Select the another date

Within the NSC Project at the construction site the following works are being performed:
- Pre-assembling and installation of Western end wall gangways;
- Installation of cable conduits bearers;
- Installation of Northern garage floor gratings;
- Installation of automatic jacks of TP-1 tilting panel;
- Completing and assembly of cladding purlines;
- Preliminary erection and assembly of steel plating packages for cladding, as well as laying of heat insulating material, assembly of EPDM membrane, assembly of bearing clip and Kalzip panels;
- Assembly of scaffolding and preparation of air ducts for assembling, assembly of air ducts of the Arch ventilation system;
- Installation of Main Cranes System elements (west bridge, classic carriage, secure carriage, Mobile Tool Platform carriage)

- Arrangement of technological building and auxiliary facilities:
* Technological building (TB) – walling, roofing (assembly of fittings and formwork, concreting, concrete curing);
* Electrical device building – priming and spackling of walls, installation of cable bearers;
* Fire units acces airlock - roofing.

- Arrangement of external and internal space of NSC (northern side):
* Storm and fire extinguishing water catchment basins;
* Arch end walls
* Outdoor underground services (power supply, water supply, sewer).

Assembly of metal structures of Western half of the Arch:

Metal structures assembled in total – 14,776.71 tons

Assembly of metal structures of Eastern half of the Arch:

Metal structures assembled in total –  14,117.81 tons

 

October 01, 2015
October 01, 2015
October 01, 2015
October 01, 2015
October 01, 2015
October 01, 2015
 

Select the another date

Within the NSC Project at the construction site the following works are being performed:
- Pre-assembling and installation of Western end wall gangways;
- Installation of cable conduits bearers;
- Installation of Northern garage floor gratings;
- Installation and tightening of bolts at the junction area of West and East halves of the Arch;
- Completing and assembly of cladding purlines;
- Preliminary erection and assembly of steel plating packages for cladding, as well as laying of heat insulating material, assembly of EPDM membrane, assembly of bearing clip and Kalzip panels;
- Assembly of scaffolding and preparation of air ducts for assembling, assembly of air ducts of the Arch ventilation system;
- Installation of Main Cranes System elements (west bridge, classic carriage, secure carriage, Mobile Tool Platform carriage)

- Arrangement of technological building and auxiliary facilities:
* Technological building (TB) – walling, roofing (assembly of fittings and formwork, concreting, concrete curing);
* Electrical device building – priming and spackling of walls, installation of cable bearers;
* Fire units acces airlock - roofing.

- Arrangement of external and internal space of NSC (northern side):
* Storm and fire extinguishing water catchment basins;
* Arch end walls
* Outdoor underground services (power supply, water supply, sewer).

Assembly of metal structures of Western half of the Arch:

Metal structures assembled in total – 14,756.51 tons

Assembly of metal structures of Eastern half of the Arch:

Metal structures assembled in total –  14,114.92 tons

 

September 24, 2015
September 24, 2015
September 24, 2015
September 24, 2015
September 24, 2015
September 24, 2015
 

Select the another date

Within the NSC Project at the construction site the following works are being performed:
- Pre-assembling and installation of Western end wall gangways;
- Installation of cable conduits bearers;
- Installation and tightening of bolts at the junction area of West and East halves of the Arch;
- Preparation for installation of TP-1 tilting panel turning mechanisms;
- Completing and assembly of cladding purlines;
- Preliminary erection and assembly of steel plating packages for cladding, as well as laying of heat insulating material, assembly of EPDM membrane, assembly of bearing clip and Kalzip panels;
- Assembly of scaffolding and preparation of air ducts for assembling, assembly of air ducts of the Arch ventilation system;
- Installation of Main Cranes System elements (west bridge, classic carriage, secure carriage, Mobile Tool Platform carriage)

- Arrangement of technological building and auxiliary facilities:
* Technological building (TB) – walling, roofing (assembly of fittings and formwork, concreting, concrete curing);
* Electrical device building – priming and spackling of walls;
* Fire units acces airlock - roofing.

- Arrangement of external and internal space of NSC (northern side):
* Storm and fire extinguishing water catchment basins;
* Arch end walls
* Outdoor underground services (power supply, water supply, sewer).

Assembly of metal structures of Western half of the Arch:

Metal structures assembled in total – 14,737.29 tons

Assembly of metal structures of Eastern half of the Arch:

Metal structures assembled in total –  14,109.268 tons

 

September 17, 2015
September 17, 2015
September 17, 2015
September 17, 2015
 

Select the another date

Within the NSC Project at the construction site the following works are being performed:
- Pre-assembling and installation of Western end wall gangways;
- Installation of cable conduits bearers;
- Installation and tightening of bolts at the junction area of West and East halves of the Arch;
- Preparation for installation of TP-1 tilting panel turning mechanisms;
- Completing and assembly of cladding purlines;
- Preliminary erection and assembly of steel plating packages for cladding, as well as laying of heat insulating material, assembly of EPDM membrane, assembly of bearing clip and Kalzip panels;
- Assembly of scaffolding and preparation of air ducts for assembling, assembly of air ducts of the Arch ventilation system;
- Installation of Main Cranes System elements (west bridge, classic carriage, secure carriage, Mobile Tool Platform carriage)

- Arrangement of technological building and auxiliary facilities:
* Technological building (TB) – walling, roofing (assembly of fittings and formwork, concreting, concrete curing);
* Electrical device building – priming and spackling of walls, installation of floor levelcrete;
* Fire units acces airlock - roofing, priming and spackling of walls, installation of floor levelcrete.

- Arrangement of external and internal space of NSC (northern side):
* Storm and fire extinguishing water catchment basins;
* Arch end walls
* Outdoor underground services (power supply, water supply, sewer).

Assembly of metal structures of Western half of the Arch:

Metal structures assembled in total – 14,730.75 tons

Assembly of metal structures of Eastern half of the Arch:

Metal structures assembled in total –  14,109.268 tons

 

September 10, 2015
September 10, 2015
September 10, 2015
September 10, 2015
September 10, 2015
September 10, 2015
 

Select the another date

Within the NSC Project at the construction site the following works are being performed:
- Pre-assembling and installation of Western end wall gangways;
- Installation of cable conduits bearers;
- Pre-assembling and installation of Northern garage gangways, stairs and banisters;
- Completing and assembly of cladding purlines;
- Preliminary erection and assembly of steel plating packages for cladding, as well as laying of heat insulating material, assembly of EPDM membrane, assembly of bearing clip and Kalzip panels;
- Assembly of scaffolding and preparation of air ducts for assembling, assembly of air ducts of the Arch ventilation system;
- Installation of Main Cranes System elements (west bridge, classic carriage, secure carriage, Mobile Tool Platform carriage)

- Arrangement of technological building and auxiliary facilities:
* Technological building (TB) – walling, roofing (assembly of fittings and formwork, concreting, concrete curing);
* Electrical device building – priming and spackling of walls, installation of floor levelcrete;
* Fire units acces airlock - roofing, priming and spackling of walls, installation of floor levelcrete.

- Arrangement of external and internal space of NSC (northern side):
* Storm and fire extinguishing water catchment basins;
* Arch end walls
* Outdoor underground services (power supply, water supply, sewer).

Assembly of metal structures of Western half of the Arch:

Metal structures assembled in total – 14,714.53 tons

Assembly of metal structures of Eastern half of the Arch:

Metal structures assembled in total –  14,109.268 tons

 

September 03, 2015
September 03, 2015
September 03, 2015
September 03, 2015
September 03, 2015
September 03, 2015