Within the NSC Project at the construction site the following works are being performed:
- Supply of metal structures to the site;
- Mounting of hydraulic jacks for the Arch sliding;
- Installation of special doors of the Arch;
- Installation of sealing membrane of tilting panels;
- Installation of cable routes for control and measuring instruments of North and South Ventilation Centers;
- Installation of protective shielding of North Garage;
- Installation of external and internal cladding;
- Ventilation system (preparing the air ducts for installation, installation of air ducts, installation of supports and scaffolding, preparing the North Ventilation Center (NVC) for installation of ventilation equipment);
- Start of delivering the NSC’s ventilation stack elements.

- Main Cranes System (MCS) installation:
* Adjusting the crane beams and rails;
* Preparing the MCS bridges for rerolling to west side of the Arch;
* MCS temporary control board installed. Adjusting the control system.

- Erection of 25t crane for MCS maintenance garage:
* Installation of electrical crane equipment.

- Arrangement of technological building and auxiliary facilities:
* Technological building (TEC) – works relating to polishing, pre-coating, filling with putty and painting of walls and ceilings inside the building, installation of doors, installation of dividing walls from gas blocks;
* Electrical Equipment Building (EEB) – installation of fire alarm system within premises, mounting of cable supports and trays, installation of supports and pipes for fire-preventive and drinking water supply;
* Access gateway for fire brigades – roof water isolation, installation of pipelines for fire-preventive and drinking water supply, laying electrical cables;
* Fire pump station (FPS) – works relating to pre-coating, filling with putty and painting of walls inside the building;
* Site of diesel power plant for power supply – laying electrical cables and connecting diesel generators.

- Arrangement of internal and external space of the NSC:
* Outdoor cable routes;
* Outdoor and underground utility systems;
* Storm water collecting basins;
* Construction of roads in the Local Zone.

Erection of Arch western part steelwork:
Erected in total
– 15,931.41 t

Erection of Arch eastern part steelwork:
Erected in total
– 14,265.62 t

July 28, 2016
July 28, 2016
July 28, 2016
July 28, 2016
July 28, 2016
July 28, 2016

Select another date

Within the NSC Project at the construction site the following works are being performed:
- Supply of metal structures to the site;
- Supply of hydraulic jacks to the site for the Arch sliding;
- Installation of special doors of the Arch;
- Installation of sealing membrane of tilting panels;
- Installation of cable routes for control and measuring instruments of North and South Ventilation Centers;
- Installation of protective shielding of North Garage;
- Installation of external and internal cladding. Total progress – 98%;
- Ventilation system (preparing the air ducts for installation, installation of air ducts, installation of supports and scaffolding, preparing the North Ventilation Center (NVC) for installation of ventilation equipment). Progress – 88 %;

Main Cranes System (MCS) installation:

- Adjusting the crane beams and rails;
- Preparing the MCS bridges for rerolling to west side of the Arch;
- Preparing for mounting a bottom platform of a mobile tool platform (MTP) – completed;
- Installation of MCS control boards for subsequent testing the crane.

- Erection of 25t crane for MCS maintenance garage:
* Installation of electrical crane equipment.

- Arrangement of technological building and auxiliary facilities:
* Technological building (TEC) – works relating to polishing, pre-coating, filling with putty and painting of walls and ceilings inside the building, installation of doors. Progress (construction part – 93%);
* Electrical Equipment Building (EEB) – installation of fire alarm system within premises, mounting of cable supports and trays, installation of supports and pipes for fire-preventive and drinking water supply. Progress (construction part) – 100%;
* Access gateway for fire brigades – roof water isolation, installation of pipelines for fire-preventive and drinking water supply, laying electrical cables;
* Fire pump station (FPS) – works relating to pre-coating, filling with putty and painting of walls inside the building;
* Site of diesel power plant for power supply – laying electrical cables and connecting diesel generators.

- Arrangement of internal and external space of the NSC:
* Outdoor cable routes;
* Outdoor and underground utility systems;
* Storm water collecting basins;
* Construction of roads in the Local Zone.

Erection of Arch western part steelwork:
Erected in total
– 15,917.11 t

Erection of Arch eastern part steelwork:
Erected in total
– 14,265.62 t

July 21, 2016
July 21, 2016
July 21, 2016
July 21, 2016
July 21, 2016
July 21, 2016

Select another date

Within the NSC Project at the construction site the following works are being performed:

- Delivery of steelwork to the site;
- Installation of special doors of the Arch;
- Adjustment of automated jacks of tilting panels TP-5.1, TP-5.2, TP-6;
- Installation of tilting panels sealing membrane;
- Installation of cable routes for control and instrumentation of Northern and Southern Ventilation Centres;
- Installation of Northern garage protective shielding;
- Installation of external and internal cladding. Overall progress – 96%;
- Ventilation system (preparation of air ducts for installation, installation of air ducts, supports and scaffolding, preparation of NVC for vent systems installation. Progress – 88%

- Main Cranes System (MCS) installation:

* Final leveling of crane-runway girders;
* Cutting and installation of tracks.

- 25t crane for MCS Maintenance garage:

* Reassembly of crane;
* Final leveling of crane-runway girders and installation of tracks (works completed).

