During the first half of June 2016 at ISF-2 construction site the following works were carried out:

Spent Fuel Processing Facility (SFPF):

- Installation of air ducts for PPS CAVS-3 air supply ventilation system at elev. +11.700;
- Installation of cable routes in premises of the facility;
- Installation of lighting system;
- Finishing of the premises;
- Installation of the cooling system pipelines;
- Installation of pipelines for LRW treatment system special drainage;
- Installation of compressed air system pipelines;
- Installation of pipelines for chemically demineralized water system;

CSM:

- Installation of lightning protection on the modules.

Gate house:

- Electric installation works.

The following works were also performed:

- Laying of power distribution network from automatic throw-over circuit-breaker cabinets to consumers of security equipment;
- Reinstallation of PPS safety gates;
- Installation of ARMS station equipment.

The general Сontractor of the project is Holtec Company. Works at the site are being performed by Holtec subcontractors: CDI, UTEM, UTB, ZEM, EPI, BEM, Kranservis, Konditsioner. 179 people at the total were engaged in work performance.  6 units of earth-moving machinery, lorry, and lifting machines were used for implementing tasks at the site.

June 16, 2016
June 16, 2016
June 16, 2016
June 16, 2016
June 16, 2016
June 16, 2016

Select another date

 

During the period under review, at ISF-2 construction site the following works were carried out:

Spent Fuel Processing Facility (SFPF):

- Installation of cable routes in premises of the facility;
- Installation of lighting system;
- Finishing of the premises;
- Installation of the cooling system pipelines;
- Installation of pipelines for LRW treatment system special drainage;
- Installation of compressed air system pipelines;
- Installation of pipelines for chemically demineralized water system;
- Installation of pumps of auxiliary process systems;
- Installation of pipelines for RAW level monitoring tanks.

CSM:

- Installation of security lighting system;
- Installation of vent grilles;
- Installation of lightning protection on the modules.

Gate house:

- Electric installation works.

The following works were also performed:

- Laying of power distribution network from automatic throw-over circuit-breaker cabinets to consumers of security equipment;
- Reinstallation of PPS safety gates;
- Installation of ARMS station equipment.

The general Сontractor of the project is Holtec Company. Works at the site are being performed by Holtec subcontractors: CDI, UTEM, UTB, ZEM, EPI, BEM, Kranservis, Konditsioner. 181 people at the total were engaged in work performance.  6 units of earth-moving machinery, lorry, and lifting machines were used for implementing tasks at the site.

June 09, 2016
June 09, 2016
June 09, 2016
June 09, 2016
June 09, 2016
June 09, 2016

Select another date

Within the NSC Project at the construction site the following works are being performed:

- Delivery of steelwork to the site;
- Installation of Northern garage floor grating (tertiary structures);
- Installation of special doors of the Arch;
- Installation of TP-5.1, TP-5.2, TP-6 tilting panels automatic jacks;
- Installation of stairs between Western wall walkways;
- Pre-assembly and installation of access hole for MCS Northern garage;
- Installation of purlins of internal and external cladding;
- Installation of external and internal cladding;
- Ventilation system (preparation of air ducts for installation, installation of air ducts, supports, and scaffolding, preparation of NVC for vent systems installation and connection with air ducts).
- Installation of cable supports and cable ducts inside the Maintenance garage. Laying of cable from NVC to Maintenance garage. 

- Main Cranes System (MCS) installation:
* Final leveling (alignment) of crane-runway girders;
* Cutting and installation of tracks. 

- 25t crane for MCS Maintenance garage:
* Crane components have been delivered to the Assembly site; the equipment is undergoing incoming control.

- Arrangement of technological building and auxiliary facilities:
* Technological building (TEC) – installation of reinforcing cages and formwork of TEC walls, heat insulation of roof, primer coating and puttying of walls and ceilings. Overall progress (construction part) – 91 %;
* Electrical Equipment Building (EEB) – installation of cable supports and cable trays, cable routing, and heat insulation of roof. Overall progress (construction part) – 91 %;
* Fire Subdivision Access Lock (FSAL) – heat insulation of roof. Installation of scaffolding, formwork, and reinforcing of the northern floor slab area. Overall progress (construction part) – 88%;
* Firewater pumping station (FWR) – installation of formwork of northern tank foundation; works commenced on reinforcing the foundation for southern tank. Overall progress (construction part) – 99%;
* Diesel power plant area – laying of electrical cables and connection of diesel generators.

- Arrangement of internal and external space of the NSC:
* Outdoor cable routes;
* Outdoor and underground utility systems;
* Storm water catching basins;
* Construction of roads in Local zone.

