at ISF-2 construction site the following works were carried out:

Spent Fuel Processing Facility (SFPF):

- Installation of cable routes in premises of the facility;
- Installation of lighting system;
- Finishing of the premises;
- Installation of the cooling system pipelines;
- Installation of pipelines for LRW treatment system special drainage;
- Installation of compressed air system pipelines;
- Installation of pipelines for chemically demineralized water system;
- Installation of pumps of auxiliary process systems;
- Installation of pipelines for RAW level monitoring tanks.

CSM:

- Installation of security lighting system;
- Installation of vent grilles;
- Installation of lightning protection on the modules.

Gate house:

- Electric installation works.

The following works were also performed:

- Laying of power distribution network from automatic throw-over circuit-breaker cabinets to consumers of security equipment;
- Reinstallation of PPS safety gates;
- Installation of ARMS station equipment.

The general Сontractor of the project is Holtec Company. Works at the site are being performed by Holtec subcontractors: CDI, UTEM, UTB, ZEM, EPI, BEM, Kranservis, Konditsioner. 181 people at the total were engaged in work performance.  6 units of earth-moving machinery, lorry, and lifting machines were used for implementing tasks at the site.