NSC construction progress as of January 21, 2016

Select another date

Within the NSC Project at the construction site the following works are being performed:

- Removal of snow and ice from the Arch assembly site;
- Delivery of structural steelwork to the site;
- Repair and maintenance of equipment and installations;
- Preparation of secondary and tertiary structural steelwork of the Arch Western part for erection;
- Installation of the Main Cranes System:
* Delivery of MCS components to the site;
* Reassembly of the East bridge (structural);
* Reassembly of the Mobile Tool Platform (electrical part);
* Mounting of MCS crane runways (preparation, adjustment and mounting).

- Arrangement of technological building and auxiliary facilities:
* Technological building (TEC) – installation of partitions out of gas block;
* Electrical Equipment Building (EEB) – installation of cable supports and cable trays;
* Fire Subdivision Access Lock (FSAL) – removal of snow, arrangement of traffic routes;
* Firewater pumping station (FWR) – reinforcement of walls of the building;

- Arrangement of external and internal space of the NSC:
* Storm water catching basins;
* Outdoor underground utility systems.

 