Within the NSC Project at the construction site the following works are being performed:

- Delivery of structural steelwork to the site;
- Installation of Northern garage floor grating (tertiary structures);
- Installation of special doors of the Arch;
- Installation of TP-4 tilting panel hinged joints;
- Preparation of secondary and tertiary structural steelwork of the Arch western part for erection;
- Installation of purlins of internal and external cladding;
- Installation of external and internal cladding;
- Ventilation system (preparation of air ducts for installation, installation of air ducts, supports and scaffolding);

- MCS mounting:
* Reassembly of the East bridge – installation of electrical and mechanical part;
* Installation of cable supports and cable ducts inside the Arch Maintenance garage;
* Mounting of MCS crane runways (preparation, adjustment and mounting).

- Arrangement of technological building and auxiliary facilities:
* Technological building (TEC) – walling, roofing (reinforcement, formwork, concreting);
* Electrical Equipment Building (EEB) – installation of cable supports, cable trays, and transformers;
* Fire Subdivision Access Lock (FSAL) – walling (reinforcement, formwork, concreting);
* Firewater pumping station (FWR) – reinforcement of walls of the building, installation of formwork, concreting;
* Central control room – walling (reinforcement, formwork, concreting). 

- Arrangement of external and internal space of the NSC:
* Outdoor cable routes;
* Outdoor, underground utility systems;
* Storm water catching basins.

 

February 11, 2016
February 11, 2016
February 11, 2016
February 11, 2016
February 11, 2016
February 11, 2016

Select another date

During the second half of January at ISF-2 construction site the following works were carried out:

Spent Fuel Processing Facility (SFPF) :
- Installation of frames for protective windows in room 501 was completed;
- Welding of embedded elements of penetrations for slave manipulators in room 501 was completed;
- Installation of embedded plates for equipment in room 501;
- Mounting of st.steel cladding sheets on walls in room 501;
- Mounting of st.steel cladding sheets on the floor in room 501;
- Construction of F1-xx foundations (axes 2С-2D; 205-206) in room 501 was completed;
- Installation of embedded parts for crane MIS-CR-221 (elev. +28.140) in room 603;
- Installation of crane embedded parts in room IS102C9;
- Erection of crane structural steelwork in room 505A was completed;
- Inspection of the existing fire line fixtures;
- Insulation of hot water supply system pipelines T3, T4 and drinking water pipeline B1 was completed;
- Air ducts installation of CCA ventilation system (intake) of non-attended and periodically attended CAVS-S-1 rooms at elev. +5.600;
- Air ducts installation of CCA ventilation system (exhaust) of non-attended and periodically attended CAVS-E-1 rooms at elev. +5.600;
- Mounting of ventilation systems fire retardant valves at elev. +5.600;
- Installation of chiller into the design position was completed;
- Installation of external fire ladders;
- Installation of lightning protection of the building;
- Facades installation works.

Repair and finishing of Gate house premises;

Installation of equipment (pumps, filters) and pipelines of the sewage treatment facility was completed;

Electric installation works (installation of electrical cabinets, sensors, floats, termination, and grounding) of the sewage treatment facility were completed;

Hydraulic testing of the sewage treatment facility pipelines was carried out;

Hydraulic testing of K1, K15 sewage systems, B1, B2, T3 and T4 pipelines systems was carried out.

Installation of parts of position 5 and position 6 on concrete storage modules. 

The general Сontractor of the project is Holtec Company. Works at the site are performed by Holtec subcontractors: CDI, UTEM, UTB, ZEM, EPI, BEM, Konditsioner. 196 people at the total were engaged in work performance. 6 units of excavation and lifting equipment were also used for implementing tasks at the site.

04 лютого 2016 року
04 лютого 2016 року
04 лютого 2016 року
04 лютого 2016 року
04 лютого 2016 року
04 лютого 2016 року

Select another date

Within the NSC Project at the construction site the following works are being performed:

- Removal of snow and ice from the Arch assembly site;
- Delivery of structural steelwork to the site;
- Installation of Northern garage floor grating (tertiary structures);
- Installation of special doors of the Arch;
- Preparation of secondary and tertiary structural steelwork of the Arch western part for erection;
- Installation of purlins of internal and external cladding;
- Ventilation system (preparation of air ducts for installation, installation of air ducts, supports and scaffolding);

- MCS mounting:
* Reassembly of the East bridge – assembly of structures, installation of electrical part;
* Installation of cable supports and cable ducts inside the Arch Maintenance garage;
* Mounting of MCS crane runways (preparation, adjustment and mounting).

