During the first half of November the following works were performed at ISF-2 construction site:

Spent Fuel Processing Facility (SFPF):
-Startup finishing operations (plastering) in premises at elevations +17.000; +21.000;
-Installation of the slab MS6-2 at elevation +26.000 (over rooms 706; 704);
-Installation of external fire ladders and staircases;
-Cladding of rooms -106, -105 at elevation -3.400 was completed;
-Cladding works of rooms 111А, 111В, 305;
-Installation of brick partition walls at elevation +17.000;
-Installation of penetrations embedded elements in room 501;
-Drilling of holes for penetrations in room IS102C6;
-Air ducts installation of CCA ventilation systems (inflow) of non attended and periodically attended rooms CAVS-S-1 at elev. +2.800;
-Installation of the vent stack lower part was completed;
-Installation of pipelines of water supply systems B1, T3, T4;

Gate house:
-Repair and finishing of premises;
-Installation of cable structures of power supply systems of the 1st floor;
-Works on arrangement of lighting system of the 1st floor.

Physical Protection System (PPS):
-Power supply unit for PPS equipment – installation of cable pits, pipes for cable ducts, except for the parking areas of KB-408 tower crane and DEC, was completed;
-Installation of operating and backup power supply system (in ducts, in trench) for security lighting of the site perimeter;
-Installation and connection of lighting posts, lamps;
-Restoration of fences (installation of new posts) of PPS perimeter;
-Installation of shields SHAVR1-5 was completed;
-Road 2 construction work was completed.

The general Сontractor of the project is Holtec Company. Works are carried out at the site by Holtec subcontractors: CDI, UTEM, UTB, ZEM, EPI, BEM, Promkomplekt, UTEM-KRANSERVIS. 234 people at the total were engaged in work performance. To perform tasks at the site, 10 units of earthmoving and lifting equipment were also used.

19 листопада 2015 року
19 листопада 2015 року
19 листопада 2015 року
19 листопада 2015 року
19 листопада 2015 року
19 листопада 2015 року
19 листопада 2015 року
19 листопада 2015 року
19 листопада 2015 року

Select another date

Within the NSC Project at the construction site the following works are being performed:
- Pre-assembling and installation of Western end wall gangways;
- Installation of cable conduits bearers;
- Installation of Northern ventilation center metal structures;
- Installation of crane beams at East and West halves' connection point; 
- Installation of automatic jacks of TP-2 tilting panel;
- Completing and assembly of cladding purlines;
- Preliminary erection and assembly of steel plating packages for cladding, as well as laying of heat insulating material, assembly of EPDM membrane, assembly Kalzip panels;
- Assembly of scaffolding and preparation of air ducts for assembling, assembly of air ducts of the Arch ventilation system;
- Installation of Main Cranes System elements (reassembly of mobile tool platform, preparatory works before lifting the west bridge to its installation area).

- Arrangement of technological building and auxiliary facilities:
* Technological building (TB) – walling, roofing (assembly of fittings and formwork, concreting, concrete curing);
* Electrical device building – priming, spackling and painting of walls, floors and ceilings, installation of roof heat insulation;
* Fire units acces airlock - roofing (concrete curing, formwork dismantling);
* Fire pumping station (assembly of formwork and foundation fittings).

- Arrangement of external and internal space of NSC (northern side):
* Outdoor underground services (power supply, water supply, sewer).

Assembly of metal structures of Western half of the Arch:

Metal structures assembled in total – 15,116.08 tons

Assembly of metal structures of Eastern half of the Arch:

Metal structures assembled in total –  14,138.22 tons

 

November 19, 2015
November 19, 2015
November 19, 2015
November 19, 2015
November 19, 2015
November 19, 2015

Select the another date

Within the NSC Project at the construction site the following works are being performed:
- Pre-assembling and installation of Western end wall gangways;
- Installation of cable conduits bearers;
- Installation of Northern ventilation center metal structures;
- Installation of crane beams at East and West halves' connection point; 
- Installation of automatic jacks of TP-1, TP-2 tilting panels;
- Completing and assembly of cladding purlines;
- Preliminary erection and assembly of steel plating packages for cladding, as well as laying of heat insulating material, assembly of EPDM membrane, assembly of bearing clip and Kalzip panels;
- Assembly of scaffolding and preparation of air ducts for assembling, assembly of air ducts of the Arch ventilation system;
- Installation of Main Cranes System elements (reassembly of mobile tool platform, preparatory works before lifting the west bridge to its installation area).


