In late March and early April at ISF-2 construction site the following works were carried out:
Spent Fuel Processing Facility (SFPF):
- Air ducts installation of CCA ventilation system (intake) of non-attended and periodically attended CAVS-S-1 rooms at elev. +17.000;
- Air ducts installation of CCA ventilation system (exhaust) of non-attended and periodically attended CAVS-E-1 rooms at elev. +17.000;
- Installation of main cable routes structures at elev. +11.700 of rooms 502, 504;
- Installation of cable routes structures at elev. +5.600 of rooms 303, 304;
- Installation of lighting system at elev. +5.600;
- Installation of lighting system at elev. +11.700;
- Installation of lighting system at elev. +0.000;
- Installation of the cooling system pipelines;
- SFPS facades installation works, i.e. plinth installation;
- Finishing of the premises;
- Installation of LRW treatment system equipment – corrective actions on drainage water tanks installation in rooms -103, -104;
- Installation of pipelines for LRW treatment system special drainage;
- Installation of compressed air system pipelines;
- Installation of chemically demineralized water system pipelines.
CSM:
- Installation of parts of pos. 5 and pos. 6;
- Installation of cable routes structures.
Gate house:
- Electric installation works.
Additional works:
- Laying of crushed stone base in PPS protected zone;
- Placement of security patrol route slabs;
- ISF site improvement works;
- Construction of Road 3.
The general Сontractor of the project is Holtec Company. Works at the site are performed by Holtec subcontractors: CDI, UTEM, UTB, ZEM, EPI, BEM, Kranservis, Konditsioner. 256 people at the total were engaged in work performance. 12 units of earth-moving machinery, lorry, and lifting machines were also used for implementing tasks at the site.