ISF-2 construction progress as of April 08, 2016

Select another date

In late March and early April at ISF-2 construction site the following works were carried out:

Spent Fuel Processing Facility (SFPF):

- Air ducts installation of CCA ventilation system (intake) of non-attended and periodically attended CAVS-S-1 rooms at elev. +17.000;

- Air ducts installation of CCA ventilation system (exhaust) of non-attended and periodically attended CAVS-E-1 rooms at elev. +17.000;

- Installation of main cable routes structures at elev. +11.700 of rooms 502, 504;

- Installation of cable routes structures at elev. +5.600 of rooms 303, 304;

- Installation of lighting system at elev. +5.600;

- Installation of lighting system at elev. +11.700;

- Installation of lighting system at elev. +0.000;

- Installation of the cooling system pipelines;

- SFPS facades installation works, i.e. plinth installation;

- Finishing of the premises;

- Installation of LRW treatment system equipment – corrective actions on drainage water tanks installation in rooms -103, -104;

- Installation of pipelines for LRW treatment system special drainage;

- Installation of compressed air system pipelines;

- Installation of chemically demineralized water system pipelines.

 

CSM:

- Installation of parts of pos. 5 and pos. 6; 

- Installation of cable routes structures.

 

Gate house:

- Electric installation works.

 

Additional works:

- Laying of crushed stone base in PPS protected zone; 

- Placement of security patrol route slabs; 

- ISF site improvement works; 

- Construction of Road 3.

 

The general Сontractor of the project is Holtec Company. Works at the site are performed by Holtec subcontractors: CDI, UTEM, UTB, ZEM, EPI, BEM, Kranservis, Konditsioner. 256 people at the total were engaged in work performance. 12 units of earth-moving machinery, lorry, and lifting machines were also used for implementing tasks at the site.