Within the NSC Project at the construction site the following works are being performed:
- Removal of snow and ice from the Arch assembly site;
- Delivery of structural steelwork to the site;
- Repair and maintenance of equipment and installations;
- Preparation of secondary and tertiary structural steelwork of the Arch Western part for erection;
- Installation of purlins of internal and external cladding;
- Installation of the Main Cranes System:
* Delivery of MCS components to the site;
* Reassembly of the East bridge (structural);
* Reassembly of the Mobile Tool Platform (electrical part);
* Mounting of MCS crane runways (preparation, adjustment and mounting).
- Arrangement of technological building and auxiliary facilities:
* Technological building (TEC) – walling, roofing (reinforcement, formwork, concreting);
* Electrical Equipment Building (EEB) – installation of cable supports and cable trays;
* Fire Subdivision Access Lock (FSAL) – walling (reinforcement, formwork, concreting);
* Firewater pumping station (FWR) – reinforcement of walls of the building;
* Central control room – walling (reinforcement, formwork, concreting).
- Arrangement of external and internal space of the NSC:
* Outdoor cable routes;
* Outdoor underground utility systems.