Within the NSC Project at the construction site the following works are being performed:
-Pre-assembly and installation of West End Wall gangways;
-Installation of cable conduits bearers;
-Erection of North Ventilation Centre structural steel;
-Installation of the sealing membrane flashing anchor on TP-2 tilting panel;
-Installation of automatic jacks of TP-2 tilting panel;
-Completing and erection of cladding purlins;
-Pre-assembly and erection of steel decking packages for cladding, as well as laying of heat insulating material, installation of EPDM membrane and Kalzip panels;
-Assembly of scaffolding and preparation of air ducts for installation, installation of air ducts of the Arch ventilation system;
-Installation of cable conduits for MCS power supply;
-Installation of the Main Cranes System (28.11.2015 MCS west bridge jacking was completed, work is underway on roller beam installation in the project position).

- Arrangement of technological building and auxiliary facilities:
* Technological building (TEC) – walling, roofing (installation of fittings, formwork, concreting, concrete curing);
* Electrical Equipment Building (EEB) – priming, spackling and painting of walls, floors and ceilings, installation of roof heat insulation;
* Fire Subdivision Access Lock (FSAL) – installation of reinforcement cage and walls fragments formwork;
* Firewater pumping station (FWR) –concrete curing of the foundation.

- Arrangement of external and internal space of NSC:
* Storm water ponds (concrete curing of the monolithic slab);
* Outdoor underground services (power supply, water supply, sewage).

Assembly of metal structures of Western half of the Arch:
Metal structures assembled in total – 15,136.02 tons

Assembly of metal structures of Eastern half of the Arch:
Metal structures assembled in total –  14,138.22 tons

 

December 03, 2015
December 03, 2015
December 03, 2015
December 03, 2015
December 03, 2015
December 03, 2015

Select another date

Within the NSC Project at the construction site the following works are being performed:
- Pre-assembling and installation of Western end wall gangways;
- Installation of cable conduits bearers;
- Installation of Northern ventilation center metal structures;
- Installation of crane beams at East and West halves' connection point; 
- Installation of automatic jacks of TP-2 tilting panel;
- Completing and assembly of cladding purlines;
- Preliminary erection and assembly of steel plating packages for cladding, as well as laying of heat insulating material, assembly of EPDM membrane, assembly Kalzip panels;
- Assembly of scaffolding and preparation of air ducts for assembling, assembly of air ducts of the Arch ventilation system;
- Installation of cable ducts for Main Cranes System's power supply;
- Installation of Main Cranes System elements (25-11-2015 jacking of MCS started, 25-11-2015 the West Bridge jacked to 100 mm up, 26-11-2015 the West Bridge jacked to 20 meters up, work is underway).

- Arrangement of technological building and auxiliary facilities:
* Technological building (TB) – walling, roofing (assembly of fittings and formwork, concreting, concrete curing);
* Electrical device building – priming, spackling and painting of walls, floors and ceilings, installation of roof heat insulation;
* Fire units acces airlock - interior finish;
* Fire pumping station (assembly of formwork).

- Arrangement of external and internal space of NSC (northern side):
* Hinged bearers gallery (North strip, wall concreting)
* Outdoor underground services (power supply, water supply, sewer).

Assembly of metal structures of Western half of the Arch:

Metal structures assembled in total – 15,124.58 tons

Assembly of metal structures of Eastern half of the Arch:

Metal structures assembled in total –  14,138.22 tons

 

November 26, 2015
November 26, 2015
November 26, 2015
November 26, 2015
November 26, 2015
November 26, 2015

Select another date

Within the NSC Project at the construction site the following works are being performed:
- Pre-assembling and installation of Western end wall gangways;
- Installation of cable conduits bearers;
- Installation of Northern ventilation center metal structures;
- Installation of crane beams at East and West halves' connection point; 
- Installation of automatic jacks of TP-2 tilting panel;
- Completing and assembly of cladding purlines;
- Preliminary erection and assembly of steel plating packages for cladding, as well as laying of heat insulating material, assembly of EPDM membrane, assembly Kalzip panels;
- Assembly of scaffolding and preparation of air ducts for assembling, assembly of air ducts of the Arch ventilation system;
- Installation of Main Cranes System elements (reassembly of mobile tool platform, preparatory works before lifting the west bridge to its installation area).

- Arrangement of technological building and auxiliary facilities:
* Technological building (TB) – walling, roofing (assembly of fittings and formwork, concreting, concrete curing);
* Electrical device building – priming, spackling and painting of walls, floors and ceilings, installation of roof heat insulation;
* Fire units acces airlock - roofing (concrete curing, formwork dismantling);
* Fire pumping station (assembly of formwork and foundation fittings).

- Arrangement of external and internal space of NSC (northern side):
* Outdoor underground services (power supply, water supply, sewer).

Assembly of metal structures of Western half of the Arch:

Metal structures assembled in total – 15,116.08 tons

Assembly of metal structures of Eastern half of the Arch:

Metal structures assembled in total –  14,138.22 tons

 

November 19, 2015
November 19, 2015
November 19, 2015
November 19, 2015
November 19, 2015
November 19, 2015

Select the another date

Within the NSC Project at the construction site the following works are being performed:
- Pre-assembling and installation of Western end wall gangways;
- Installation of cable conduits bearers;
- Installation of Northern ventilation center metal structures;
- Installation of crane beams at East and West halves' connection point; 
- Installation of automatic jacks of TP-1, TP-2 tilting panels;
- Completing and assembly of cladding purlines;
- Preliminary erection and assembly of steel plating packages for cladding, as well as laying of heat insulating material, assembly of EPDM membrane, assembly of bearing clip and Kalzip panels;
- Assembly of scaffolding and preparation of air ducts for assembling, assembly of air ducts of the Arch ventilation system;
- Installation of Main Cranes System elements (reassembly of mobile tool platform, preparatory works before lifting the west bridge to its installation area).


- Arrangement of technological building and auxiliary facilities:
* Technological building (TB) – walling, roofing (assembly of fittings and formwork, concreting, concrete curing);
* Electrical device building – priming, spackling and painting of walls, floors and ceilings, installation of roof heat insulation;
* Fire units acces airlock - roofing (concrete curing, formwork dismantling).


- Arrangement of external and internal space of NSC (northern side):
* Storm and fire extinguishing water catchment basins;
* Arch end walls
* Outdoor underground services (power supply, water supply, sewer).

Assembly of metal structures of Western half of the Arch:

Metal structures assembled in total – 15,116.08 tons

Assembly of metal structures of Eastern half of the Arch:

Metal structures assembled in total –  14,138.22 tons

 

November 12, 2015
November 12, 2015
November 12, 2015
November 12, 2015
November 12, 2015
November 12, 2015