Within the NSC Project at the construction site the following works are being performed:

- Delivery of structural steelwork to the site;
- Installation of Northern garage floor grating (tertiary structures);
- Installation of special doors of the Arch;
- Installation of TP-4 tilting panel hinged joints;
- Preparation of secondary and tertiary structural steelwork of the Arch western part for erection;
- Installation of purlins of internal and external cladding;
- Installation of external and internal cladding;
- Ventilation system (preparation of air ducts for installation, installation of air ducts, supports and scaffolding);

- MCS mounting:
* Reassembly of the East bridge – installation of electrical and mechanical part;
* Installation of cable supports and cable ducts inside the Arch Maintenance garage;
* Mounting of MCS crane runways (preparation, adjustment and mounting).

- Arrangement of technological building and auxiliary facilities:
* Technological building (TEC) – walling, roofing (reinforcement, formwork, concreting);
* Electrical Equipment Building (EEB) – installation of cable supports, cable trays, and transformers;
* Fire Subdivision Access Lock (FSAL) – walling (reinforcement, formwork, concreting);
* Firewater pumping station (FWR) – reinforcement of walls of the building, installation of formwork, concreting;
* Central control room – walling (reinforcement, formwork, concreting). 

- Arrangement of external and internal space of the NSC:
* Outdoor cable routes;
* Outdoor, underground utility systems;
* Storm water catching basins.

Assembly of metal structures of Western half of the Arch:
Metal structures assembled in total – 15,302.69 tons

Assembly of metal structures of Eastern half of the Arch:
Metal structures assembled in total – 14,150.9 tons

Select another date

Within the NSC Project at the construction site the following works are being performed:

- Delivery of structural steelwork to the site;
- Installation of Northern garage floor grating (tertiary structures);
- Installation of special doors of the Arch;
- Installation of TP-4 tilting panel hinged joints;
- Preparation of secondary and tertiary structural steelwork of the Arch western part for erection;
- Installation of purlins of internal and external cladding;
- Installation of external and internal cladding;
- Ventilation system (preparation of air ducts for installation, installation of air ducts, supports and scaffolding);

- MCS mounting:
* Reassembly of the East bridge – installation of electrical and mechanical part;
* Installation of cable supports and cable ducts inside the Arch Maintenance garage;
* Mounting of MCS crane runways (preparation, adjustment and mounting).

- Arrangement of technological building and auxiliary facilities:
* Technological building (TEC) – walling, roofing (reinforcement, formwork, concreting);
* Electrical Equipment Building (EEB) – installation of cable supports, cable trays, and transformers;
* Fire Subdivision Access Lock (FSAL) – walling (reinforcement, formwork, concreting);
* Firewater pumping station (FWR) – reinforcement of walls of the building, installation of formwork, concreting;
* Central control room – walling (reinforcement, formwork, concreting). 

- Arrangement of external and internal space of the NSC:
* Outdoor cable routes;
* Outdoor, underground utility systems;
* Storm water catching basins.

Assembly of metal structures of Western half of the Arch:
Metal structures assembled in total – 15,285.36 tons

Assembly of metal structures of Eastern half of the Arch:
Metal structures assembled in total – 14,150.9 tons

February 18, 2016
February 18, 2016
February 18, 2016
February 18, 2016
February 18, 2016
February 18, 2016

 

 

Select another date

Within the NSC Project at the construction site the following works are being performed:

- Delivery of structural steelwork to the site;
- Installation of Northern garage floor grating (tertiary structures);
- Installation of special doors of the Arch;
- Installation of TP-4 tilting panel hinged joints;
- Preparation of secondary and tertiary structural steelwork of the Arch western part for erection;
- Installation of purlins of internal and external cladding;
- Installation of external and internal cladding;
- Ventilation system (preparation of air ducts for installation, installation of air ducts, supports and scaffolding);

- MCS mounting:
* Reassembly of the East bridge – installation of electrical and mechanical part;
* Installation of cable supports and cable ducts inside the Arch Maintenance garage;
* Mounting of MCS crane runways (preparation, adjustment and mounting).

- Arrangement of technological building and auxiliary facilities:
* Technological building (TEC) – walling, roofing (reinforcement, formwork, concreting);
* Electrical Equipment Building (EEB) – installation of cable supports, cable trays, and transformers;
* Fire Subdivision Access Lock (FSAL) – walling (reinforcement, formwork, concreting);
* Firewater pumping station (FWR) – reinforcement of walls of the building, installation of formwork, concreting;
* Central control room – walling (reinforcement, formwork, concreting). 

- Arrangement of external and internal space of the NSC:
* Outdoor cable routes;
* Outdoor, underground utility systems;
* Storm water catching basins.

 

February 11, 2016
February 11, 2016
February 11, 2016
February 11, 2016
February 11, 2016
February 11, 2016

Select another date

Within the NSC Project at the construction site the following works are being performed:

- Removal of snow and ice from the Arch assembly site;
- Delivery of structural steelwork to the site;
- Installation of Northern garage floor grating (tertiary structures);
- Installation of special doors of the Arch;
- Preparation of secondary and tertiary structural steelwork of the Arch western part for erection;
- Installation of purlins of internal and external cladding;
- Ventilation system (preparation of air ducts for installation, installation of air ducts, supports and scaffolding);

- MCS mounting:
* Reassembly of the East bridge – assembly of structures, installation of electrical part;
* Installation of cable supports and cable ducts inside the Arch Maintenance garage;
* Mounting of MCS crane runways (preparation, adjustment and mounting).

- Arrangement of technological building and auxiliary facilities:
* Technological building (TEC) – walling, roofing (reinforcement, formwork, concreting);
* Electrical Equipment Building (EEB) – installation of cable supports, cable trays, and transformers;
* Fire Subdivision Access Lock (FSAL) – walling (reinforcement, formwork, concreting);
* Firewater pumping station (FWR) – reinforcement of walls of the building;
* Central control room – walling (reinforcement, formwork, concreting). 

- Arrangement of external and internal space of the NSC:
* Outdoor cable routes;
* Outdoor, underground utility systems. 

 

February 04, 2016
February 04, 2016
February 04, 2016
February 04, 2016
February 04, 2016
February 04, 2016

Select another date

Within the NSC Project at the construction site the following works are being performed:

- Removal of snow and ice from the Arch assembly site;
- Delivery of structural steelwork to the site;
- Repair and maintenance of equipment and installations;
- Preparation of secondary and tertiary structural steelwork of the Arch Western part for erection;
- Installation of purlins of internal and external cladding;
- Installation of the Main Cranes System:
* Delivery of MCS components to the site;
* Reassembly of the East bridge (structural);
* Reassembly of the Mobile Tool Platform (electrical part);
* Mounting of MCS crane runways (preparation, adjustment and mounting).

- Arrangement of technological building and auxiliary facilities:
* Technological building (TEC) – walling, roofing (reinforcement, formwork, concreting);
* Electrical Equipment Building (EEB) – installation of cable supports and cable trays;
* Fire Subdivision Access Lock (FSAL) – walling (reinforcement, formwork, concreting);
* Firewater pumping station (FWR) – reinforcement of walls of the building;
* Central control room – walling (reinforcement, formwork, concreting).

- Arrangement of external and internal space of the NSC:
* Outdoor cable routes;
* Outdoor underground utility systems.

 