Within the NSC Project at the construction site the following works are being performed:
- Supply of metal structures to the site;
- Installation of protective shielding of North Garage;
- Installation of special doors of the Arch;
- Installation of automatic jacks of  tilting panels TP-5.1, TP-5.2, TP-6;
- Mounting of cable tracks of control instrumentation of north and south ventilation centers;
- Pre-assembling of monorail crane structures in South Ventilation Center;
- Installation of internal and external casing girders;
- Mounting of external and internal casing;
- Ventilation system (preparing the air ducts for installation, installation of air ducts, installation of supports and scaffolding, preparing the North Ventilation Center (NVC) for installation of ventilation equipment).

- Main Cranes System (MCS) installation:
* Adjusting the crane beams;
* Cutting and installation of rails are being performed.

- 25t crane for MCS Maintenance garage:
* Preparatory activities for crane erection;
* Final adjustment of crane beams and mounting of rails.

- Arrangement of technological building and auxiliary facilities:
* Terms of Reference (ToR) – installation of reinforcing cages and wall formworks, roof sealing, pre-coating, coating of walls and ceilings;
* Building of electrical devices – installation of cable supports and trays, cable grooming, roof sealing;
* Access gateway for fire brigades – roof sealing;
* Fire pump station (FPS) – installation of foundation formworks for north and south storage tanks; activities on repair and preparation for coating and painting of internal wall surfaces of FPS building;
* Site of diesel power plant for power supply – laying the electrical cables and connecting diesel generators.

- Arrangement of internal and external space of the NSC:

* Outdoor cable routes;
* Outdoor and underground utility systems;
* Storm water catching basins;
* Construction of roads in Local zone.

Erection of Arch western part steelwork: 

Erected in total – 15,860.16 t

Erection of Arch eastern part steelwork: 

Erected in total – 14,265.62 t

June 23, 2016
June 23, 2016
June 23, 2016

Select another date

Within the NSC Project at the construction site the following works are being performed:

- Delivery of steelwork to the site;
- Installation of protective shielding of Northern garage;
- Installation of special doors of the Arch;
- Installation of TP-5.1, TP-5.2, TP-6 tilting panels automatic jacks;
- Installation of control and instrumentation cable routes of Northern and Southern Ventilation Centres;
- Pre-assembly of monorail crane components in Southern Ventilation Centre;
- Pre-assembly and installation of access hole for MCS Northern garage (works completed);
- Installation of purlins of internal and external cladding;
- Installation of external and internal cladding. Overall progress – 95%;
- Ventilation system (preparation of air ducts for installation, installation of air ducts, supports and scaffolding, preparation of NVC for vent systems installation. Air ducts installed – 86%;
- Installation of cable supports and cable ducts inside the Maintenance garage. Cable routing from NVC to Maintenance garage. 

- Main Cranes System (MCS) installation:

* Leveling (alignment) of crane-runway girders;
* Cutting and installation of tracks. 

- 25t crane for MCS Maintenance garage:

* Crane components have been delivered to the Assembly site; 
* Final leveling of crane-runway girders and installation of tracks.

- Arrangement of technological building and auxiliary facilities:

* Technological building (TEC) – walling and roofing (reinforcement, formwork, concreting). Overall progress (construction part) – 91.5%;
* Electrical Equipment Building (EEB) – installation of cable supports, cable trays, and staircase. Overall progress (construction part) – 100%;
* Fire Subdivision Access Lock (FSAL) – construction works completed. Finishing of the premise is underway. Overall progress (construction part) – 100%;
* Firewater pumping station (FWR) – roofing (installation of scaffolding and formwork). Overall progress (construction part) – 99%. Reinforcement works for foundations for tanks.

- Arrangement of internal and external space of the NSC:

* Outdoor cable routes;
* Outdoor and underground utility systems;
* Storm water catching basins;
* Construction of roads in Local zone.

