Within the NSC Project at the construction site the following works are being performed:
- Delivery of steelwork to the site;
- Installation of Northern garage floor grating (tertiary structures);
- Installation of special doors of the Arch;
- Pre-assembly of modules, and elevator shaft construction;
- Installation of crane runway girders for the northern garage 25 t crane;
- Installation of TP-5.1, TP-5.2, TP-6 tilting panels automatic jacks;
- Installation of the sealing membrane flashing anchors on TP-5.2 tilting panel;
- Installation of purlins of internal and external cladding;
- Installation of external and internal cladding. Overall progress is 92%;
- Ventilation system (preparation of air ducts for installation, installation of air ducts, supports, and scaffolding, preparation of NVC for vent systems installation and connection with air ducts). Overall progress is 83%;
- Main Cranes System (MCS) installation:
* Leveling (alignment) of crane-runway girders;
* Installation of prisms for crane-runway girder alignment (Arch western part) – works completed;
* Cutting of tracks, drilling of holes, and installation of tracks – works completed;
* Completing of Eastern bridge power supply installation – works completed;
* Installation of wireway for bridges power supply connection.
- Arrangement of technological building and auxiliary facilities:
* Technological building (TEC) – walling, roofing (reinforcement, formwork, and concreting), and heat insulation of roof. Overall progress (construction) – 88%;
* Electrical Equipment Building (EEB) – installation of cable supports and cable trays, cable layout and installation of terminations in sections and transformer chambers, installation of doors, heat insulation of roof. Overall progress (construction) – 93.5%;
* Fire Subdivision Access Lock (FSAL) – heat insulation of roof, installation of scaffolding, and formwork. Overall progress (construction) – 88%;
* Firewater pumping station (FWR) – concreting of roof, concrete curing, surface preparation of the roof. Overall progress (construction) – 88%;
* FWR tanks area – concrete curing, reinforcement of the foundation;
* Central control room – walling and roofing (reinforcement, formwork, concreting);
* Diesel power plant site – curing of concrete.
- Arrangement of external and internal space of the NSC:
* Outdoor cable routes (cable laying);
* Outdoor, underground utility systems;
* Storm water catching basin;
* Construction of roads in Local zone.
Erection of Arch western part structural steelwork:
Erected in total – 15,632.30 tons
Erection of Arch eastern part structural steelwork:
Erected in total – 14,213.23 tons