- Arrangement of technological building and auxiliary facilities:

* Technological building (TEC) – installation of reinforcement cages and formwork of walls, and heat insulation of roof. Overall progress (construction part) – 93%;
* Electrical Equipment Building (EEB) – installation of cable supports and cable trays,  cable layout, heat insulation of roof. Progress (construction part) – 100%;
* Fire Subdivision Access Lock (FSAL) – finishing of the building and heat insulation of roof;
* Firewater pumping station (FWR) – construction works completed. Finishing of the building and heat insulation of roof. 

- Arrangement of internal and external space of the NSC:

* Outdoor cable routes;
* Outdoor and underground utility systems;
* Storm water catching basins;
* Construction of roads in Local zone.

Erection of Arch western part steelwork: 

Erected in total – 15,906.47 t

Erection of Arch eastern part steelwork: 

Erected in total – 14,265.62 t

July 14, 2016
July 14, 2016
July 14, 2016
July 14, 2016
July 14, 2016
July 14, 2016

Select another date

Within the NSC Project at the construction site the following works are being performed:

- Delivery of steelwork to the site;
- Installation of special doors of the Arch;
- Adjustment of automated jacks of tilting panels TP-5.1, TP-5.2, TP-6;
- Installation of tilting panels sealing membrane;
- Installation of cable routes for control and instrumentation of Northern and Southern Ventilation Centres;
- Installation of Northern garage protective shielding;
- Installation of external and internal cladding. Overall progress – 96.21%;
- Ventilation system (preparation of air ducts for installation, installation of air ducts, supports and scaffolding, preparation of NVC for vent systems installation. Progress – 86%

- Main Cranes System (MCS) installation:

* Final leveling of crane-runway girders;
* Cutting and installation of tracks.

- 25t crane for MCS Maintenance garage:

* Reassembly of crane;
* Final leveling of crane-runway girders and installation of tracks.

- Arrangement of technological building and auxiliary facilities:

* Technological building (TEC) – installation of reinforcing cages and formwork of walls, heat insulation of roof, primer coating and puttying of walls and ceilings. Overall progress (construction part) – 93%;
* Electrical Equipment Building (EEB) – installation of cable supports and cable trays, cable layout, heat insulation of roof. Progress (construction part) – 100%;
* Fire Subdivision Access Lock (FSAL) – heat insulation of roof. Progress (construction part) – 100%;
* Firewater pumping station (FWR) – installation of formwork of northern and southern tanks. Works on repair and preparation of inner surfaces of FWR building walls for puttying and painting are being carried out. Progress (construction part) – 99%;
* Diesel power plant area – laying of electrical cables, connection of diesel-generators.

- Arrangement of internal and external space of the NSC:

* Outdoor cable routes;
* Outdoor and underground utility systems;
* Storm water catching basins;
* Construction of roads in Local zone.

Erection of Arch western part steelwork: 

Erected in total – 15,896.47 t

Erection of Arch eastern part steelwork: 

Erected in total – 14,265.62 t

July 07, 2016
July 07, 2016
July 07, 2016
July 07, 2016
July 07, 2016
July 07, 2016

Select another date

Within the NSC Project at the construction site the following works are being performed:

- Delivery of steelwork to the site;
- Installation of special doors of the Arch;
- Adjustment of automated jacks of tilting panels TP-5.1, TP-5.2, TP-6;
- Installation of cable routes for control and instrumentation of Northern and Southern Ventilation Centres;
- Installation of monorail crane in Southern Ventilation Centre;
- Installation of Northern garage protective shielding;
- Installation of purlins of internal cladding;
- Installation of external and internal cladding. Overall progress – 96.21%;
- Ventilation system (preparation of air ducts for installation, installation of air ducts, supports and scaffolding, preparation of NVC for vent systems installation. Progress – 86%

- Main Cranes System (MCS) installation:

* Final leveling of crane-runway girders;
* Cutting and installation of tracks.

- 25t crane for MCS Maintenance garage:

* Preparatory works for crane installation;
* Final leveling of crane-runway girders and installation of tracks.

- Arrangement of technological building and auxiliary facilities:

* Technological building (TEC) – installation of reinforcing cages and formwork of walls, heat insulation of roof, primer coating and puttying of walls and ceilings. Overall progress (construction part) – 93%;
* Electrical Equipment Building (EEB) – installation of cable supports, cable trays, cable layout, heat insulation of roof. Progress (construction part) – 100%;
* Fire Subdivision Access Lock (FSAL) – heat insulation of roof. Progress (construction part) – 100%;
* Firewater pumping station (FWR) – installation of formwork of northern and southern tanks. Works on repair and preparation of inner surfaces of FWR building walls for puttying and painting are being carried out. Progress (construction part) – 99%;
* Diesel power plant area – laying of electrical cables, connection of diesel-generators.

- Arrangement of internal and external space of the NSC:

* Outdoor cable routes;
* Outdoor and underground utility systems;
* Storm water catching basins;
* Construction of roads in Local zone.

Erection of Arch western part steelwork: 

Erected in total – 15,885.47 t

Erection of Arch eastern part steelwork: 

Erected in total – 14,265.62 t

June 30, 2016
June 30, 2016
June 30, 2016
June 30, 2016
June 30, 2016
June 30, 2016