Erection of Arch western part steelwork: 

Erected in total – 15,827.45 t

Erection of Arch eastern part steelwork: 

Erected in total – 14,265.62 t

16 червня 2016 року
16 червня 2016 року
16 червня 2016 року
16 червня 2016 року
16 червня 2016 року
16 червня 2016 року

Select another date

Within the NSC Project at the construction site the following works are being performed:

- Delivery of steelwork to the site;
- Installation of Northern garage floor grating (tertiary structures);
- Installation of special doors of the Arch;
- Installation of TP-5.1, TP-5.2, TP-6 tilting panels automatic jacks;
- Installation of stairs between Western wall walkways;
- Pre-assembly and installation of access hole for MCS Northern garage;
- Installation of purlins of internal and external cladding;
- Installation of external and internal cladding;
- Ventilation system (preparation of air ducts for installation, installation of air ducts, supports, and scaffolding, preparation of NVC for vent systems installation and connection with air ducts).
- Installation of cable supports and cable ducts inside the Maintenance garage. Laying of cable from NVC to Maintenance garage. 

- Main Cranes System (MCS) installation:
* Final leveling (alignment) of crane-runway girders;
* Cutting and installation of tracks. 

- 25t crane for MCS Maintenance garage:
* Crane components have been delivered to the Assembly site; the equipment is undergoing incoming control.

- Arrangement of technological building and auxiliary facilities:
* Technological building (TEC) – installation of reinforcing cages and formwork of TEC walls, heat insulation of roof, primer coating and puttying of walls and ceilings. Overall progress (construction part) – 91 %;
* Electrical Equipment Building (EEB) – installation of cable supports and cable trays, cable routing, and heat insulation of roof. Overall progress (construction part) – 91 %;
* Fire Subdivision Access Lock (FSAL) – heat insulation of roof. Installation of scaffolding, formwork, and reinforcing of the northern floor slab area. Overall progress (construction part) – 88%;
* Firewater pumping station (FWR) – installation of formwork of northern tank foundation; works commenced on reinforcing the foundation for southern tank. Overall progress (construction part) – 99%;
* Diesel power plant area – laying of electrical cables and connection of diesel generators.

- Arrangement of internal and external space of the NSC:
* Outdoor cable routes;
* Outdoor and underground utility systems;
* Storm water catching basins;
* Construction of roads in Local zone.

Erection of Arch western part steelwork: 

Erected in total – 15,793.33 t

Erection of Arch eastern part steelwork: 

Erected in total – 14,265.62 t

June 09, 2016
June 09, 2016
June 09, 2016
June 09, 2016
June 09, 2016
June 09, 2016

Select another date

Within the NSC Project at the construction site the following works are being performed:

- Delivery of steelwork to the site;
- Preparation of Arch western part secondary and tertiary steel structures for erection;
- Installation of Northern garage floor grating (tertiary structures);
- Installation of special doors of the Arch;
- Installation of intrados purlins of West End wall;
- Installation of cladding purlins of South Ventilation Centre;
- Pre-assembly of modules, and elevator shaft construction;
- Installation of crane runway girders for Northern garage 25 t crane;
- Pre-assembly and installation of access hole for MCS Northern garage;
- Installation of TP-5.1, TP-5.2, TP-6 tilting panels automatic jacks;
- Installation of stairs between Western wall walkways #2 at elev.+76.311 and #5 at elev.+78.647;
- Pre-assembly of access stair structures, installation of stair modules;
- Installation of the sealing membrane flashing anchors on TP-5.2 tilting panel;
- Installation of purlins of internal and external cladding;
- Installation of external and internal cladding;
- Ventilation system (preparation of air ducts for installation, installation of air ducts, supports, and scaffolding, preparation of NVC for vent systems installation and connection with air ducts).

 - Main Cranes System (MCS) installation: 

* Leveling (alignment) of crane-runway girders (Arch western part) – works completed;
* Final leveling (alignment) of crane-runway girders (Arch eastern part) – works in progress;
* Cutting and installation of tracks (Arch western part) – works completed;
* Cutting and installation of tracks (Arch eastern part) – works in progress;
* Preparation and repair of standard MCS trolley;
* Installation of wireway for bridges power supply connection.

