During the first half of July 07, 2016 at ISF-2 construction site the following works were carried out:
Spent Fuel Processing Facility (SFPF):
- Installation of cable routes in premises of the facility;
- Laying of cable products in premises of the facility;
- Arrangement of self-levelling floors;
- Arrangement of a new premise 410;
- Preparation of cold supply system pipelines for hydrotesting;
- Installation of pipelines for LRW special sewage system;
- Preparation of compressed air system pipelines for pneumatic testing;
- Installation of pipelines for chemically demineralized water system;
- Installation of pipelines for monitoring tanks;
- Installation of main process equipment – lifting device SFP-TD-211;
- Installation of gate MIS-LD-04 of premise 114.
Concrete storage modules (CSM):
-Installation of lightning protection on the modules;
- Installation of embedded items for CSMs temperature control;
- Installation of ventilation grids.
The following activities were also performed at the facility:
- Laying of power distribution network from automatic throw-over circuit-breaker cabinets to consumers of security equipment;
- Reinstallation of PPS security gates – construction of new foundations from the direction of Check Point.
The general Сontractor of the project is Holtec Company. Works at the site are being performed by Holtec subcontractors: CDI, UTEM, UTB, ZEM, EPI, BEM, Kranservis, Konditsioner. 219 people at the total were engaged in work performance. 6 units of earth-moving machinery, lorry, and lifting machines were used for implementing tasks at the site.