During the first half of July 07, 2016 at ISF-2 construction site the following works were carried out:

Spent Fuel Processing Facility (SFPF):
- Installation of cable routes in premises of the facility;
- Laying of cable products in premises of the facility;
- Arrangement of self-levelling floors;
- Arrangement of a new premise 410;
- Preparation of cold supply system pipelines for hydrotesting;
- Installation of pipelines for LRW special sewage system;
- Preparation of compressed air system pipelines for pneumatic testing;
- Installation of pipelines for chemically demineralized water system;
- Installation of pipelines for monitoring tanks;
- Installation of main process equipment – lifting device SFP-TD-211;
- Installation of gate MIS-LD-04 of premise 114.

Concrete storage modules (CSM):
-Installation of lightning protection on the modules;
- Installation of embedded items for CSMs temperature control;
- Installation of ventilation grids.

The following activities were also performed at the facility:
- Laying of power distribution network from automatic throw-over circuit-breaker cabinets to consumers of security equipment;
- Reinstallation of PPS security gates – construction of new foundations from the direction of Check Point.

The general Сontractor of the project is Holtec Company. Works at the site are being performed by Holtec subcontractors: CDI, UTEM, UTB, ZEM, EPI, BEM, Kranservis, Konditsioner. 219 people at the total were engaged in work performance.  6 units of earth-moving machinery, lorry, and lifting machines were used for implementing tasks at the site.

07 июля 2016 года
07 июля 2016 года
07 июля 2016 года
07 июля 2016 года
07 июля 2016 года
07 июля 2016 года

Select another date

Within the NSC Project at the construction site the following works are being performed:

- Delivery of steelwork to the site;
- Installation of special doors of the Arch;
- Adjustment of automated jacks of tilting panels TP-5.1, TP-5.2, TP-6;
- Installation of tilting panels sealing membrane;
- Installation of cable routes for control and instrumentation of Northern and Southern Ventilation Centres;
- Installation of Northern garage protective shielding;
- Installation of external and internal cladding. Overall progress – 96.21%;
- Ventilation system (preparation of air ducts for installation, installation of air ducts, supports and scaffolding, preparation of NVC for vent systems installation. Progress – 86%

- Main Cranes System (MCS) installation:

* Final leveling of crane-runway girders;
* Cutting and installation of tracks.

- 25t crane for MCS Maintenance garage:

* Reassembly of crane;
* Final leveling of crane-runway girders and installation of tracks.

- Arrangement of technological building and auxiliary facilities:

* Technological building (TEC) – installation of reinforcing cages and formwork of walls, heat insulation of roof, primer coating and puttying of walls and ceilings. Overall progress (construction part) – 93%;
* Electrical Equipment Building (EEB) – installation of cable supports and cable trays, cable layout, heat insulation of roof. Progress (construction part) – 100%;
* Fire Subdivision Access Lock (FSAL) – heat insulation of roof. Progress (construction part) – 100%;
* Firewater pumping station (FWR) – installation of formwork of northern and southern tanks. Works on repair and preparation of inner surfaces of FWR building walls for puttying and painting are being carried out. Progress (construction part) – 99%;
* Diesel power plant area – laying of electrical cables, connection of diesel-generators.

- Arrangement of internal and external space of the NSC:

* Outdoor cable routes;
* Outdoor and underground utility systems;
* Storm water catching basins;
* Construction of roads in Local zone.

Erection of Arch western part steelwork: 

Erected in total – 15,896.47 t

Erection of Arch eastern part steelwork: 

Erected in total – 14,265.62 t

July 07, 2016
July 07, 2016
July 07, 2016
July 07, 2016
July 07, 2016
July 07, 2016

Select another date

Within the NSC Project at the construction site the following works are being performed:

- Delivery of steelwork to the site;
- Installation of special doors of the Arch;
- Adjustment of automated jacks of tilting panels TP-5.1, TP-5.2, TP-6;
- Installation of cable routes for control and instrumentation of Northern and Southern Ventilation Centres;
- Installation of monorail crane in Southern Ventilation Centre;
- Installation of Northern garage protective shielding;
- Installation of purlins of internal cladding;
- Installation of external and internal cladding. Overall progress – 96.21%;
- Ventilation system (preparation of air ducts for installation, installation of air ducts, supports and scaffolding, preparation of NVC for vent systems installation. Progress – 86%

- Main Cranes System (MCS) installation:

* Final leveling of crane-runway girders;
* Cutting and installation of tracks.

- 25t crane for MCS Maintenance garage:

* Preparatory works for crane installation;
* Final leveling of crane-runway girders and installation of tracks.