- Arrangement of technological building and auxiliary facilities:
* Technological building (TEC) – walling, roofing (reinforcement, formwork, concreting);
* Electrical Equipment Building (EEB) – installation of cable supports, cable trays, and transformers;
* Fire Subdivision Access Lock (FSAL) – walling (reinforcement, formwork, concreting);
* Firewater pumping station (FWR) – reinforcement of walls of the building;
* Central control room – walling (reinforcement, formwork, concreting). 

- Arrangement of external and internal space of the NSC:
* Outdoor cable routes;
* Outdoor, underground utility systems. 

 

February 04, 2016
February 04, 2016
February 04, 2016
February 04, 2016
February 04, 2016
February 04, 2016

Select another date

Within the NSC Project at the construction site the following works are being performed:

- Removal of snow and ice from the Arch assembly site;
- Delivery of structural steelwork to the site;
- Repair and maintenance of equipment and installations;
- Preparation of secondary and tertiary structural steelwork of the Arch Western part for erection;
- Installation of purlins of internal and external cladding;
- Installation of the Main Cranes System:
* Delivery of MCS components to the site;
* Reassembly of the East bridge (structural);
* Reassembly of the Mobile Tool Platform (electrical part);
* Mounting of MCS crane runways (preparation, adjustment and mounting).

- Arrangement of technological building and auxiliary facilities:
* Technological building (TEC) – walling, roofing (reinforcement, formwork, concreting);
* Electrical Equipment Building (EEB) – installation of cable supports and cable trays;
* Fire Subdivision Access Lock (FSAL) – walling (reinforcement, formwork, concreting);
* Firewater pumping station (FWR) – reinforcement of walls of the building;
* Central control room – walling (reinforcement, formwork, concreting).

- Arrangement of external and internal space of the NSC:
* Outdoor cable routes;
* Outdoor underground utility systems.

 

28 січня 2016 року
28 січня 2016 року
Східний міст системи основних кранів
Мобільна інструментальна платформа
28 січня 2016 року
28 січня 2016 року

Select another date

During the first half of January at ISF-2 construction site the following works were carried out:

Spent Fuel Processing Facility (SFPF):
- Painting of walls in rooms at elev. +0.000; +2.800; +17.000; +21.300;
- Arrangement of accessories to install frames for protective windows in room 501;
- Welding of embedded elements of penetrations for slave manipulators in room 501;
- Installation of embedded plates for equipment in room 501;
- Construction of F1-xx foundations (axes 2С-2D; 205-206) in room 501;
- Installation of embedded parts for crane MIS-CR-221 (elev. +28.140) in room 603;
- Installation of crane embedded parts in room IS102C9;
- Erection of crane structural steelwork in room 505A;
- Installation and concreting of penetrations elements at elev. +8.500 (3 pcs.) and at elev. +11.700 (1 pcs.) was completed;
- Inspection of the existing fire line fixtures;
- Air ducts installation of CCA ventilation system (intake) of non-attended and periodically attended CAVS-S-1 rooms at elev. +5.600;
- Air ducts installation of CCA ventilation system (exhaust) of non-attended and periodically attended CAVS-E-1 rooms at elev. +5.600;
- Mounting of ventilation systems fire retardant valves at elev. +5.600;
- Installation of external fire ladders;
- Installation of lightning protection of the building;
- Facades installation works.

Gate house:
- Repair and finishing of premises;
- Facades installation works were completed.

Installation of equipment (pumps, filters) and pipelines of the sewage treatment facility.

Post-completion and turn-over documentation selection for delivery of works of relevant stages according to the Contract.

Development of testing programs for process units and systems.

The general Сontractor of the project is Holtec Company. Works at the site are performed by Holtec subcontractors: CDI, UTEM, UTB, ZEM, EPI, BEM, Konditsioner. 170 people at the total were engaged in work performance. 6 units of excavation and lifting equipment were also used for implementing tasks at the site.