Erection of Arch western part steelwork: 

Erected in total – 15,793.33 t

Erection of Arch eastern part steelwork: 

Erected in total – 14,265.62 t

June 09, 2016
June 09, 2016
June 09, 2016
June 09, 2016
June 09, 2016
June 09, 2016

Select another date

Within the NSC Project at the construction site the following works are being performed:

- Delivery of steelwork to the site;
- Preparation of Arch western part secondary and tertiary steel structures for erection;
- Installation of Northern garage floor grating (tertiary structures);
- Installation of special doors of the Arch;
- Installation of intrados purlins of West End wall;
- Installation of cladding purlins of South Ventilation Centre;
- Pre-assembly of modules, and elevator shaft construction;
- Installation of crane runway girders for Northern garage 25 t crane;
- Pre-assembly and installation of access hole for MCS Northern garage;
- Installation of TP-5.1, TP-5.2, TP-6 tilting panels automatic jacks;
- Installation of stairs between Western wall walkways #2 at elev.+76.311 and #5 at elev.+78.647;
- Pre-assembly of access stair structures, installation of stair modules;
- Installation of the sealing membrane flashing anchors on TP-5.2 tilting panel;
- Installation of purlins of internal and external cladding;
- Installation of external and internal cladding;
- Ventilation system (preparation of air ducts for installation, installation of air ducts, supports, and scaffolding, preparation of NVC for vent systems installation and connection with air ducts).

 - Main Cranes System (MCS) installation: 

* Leveling (alignment) of crane-runway girders (Arch western part) – works completed;
* Final leveling (alignment) of crane-runway girders (Arch eastern part) – works in progress;
* Cutting and installation of tracks (Arch western part) – works completed;
* Cutting and installation of tracks (Arch eastern part) – works in progress;
* Preparation and repair of standard MCS trolley;
* Installation of wireway for bridges power supply connection.

- 25t crane for MCS Maintenance garage:

 * Crane components have been delivered to the Assembly site; the equipment is undergoing incoming control.

- Arrangement of technological building and auxiliary facilities:

Technological building (TEC) – walling, roofing (reinforcement, formwork, and concreting), and heat insulation of roof;
* Electrical Equipment Building (EEB) – installation of cable supports and cable trays, cable routing and installation of terminations in sections and transformer chambers, installation of doors, and heat insulation of roof;
* Fire Subdivision Access Lock (FSAL) – heat insulation of roof, installation of scaffolding, and formwork;
* Firewater pumping station (FWR) – concrete curing, and surface preparation of the roof;
* FWR tanks area – concrete curing, and reinforcement of the foundation;
* Central control room – walling and roofing (reinforcement, formwork, concreting);
* Diesel power plant site – curing of concrete.

- Arrangement of external and internal space of the NSC:

* Outdoor cable routes;
* Outdoor and underground utility systems;
* Storm water catching basins;
* Construction of roads and sidewalks in Local zone.

Erection of Arch western part steelwork: 

Erected in total – 15,747.83 tons

Erection of Arch eastern part steelwork: 

Erected in total – 14,265.62 tons

June 02, 2016
June 02, 2016
June 02, 2016
June 02, 2016
June 02, 2016
June 02, 2016

Select another date

Within the NSC Project at the construction site the following works are being performed:

- Delivery of steelwork to the site;
- Installation of Northern garage floor grating (tertiary structures);
- Installation of special doors of the Arch;
- Pre-assembly of modules, and elevator shaft construction;
- Installation of crane runway girders for the northern garage 25 t crane;
- Installation of TP-5.1, TP-5.2, TP-6 tilting panels automatic jacks;
- Installation of the sealing membrane flashing anchors on TP-5.2 tilting panel;
- Installation of purlins of internal and external cladding;
- Installation of external and internal cladding. Overall progress is 92%;
- Ventilation system (preparation of air ducts for installation, installation of air ducts, supports, and scaffolding, preparation of NVC for vent systems installation and connection with air ducts). Overall progress is 83%;

- Main Cranes System (MCS) installation:
* Leveling (alignment) of crane-runway girders;
* Installation of prisms for crane-runway girder alignment (Arch western part) – works completed;
* Cutting of tracks, drilling of holes, and installation of tracks – works completed;
* Completing of Eastern bridge power supply installation – works completed;
* Installation of wireway for bridges power supply connection.

- Arrangement of technological building and auxiliary facilities:
* Technological building (TEC) – walling, roofing (reinforcement, formwork, and concreting), and heat insulation of roof. Overall progress (construction) – 88%;
* Electrical Equipment Building (EEB) – installation of cable supports and cable trays, cable layout and installation of terminations in sections and transformer chambers, installation of doors, heat insulation of roof. Overall progress (construction) – 93.5%;
* Fire Subdivision Access Lock (FSAL) – heat insulation of roof, installation of scaffolding, and formwork. Overall progress (construction) – 88%;
* Firewater pumping station (FWR) – concreting of roof, concrete curing, surface preparation of the roof. Overall progress (construction) – 88%;
* FWR tanks area – concrete curing, reinforcement of the foundation;
* Central control room – walling and roofing (reinforcement, formwork, concreting);
* Diesel power plant site – curing of concrete.

- Arrangement of external and internal space of the NSC:
* Outdoor cable routes (cable laying);
* Outdoor, underground utility systems;
* Storm water catching basin;
* Construction of roads in Local zone.

Erection of Arch western part structural steelwork:
Erected in total – 15,685.85 tons

Erection of Arch eastern part structural steelwork:
Erected in total – 14,265.62 tons

May 26, 2016
May 26, 2016
May 26, 2016
May 26, 2016
May 26, 2016
May 26, 2016