Within the NSC Project at the construction site the following works are being performed:
-Pre-assembly and installation of West End Wall gangways;
-Installation of cable conduits bearers;
-Erection of structural steel of North Ventilation Centre;
-Installation of doors in the access ways;
-Installation of automatic jacks of TP-2 tilting panel;
-Completing and erection of cladding purlins;
-Pre-assembly and erection of steel decking packages for cladding, as well as laying of heat insulating material, installation of EPDM membrane and Kalzip panels;
-Assembly of scaffolding and preparation of air ducts for installation, installation of air ducts of the Arch ventilation system;
-Installation of cable conduits for MCS power supply;
-Installation of the Main Cranes System (07.12.2015 the procedure of transferring the load from the lifting system to the crane beams was completed, moving of the West bridge to the parking position is scheduled to be performed during the week).

- Arrangement of technological building and auxiliary facilities:
Technological building (TEC) – walling, roofing (installation of fittings, formwork, concreting, concrete curing);
* Electrical Equipment Building (EEB) – priming, spackling and painting of walls, floors and ceilings, installation of roof heat insulation;
* Fire Subdivision Access Lock (FSAL) – installation of reinforcement cage and formwork of walls fragments;
* Firewater pumping station (FWR) – foundation concrete curing;
* Slopes reinforcement of pit for diesel generator tanks.

Erection of structural steel of Western half of the Arch:
Erected in total – 15,162.58 tons

Erection of structural steel of Eastern half of the Arch:
Erected in total – 14,149.36 tons.

 

10 грудня 2015 року
10 грудня 2015 року
10 грудня 2015 року
10 грудня 2015 року
10 грудня 2015 року
10 грудня 2015 року

Select another date

Within the NSC Project at the construction site the following works are being performed:
-Pre-assembly and installation of West End Wall gangways;
-Installation of cable conduits bearers;
-Erection of North Ventilation Centre structural steel;
-Installation of the sealing membrane flashing anchor on TP-2 tilting panel;
-Installation of automatic jacks of TP-2 tilting panel;
-Completing and erection of cladding purlins;
-Pre-assembly and erection of steel decking packages for cladding, as well as laying of heat insulating material, installation of EPDM membrane and Kalzip panels;
-Assembly of scaffolding and preparation of air ducts for installation, installation of air ducts of the Arch ventilation system;
-Installation of cable conduits for MCS power supply;
-Installation of the Main Cranes System (28.11.2015 MCS west bridge jacking was completed, work is underway on roller beam installation in the project position).

- Arrangement of technological building and auxiliary facilities:
* Technological building (TEC) – walling, roofing (installation of fittings, formwork, concreting, concrete curing);
* Electrical Equipment Building (EEB) – priming, spackling and painting of walls, floors and ceilings, installation of roof heat insulation;
* Fire Subdivision Access Lock (FSAL) – installation of reinforcement cage and walls fragments formwork;
* Firewater pumping station (FWR) –concrete curing of the foundation.

- Arrangement of external and internal space of NSC:
* Storm water ponds (concrete curing of the monolithic slab);
* Outdoor underground services (power supply, water supply, sewage).

Assembly of metal structures of Western half of the Arch:
Metal structures assembled in total – 15,136.02 tons

Assembly of metal structures of Eastern half of the Arch:
Metal structures assembled in total –  14,138.22 tons

 

December 03, 2015
December 03, 2015
December 03, 2015
December 03, 2015
December 03, 2015
December 03, 2015

Select another date

During the second half of November at ISF-2 construction site the following works were carried out:

Spent Fuel Processing Facility (SFPF):
- Startup finishing operations (plastering) in premises at elevations +17.000; +21.300;
- Installation of embedded element of guiding pipe for canisters transportation double cover system;
- Installation of external fire ladders;
- Installation of temporary roof structures for mounting holes was completed;
- St.steel cladding (t=8mm) of protective channel IS102D1 (elev. +16.450);
- Cladding of rooms 111А, 111В, 305;
- Installation of transformers in electrical rooms;
- Installation of embedded elements of penetrations in ISFPS room 501 – 23 of 57 elements were installed and embedded in concrete;
- Installation of embedded elements of crane MIS-CR-220 in room 504;
- Air ducts installation of CCA ventilation system (inflow) of non-attended and periodically attended CAVS-S-1 rooms at elev. +0.000;
- Major repair of external fire stairway P2;
- Installation of water supply systems pipelines B1, T3, T4 was completed.

Gate house:
- Repair and finishing of premises;
- Installation of cable structures of power supply systems of the 1st floor;
- Installation of facades of buildings;
- Installation of lighting system of the 1st floor.

Physical Protection System (PPS):
- Installation of operating and backup power supply system (in ducts, in trench) for security lighting of the site perimeter;
- Restoration of fences (installation of new posts) of PPS perimeter;

The general Сontractor of the project is Holtec Company. Works are performed at the site by Holtec subcontractors: CDI, UTEM, UTB, ZEM, EPI, BEM, Promkomplekt, UTEM-KRANSERVIS. 222 people at the total were engaged in work performance. 11 units of excavation and lifting equipment were used for implementing the tasks at the site.

December 03, 2015
December 03, 2015
December 03, 2015
December 03, 2015
December 03, 2015
December 03, 2015

Select another date

Within the NSC Project at the construction site the following works are being performed:
- Pre-assembling and installation of Western end wall gangways;
- Installation of cable conduits bearers;
- Installation of Northern ventilation center metal structures;
- Installation of crane beams at East and West halves' connection point; 
- Installation of automatic jacks of TP-2 tilting panel;
- Completing and assembly of cladding purlines;
- Preliminary erection and assembly of steel plating packages for cladding, as well as laying of heat insulating material, assembly of EPDM membrane, assembly Kalzip panels;
- Assembly of scaffolding and preparation of air ducts for assembling, assembly of air ducts of the Arch ventilation system;
- Installation of cable ducts for Main Cranes System's power supply;
- Installation of Main Cranes System elements (25-11-2015 jacking of MCS started, 25-11-2015 the West Bridge jacked to 100 mm up, 26-11-2015 the West Bridge jacked to 20 meters up, work is underway).

- Arrangement of technological building and auxiliary facilities:
* Technological building (TB) – walling, roofing (assembly of fittings and formwork, concreting, concrete curing);
* Electrical device building – priming, spackling and painting of walls, floors and ceilings, installation of roof heat insulation;
* Fire units acces airlock - interior finish;
* Fire pumping station (assembly of formwork).

- Arrangement of external and internal space of NSC (northern side):
* Hinged bearers gallery (North strip, wall concreting)
* Outdoor underground services (power supply, water supply, sewer).

Assembly of metal structures of Western half of the Arch:

Metal structures assembled in total – 15,124.58 tons

Assembly of metal structures of Eastern half of the Arch:

Metal structures assembled in total –  14,138.22 tons

 