ISF-2 construction progress as of July 21, 2016

Select another date

During the first half of July 21, 2016 at ISF-2 construction site the following works were carried out:

Spent Fuel Processing Facility (SFPF):
- Cable routing within building premises;
- Installation of self-leveling floors;
- Installation of lighting system;
- Laying of active drainage pipes of LRW system;
- Pipe laying of RAW level monitoring tanks;
- Installation of basic process equipment – installation of sliding holder frame SFP CR 220 in the designed position is completed in premise 501 of SFPF building. Following the acceptance, the BNG representatives will restore mounting/installation activities;
- Installation of gates MIS-LD-04 in premise 114;
- Preparatory works for mounting of ventilation system equipment.

Concrete storage modules (CSM):

- Installation of lightning protection on modules;
- Installation of imbedded items for CSM temperature monitoring;
- Mounting of ventilation grills is completed.

The following activities were also performed at the facility:

- Laying of distribution mains from automatic load transfer cabinets to technical security equipment consumers;
- Remounting of physical protection system (PPS) safety gates – installation of new gate foundations from Check Point side;
- Twisted pair cabling from transducer locations to physical protection system (PPS) cabinets.

The general Сontractor of the project is Holtec Company. Works at the site are being performed by Holtec subcontractors: CDI, UTEM, UTB, ZEM, EPI, BEM, Kranservis, Konditsioner. 196 people at the total were engaged in work performance.  6 units of earth-moving machinery, lorry, and lifting machines were used for implementing tasks at the site.