- 25t crane for MCS Maintenance garage:

 * Crane components have been delivered to the Assembly site; the equipment is undergoing incoming control.

- Arrangement of technological building and auxiliary facilities:

Technological building (TEC) – walling, roofing (reinforcement, formwork, and concreting), and heat insulation of roof;
* Electrical Equipment Building (EEB) – installation of cable supports and cable trays, cable routing and installation of terminations in sections and transformer chambers, installation of doors, and heat insulation of roof;
* Fire Subdivision Access Lock (FSAL) – heat insulation of roof, installation of scaffolding, and formwork;
* Firewater pumping station (FWR) – concrete curing, and surface preparation of the roof;
* FWR tanks area – concrete curing, and reinforcement of the foundation;
* Central control room – walling and roofing (reinforcement, formwork, concreting);
* Diesel power plant site – curing of concrete.

- Arrangement of external and internal space of the NSC:

* Outdoor cable routes;
* Outdoor and underground utility systems;
* Storm water catching basins;
* Construction of roads and sidewalks in Local zone.

Erection of Arch western part steelwork: 

Erected in total – 15,747.83 tons

Erection of Arch eastern part steelwork: 

Erected in total – 14,265.62 tons

June 02, 2016
June 02, 2016
June 02, 2016
June 02, 2016
June 02, 2016
June 02, 2016

Select another date

Within the NSC Project at the construction site the following works are being performed:

- Delivery of steelwork to the site;
- Installation of Northern garage floor grating (tertiary structures);
- Installation of special doors of the Arch;
- Pre-assembly of modules, and elevator shaft construction;
- Installation of crane runway girders for the northern garage 25 t crane;
- Installation of TP-5.1, TP-5.2, TP-6 tilting panels automatic jacks;
- Installation of the sealing membrane flashing anchors on TP-5.2 tilting panel;
- Installation of purlins of internal and external cladding;
- Installation of external and internal cladding. Overall progress is 92%;
- Ventilation system (preparation of air ducts for installation, installation of air ducts, supports, and scaffolding, preparation of NVC for vent systems installation and connection with air ducts). Overall progress is 83%;

- Main Cranes System (MCS) installation:
* Leveling (alignment) of crane-runway girders;
* Installation of prisms for crane-runway girder alignment (Arch western part) – works completed;
* Cutting of tracks, drilling of holes, and installation of tracks – works completed;
* Completing of Eastern bridge power supply installation – works completed;
* Installation of wireway for bridges power supply connection.

- Arrangement of technological building and auxiliary facilities:
* Technological building (TEC) – walling, roofing (reinforcement, formwork, and concreting), and heat insulation of roof. Overall progress (construction) – 88%;
* Electrical Equipment Building (EEB) – installation of cable supports and cable trays, cable layout and installation of terminations in sections and transformer chambers, installation of doors, heat insulation of roof. Overall progress (construction) – 93.5%;
* Fire Subdivision Access Lock (FSAL) – heat insulation of roof, installation of scaffolding, and formwork. Overall progress (construction) – 88%;
* Firewater pumping station (FWR) – concreting of roof, concrete curing, surface preparation of the roof. Overall progress (construction) – 88%;
* FWR tanks area – concrete curing, reinforcement of the foundation;
* Central control room – walling and roofing (reinforcement, formwork, concreting);
* Diesel power plant site – curing of concrete.

- Arrangement of external and internal space of the NSC:
* Outdoor cable routes (cable laying);
* Outdoor, underground utility systems;
* Storm water catching basin;
* Construction of roads in Local zone.

Erection of Arch western part structural steelwork:
Erected in total – 15,685.85 tons

Erection of Arch eastern part structural steelwork:
Erected in total – 14,265.62 tons

May 26, 2016
May 26, 2016
May 26, 2016
May 26, 2016
May 26, 2016
May 26, 2016