Within the NSC Project at the construction site the following works are being performed:
-Pre-assembly and installation of West End Wall gangways;
-Erection of North Ventilation Centre structural steel;
-Installation of doors in the access ways;
-Installation of automatic jacks of TP-2 tilting panel;
-Completing and erection of cladding purlins;
-Pre-assembly and erection of steel decking packages for cladding, as well as laying of heat insulating material, installation of EPDM membrane and Kalzip panels;
-Assembly of scaffolding and preparation of air ducts for installation, installation of air ducts of the Arch ventilation system;
-Installation of cable conduits for MCS power supply;
-Installation of the Main Cranes System:
* Reassembly of the Mobile Tool Platform.
* Delivery of containers with East bridge components to the Free Access Zone
- Arrangement of technological building and auxiliary facilities:
Technological building (TEC) – walling, roofing (installation of fittings, formwork, concreting, concrete curing);
* Electrical Equipment Building (EEB) – priming, spackling and painting of walls, floors and ceilings, installation of roof heat insulation, installation of staircases;
* Fire Subdivision Access Lock (FSAL) – installation of reinforcement cage and formwork of walls fragments;
* Firewater pumping station (FWR) – installation of fittings and formwork for walling;
* Excavation of pit for diesel generator tanks.
- Arrangement of external and internal space of the NSC:
* Outdoor underground utility systems (installation of cable, water supply, sewage systems).
Erection of structural steel of Western half of the Arch:
Erected in total – 15,178.54 tons
Erection of structural steel of Eastern half of the Arch:
Erected in total – 14,150.9 tons.
During the period from 23.12.2015 to 10.01.2015 construction activities will not be performed.