During the first half of January at ISF-2 construction site the following works were carried out:
Spent Fuel Processing Facility (SFPF):
- Painting of walls in rooms at elev. +0.000; +2.800; +17.000; +21.300;
- Arrangement of accessories to install frames for protective windows in room 501;
- Welding of embedded elements of penetrations for slave manipulators in room 501;
- Installation of embedded plates for equipment in room 501;
- Construction of F1-xx foundations (axes 2С-2D; 205-206) in room 501;
- Installation of embedded parts for crane MIS-CR-221 (elev. +28.140) in room 603;
- Installation of crane embedded parts in room IS102C9;
- Erection of crane structural steelwork in room 505A;
- Installation and concreting of penetrations elements at elev. +8.500 (3 pcs.) and at elev. +11.700 (1 pcs.) was completed;
- Inspection of the existing fire line fixtures;
- Air ducts installation of CCA ventilation system (intake) of non-attended and periodically attended CAVS-S-1 rooms at elev. +5.600;
- Air ducts installation of CCA ventilation system (exhaust) of non-attended and periodically attended CAVS-E-1 rooms at elev. +5.600;
- Mounting of ventilation systems fire retardant valves at elev. +5.600;
- Installation of external fire ladders;
- Installation of lightning protection of the building;
- Facades installation works.
Gate house:
- Repair and finishing of premises;
- Facades installation works were completed.
Installation of equipment (pumps, filters) and pipelines of the sewage treatment facility.
Post-completion and turn-over documentation selection for delivery of works of relevant stages according to the Contract.
Development of testing programs for process units and systems.
The general Сontractor of the project is Holtec Company. Works at the site are performed by Holtec subcontractors: CDI, UTEM, UTB, ZEM, EPI, BEM, Konditsioner. 170 people at the total were engaged in work performance. 6 units of excavation and lifting equipment were also used for implementing tasks at the site.