- Arrangement of technological building and auxiliary facilities:
* Technological building (TB) – walling, roofing (assembly of fittings and formwork, concreting, concrete curing);
* Electrical device building – priming, spackling and painting of walls, floors and ceilings, installation of roof heat insulation;
* Fire units acces airlock - roofing (concrete curing, formwork dismantling).


- Arrangement of external and internal space of NSC (northern side):
* Storm and fire extinguishing water catchment basins;
* Arch end walls
* Outdoor underground services (power supply, water supply, sewer).

Assembly of metal structures of Western half of the Arch:

Metal structures assembled in total – 15,116.08 tons

Assembly of metal structures of Eastern half of the Arch:

Metal structures assembled in total –  14,138.22 tons

 

November 12, 2015
November 12, 2015
November 12, 2015
November 12, 2015
November 12, 2015
November 12, 2015

Select the another date

Within the NSC Project at the construction site the following works are being performed:
- Pre-assembling and installation of Western end wall gangways;
- Installation of cable conduits bearers;
- Installation of Northern ventilation center metal structures;
- Installation of crane beams at East and West halves' connection point; 
- Installation of automatic jacks of TP-1, TP-2 tilting panels;
- Completing and assembly of cladding purlines;
- Preliminary erection and assembly of steel plating packages for cladding, as well as laying of heat insulating material, assembly of EPDM membrane, assembly of bearing clip and Kalzip panels;
- Assembly of scaffolding and preparation of air ducts for assembling, assembly of air ducts of the Arch ventilation system;
- Installation of Main Cranes System elements (reassembly of mobile tool platform, preparatory works before lifting the west bridge to its installation area).

- Arrangement of technological building and auxiliary facilities:
* Technological building (TB) – walling, roofing (assembly of fittings and formwork, concreting, concrete curing);
* Electrical device building – priming, spackling and painting of walls, floors and ceilings, installation of roof heat insulation;
* Fire units acces airlock - roofing.

- Arrangement of external and internal space of NSC (northern side):
* Storm and fire extinguishing water catchment basins;
* Arch end walls
* Outdoor underground services (power supply, water supply, sewer).

Assembly of metal structures of Western half of the Arch:
Metal structures assembled in total – 15,050.52 tons

 

Assembly of metal structures of Eastern half of the Arch:
Metal structures assembled in total –  14,127.99 tons

 

November 05, 2015
November 05, 2015
November 05, 2015
November 05, 2015
November 05, 2015

Select the another date

Within the NSC Project at the construction site the following works are being performed:
- Pre-assembling and installation of Western end wall gangways;
- Installation of cable conduits bearers;
- Installation of Northern garage floor gratings;
- Installation of Northern ventilation center metal structures;
- Installation of crane beams at East and West halves' connection point; 
- Installation of automatic jacks of TP-1 tilting panel;
- Completing and assembly of cladding purlines;
- Preliminary erection and assembly of steel plating packages for cladding, as well as laying of heat insulating material, assembly of EPDM membrane, assembly of bearing clip and Kalzip panels;
- Assembly of scaffolding and preparation of air ducts for assembling, assembly of air ducts of the Arch ventilation system;
- Installation of Main Cranes System elements (reassembly of the west bridge and mobile tool platform preparatory works before lifting the west bridge to its installation area).

- Arrangement of technological building and auxiliary facilities:
* Technological building (TB) – walling, roofing (assembly of fittings and formwork, concreting, concrete curing);
* Electrical device building – priming, spackling and painting of walls, floors and ceilings, installation of roof heat insulation;
* Fire units acces airlock - roofing.

- Arrangement of external and internal space of NSC (northern side):
* Storm and fire extinguishing water catchment basins;
* Arch end walls
* Outdoor underground services (power supply, water supply, sewer).

Assembly of metal structures of Western half of the Arch:
Metal structures assembled in total – 14,955.77 tons

 

Assembly of metal structures of Eastern half of the Arch:
Metal structures assembled in total –  14,124.37 tons