- Arrangement of technological building and auxiliary facilities:

* Technological building (TEC) – installation of reinforcing cages and formwork of walls, heat insulation of roof, primer coating and puttying of walls and ceilings. Overall progress (construction part) – 93%;
* Electrical Equipment Building (EEB) – installation of cable supports, cable trays, cable layout, heat insulation of roof. Progress (construction part) – 100%;
* Fire Subdivision Access Lock (FSAL) – heat insulation of roof. Progress (construction part) – 100%;
* Firewater pumping station (FWR) – installation of formwork of northern and southern tanks. Works on repair and preparation of inner surfaces of FWR building walls for puttying and painting are being carried out. Progress (construction part) – 99%;
* Diesel power plant area – laying of electrical cables, connection of diesel-generators.

- Arrangement of internal and external space of the NSC:

* Outdoor cable routes;
* Outdoor and underground utility systems;
* Storm water catching basins;
* Construction of roads in Local zone.

Erection of Arch western part steelwork: 

Erected in total – 15,885.47 t

Erection of Arch eastern part steelwork: 

Erected in total – 14,265.62 t

June 30, 2016
June 30, 2016
June 30, 2016
June 30, 2016
June 30, 2016
June 30, 2016

Select another date

Within the NSC Project at the construction site the following works are being performed:
- Supply of metal structures to the site;
- Installation of protective shielding of North Garage;
- Installation of special doors of the Arch;
- Installation of automatic jacks of  tilting panels TP-5.1, TP-5.2, TP-6;
- Mounting of cable tracks of control instrumentation of north and south ventilation centers;
- Pre-assembling of monorail crane structures in South Ventilation Center;
- Installation of internal and external casing girders;
- Mounting of external and internal casing;
- Ventilation system (preparing the air ducts for installation, installation of air ducts, installation of supports and scaffolding, preparing the North Ventilation Center (NVC) for installation of ventilation equipment).

- Main Cranes System (MCS) installation:
* Adjusting the crane beams;
* Cutting and installation of rails are being performed.

- 25t crane for MCS Maintenance garage:
* Preparatory activities for crane erection;
* Final adjustment of crane beams and mounting of rails.

- Arrangement of technological building and auxiliary facilities:
* Terms of Reference (ToR) – installation of reinforcing cages and wall formworks, roof sealing, pre-coating, coating of walls and ceilings;
* Building of electrical devices – installation of cable supports and trays, cable grooming, roof sealing;
* Access gateway for fire brigades – roof sealing;
* Fire pump station (FPS) – installation of foundation formworks for north and south storage tanks; activities on repair and preparation for coating and painting of internal wall surfaces of FPS building;
* Site of diesel power plant for power supply – laying the electrical cables and connecting diesel generators.

- Arrangement of internal and external space of the NSC:

* Outdoor cable routes;
* Outdoor and underground utility systems;
* Storm water catching basins;
* Construction of roads in Local zone.

Erection of Arch western part steelwork: 

Erected in total – 15,860.16 t

Erection of Arch eastern part steelwork: 

Erected in total – 14,265.62 t

June 23, 2016
June 23, 2016
June 23, 2016

Select another date

Within the NSC Project at the construction site the following works are being performed:

- Delivery of steelwork to the site;
- Installation of protective shielding of Northern garage;
- Installation of special doors of the Arch;
- Installation of TP-5.1, TP-5.2, TP-6 tilting panels automatic jacks;
- Installation of control and instrumentation cable routes of Northern and Southern Ventilation Centres;
- Pre-assembly of monorail crane components in Southern Ventilation Centre;
- Pre-assembly and installation of access hole for MCS Northern garage (works completed);
- Installation of purlins of internal and external cladding;
- Installation of external and internal cladding. Overall progress – 95%;
- Ventilation system (preparation of air ducts for installation, installation of air ducts, supports and scaffolding, preparation of NVC for vent systems installation. Air ducts installed – 86%;
- Installation of cable supports and cable ducts inside the Maintenance garage. Cable routing from NVC to Maintenance garage. 

- Main Cranes System (MCS) installation:

* Leveling (alignment) of crane-runway girders;
* Cutting and installation of tracks. 

- 25t crane for MCS Maintenance garage:

* Crane components have been delivered to the Assembly site; 
* Final leveling of crane-runway girders and installation of tracks.

- Arrangement of technological building and auxiliary facilities:

* Technological building (TEC) – walling and roofing (reinforcement, formwork, concreting). Overall progress (construction part) – 91.5%;
* Electrical Equipment Building (EEB) – installation of cable supports, cable trays, and staircase. Overall progress (construction part) – 100%;
* Fire Subdivision Access Lock (FSAL) – construction works completed. Finishing of the premise is underway. Overall progress (construction part) – 100%;
* Firewater pumping station (FWR) – roofing (installation of scaffolding and formwork). Overall progress (construction part) – 99%. Reinforcement works for foundations for tanks.

- Arrangement of internal and external space of the NSC:

* Outdoor cable routes;
* Outdoor and underground utility systems;
* Storm water catching basins;
* Construction of roads in Local zone.

Erection of Arch western part steelwork: 

Erected in total – 15,827.45 t

Erection of Arch eastern part steelwork: 

Erected in total – 14,265.62 t