Within the NSC Project at the construction site the following works are being performed:
- removal of snow and ice from the Acrh site;
- delivery of metal structures the site;
- repair and maintenance of equipment;
- preparation for installation of secondary and tertiary metal structures of West half of the Arch;
- installation of the Main Cranes System:
* delivery of containers with East bridge components to the Free Access Zone.
- Arrangement of technological building and auxiliary facilities:
* Technological Building - snow removal, arrangement of personnel routes;
* Electrical Equipment Building - installation of cable conduit bearers and cable trays;
* Fire Unit Access Airlock - snow removal, arrangement of personnel routes.
- arrangement of external and internal space of the NSC:
* snow removal, arrangement of personnel routes.