During the first half of December at ISF-2 construction site the following works were carried out:
Spent Fuel Processing Facility (SFPF):
- Startup finishing operations (plastering) in premises at elevation +21.300;
- Installation of external fire ladders;
- Cladding of rooms 111А, 111В, 305;
- Installation of transformers in electrical rooms;
- Installation of embedded parts of penetrations in ISFPS room 501 – 50 of 57 parts were installed and embedded in concrete;
- Air ducts installation of CCA ventilation system (intake and exhaust) of non-attended and periodically attended CAVS-S-1 rooms at elev. +0.000;
- Major repair of external fire stairway P2, except the upper stairway;
- Installation of hot water supply system equipment in room 133 was completed;
- Installation of lightning protection;
- Facades installation works.
Gate house (GH):
- Repair and finishing of premises;
- Installation of air-handling unit was completed.
Physical Protection System (PPS):
- Arrangement of security patrol route –foundation, slabs placement;
- Restoration of fences (installation of new posts) of PPS perimeter.
Installation of equipment (pumps, filters) of the sewage treatment facility.
Installation of cable structures in pits and installation of grounding.
The general Сontractor of the project is Holtec Company. Works at the site are performed by Holtec subcontractors: CDI, UTEM, UTB, ZEM, EPI, BEM, Promkomplekt, UTEM-Kranservis, Konditsioner. 244 people at the total were engaged in work performance. 11 units of excavation and lifting equipment were also used for implementing tasks at the site.