Within the NSC Project at the construction site the following works were carried out:
-Pre-assembly and installation of West End Wall gangways;
-Erection of North Ventilation Centre structural steel;
-Installation of doors in the access ways;
-Installation of automatic jacks of TP-2 tilting panel;
-Completing and erection of cladding purlins;
-Pre-assembly and erection of steel decking packages for cladding, as well as laying of heat insulating material, installation of EPDM membrane and Kalzip panels;
-Assembly of scaffolding and preparation of air ducts for installation, installation of air ducts of the Arch ventilation system;
-Installation of cable conduits for MCS power supply;
-Installation of the Main Cranes System:
* Preparatory works for the West bridge moving to the parking place have been completed;
* December 16, 2015, in the afternoon, moving of the MCS West bridge to the waiting area was performed. The Contractor has commenced the delivery of the East bridge components to the Arch assembly area.
- Arrangement of technological building and auxiliary facilities:
Technological building (TEC) – walling, roofing (installation of fittings, formwork, concreting, concrete curing);
* Electrical Equipment Building (EEB) – priming, spackling and painting of walls, floors and ceilings, installation of roof heat insulation, installation of staircases;
* Fire Subdivision Access Lock (FSAL) – installation of reinforcement cage and formwork of walls fragments;
* Firewater pumping station (FWR) – installation of fittings and formwork for walling;
* Excavation of pit for diesel generator tanks.
- Arrangement of external and internal space of the NSC:
* Outdoor underground utility systems (installation of power supply, water supply, sewage systems).
Erection of structural steel of Western half of the Arch:
Erected in total – 15,178.54 tons
Erection of structural steel of Eastern half of the Arch:
Erected in total – 14,150.9 tons.