Within the NSC Project at the construction site the following works are being performed:
- Delivery of structural steelwork to the site;
- Installation of Northern garage floor grating (tertiary structures);
- Installation of special doors of the Arch;
- Pre-assembly of modules, and elevator shaft construction;
- Installation of TP-5.1 tilting panel automatic jacks;
- Installation of purlins of internal and external cladding;
- Installation of external and internal cladding. Overall progress is 86%;
- Ventilation system (preparation of air ducts for installation, installation of air ducts, supports and scaffolding, preparation of NVC for vent systems installation, and connection with air ducts). Overall progress is 81%;
- Main Crane System (MCS) installation:
* Lifting of the East Bridge was completed (01/04/2016);
* The Contractor carries out works on transferring the load from the lifting system to the main building;
* Installation of cable supports and cable channels inside the Arch Maintenance garage.
- Arrangement of technological building and auxiliary facilities:
* Technological building (TEC) – walling, roofing (reinforcement, formwork, concreting). Overall progress (construction) – 82%;
* Electrical Equipment Building (EEB) – installation of cable supports, cable trays and transformers, cable layout and installation of termination in sections and transformer chambers. Overall progress (construction) – 93%;
* Fire Subdivision Access Lock (FSAL) – walling (priming, spackling and painting of walls, floors and ceilings, installation of roof heat insulation). Overall progress (construction) – 88%;
* Firewater pumping station (FWR) – installation of slabs (installation of scaffolding and formwork) – 62%;
* Central control room – walling (reinforcement, formwork, concreting);
* Diesel power station area (concreting of the foundation slab).
- Arrangement of external and internal space of the NSC:
* Outdoor cable routes;
* Outdoor, underground utility systems;
* Storm water catching basin;
* Arch End walls (south-east);
* Pot-bearing gallery walls;
* Extension of Restricted Access Zone;
* Construction of roads in Local zone.
Erection of Arch western part structural steelwork:
Erected in total – 15,477 tons
Erection of Arch eastern part structural steelwork:
Erected in total – 14,174.91 tons