Within the NSC Project at the construction site the following works are being performed:
- Delivery of tertiary steel structures to the site;
- Mounting of sliding system control module, inspection and assembling of equipment for Arch sliding;
- installation of sealing membrane anchors along the end wall
- Installation of special doors of the Arch;
- Installation of sealing membrane of swing panels;
- Installation of protective shielding of North Garage;
- Pre-assembling and mounting of rolling doors of North Garage;
- Installation of external and internal casing. Progress - 99%;
- Ventilation system (preparing the air ducts for installation, installation of air ducts, installation of supports and scaffolding, preparing the North Ventilation Center (NVC) for installation of ventilation equipment). Progress - 91%;
- Welding of Arch Ventilation stack units. Pre-assembly of Ventilation stack maintenance sites.

- Main Cranes System (MCS) installation:
* Adjusting the crane beams and rails;
* Preparing the MCS bridges for rerolling to west side of the Arch;
* Adjusting and connecting MCS control panels.

- Arrangement of technological building and auxiliary facilities:
* Technological building (TEC) – works relating to polishing, pre-coating, coating and painting of walls and ceilings inside the building, installation of doors, installation of dividing walls of gas blocks, roof sealing. Progress (construction part) - 98%;
* Electrical Equipment Building (EEB) – installation of fire alarm system within premises, mounting of cable supports and trays, installation of supports and pipes of fire-preventive and drinking water supply;
* Access gateway for fire brigades – roof sealing, polishing, pre-coating, coating and painting of walls and ceilings inside the building, installation of doors;
* Fire pump station (FPS) – works relating to pre-coating, coating and painting of walls inside the building;
* Site of diesel power plant for power supply – laying the electrical cables and connecting diesel generators, installation of equipment.

- Arrangement of internal and external space of the NSC:
* Outdoor cable routes;
* Outdoor and underground utility systems;
* Storm water catching basins;
* Construction of roads in Local zone - 28%.

Erection of Arch western part steelwork:
Erected in total
– 16,019.88 t

Erection of Arch eastern part steelwork:
Erected in total
– 14,265.62 t

 

Select another date

Within the NSC Project at the construction site the following works are being performed:
- Delivery of tertiary steel structures to the site;
- Mounting of sliding system control module, inspection and assembling of equipment for Arch sliding;
- installation of sealing membrane anchors along the end wall
- Installation of special doors of the Arch;
- Installation of sealing membrane of swing panels;
- Installation of protective shielding of North Garage;
- Pre-assembling and mounting of rolling doors of North Garage;
- Installation of external and internal casing. Progress - 98%;
- Ventilation system (preparing the air ducts for installation, installation of air ducts, installation of supports and scaffolding, preparing the North Ventilation Center (NVC) for installation of ventilation equipment). Progress - 91%;
- Welding of Arch Ventilation stack units. Pre-assembly of Ventilation stack maintenance sites.

- Main Cranes System (MCS) installation:
* Adjusting the crane beams and rails;
* Preparing the MCS bridges for rerolling to west side of the Arch;
* Adjusting and connecting MCS control panels.

- 25t crane for MCS Maintenance garage:
* Completion of crane installation.

- Arrangement of technological building and auxiliary facilities:
* Technological building (TEC) – works relating to polishing, pre-coating, coating and painting of walls and ceilings inside the building, installation of doors, installation of dividing walls of gas blocks, roof sealing. Progress (construction part) - 97%;
* Electrical Equipment Building (EEB) – installation of fire alarm system within premises, mounting of cable supports and trays, installation of supports and pipes of fire-preventive and drinking water supply;
* Access gateway for fire brigades – roof sealing, polishing, pre-coating, coating and painting of walls and ceilings inside the building, installation of doors;
* Fire pump station (FPS) – works relating to pre-coating, coating and painting of walls inside the building;
* Site of diesel power plant for power supply – laying the electrical cables and connecting diesel generators, installation of equipment.

- Arrangement of internal and external space of the NSC:
* Outdoor cable routes;
* Outdoor and underground utility systems;
* Storm water catching basins;
* Construction of roads in Local zone - 26%.

Erection of Arch western part steelwork:
Erected in total
– 15,964.28 t

Erection of Arch eastern part steelwork:
Erected in total
– 14,265.62 t

Select another date

Within the NSC Project at the construction site the following works are being performed:
- Delivery of tertiary steel structures to the site;
- Mounting of hydraulic jacks for Arch sliding;
- Mounting of sliding system control module, inspection and assembling of equipment for Arch sliding;
- installation of sealing membrane anchors along the end wall
- Installation of special doors of the Arch;
- Installation of sealing membrane of swing panels;
- Installation of protective shielding of North Garage;
- Pre-assembling and mounting of rolling doors of North Garage;
- Installation of external and internal casing. Progress - 98%;
- Ventilation system (preparing the air ducts for installation, installation of air ducts, installation of supports and scaffolding, preparing the North Ventilation Center (NVC) for installation of ventilation equipment). Progress - 91%;
- preparation for installation and welding of Arch ventilation stack elements.

- Main Cranes System (MCS) installation:
* Adjusting the crane beams and rails;
* Preparing the MCS bridges for rerolling to west side of the Arch;
* Adjusting and connecting MCS control panels.

- 25t crane for MCS Maintenance garage:
* Completion of crane installation.

- Arrangement of technological building and auxiliary facilities:
* Technological building (TEC) – works relating to polishing, pre-coating, coating and painting of walls and ceilings inside the building, installation of doors, installation of dividing walls of gas blocks, roof sealing. Progress (construction part) - 97%;
* Electrical Equipment Building (EEB) – installation of fire alarm system within premises, mounting of cable supports and trays, installation of supports and pipes of fire-preventive and drinking water supply;
* Access gateway for fire brigades – roof sealing, polishing, pre-coating, coating and painting of walls and ceilings inside the building, installation of doors;
* Fire pump station (FPS) – works relating to pre-coating, coating and painting of walls inside the building;
* Site of diesel power plant for power supply – laying the electrical cables and connecting diesel generators, installation of equipment.

- Arrangement of internal and external space of the NSC:
* Outdoor cable routes;
* Outdoor and underground utility systems;
* Storm water catching basins;
* Construction of roads in Local zone - 25.7%.

Erection of Arch western part steelwork:
Erected in total
– 15,951.41 t

Erection of Arch eastern part steelwork:
Erected in total
– 14,265.62 t

August 18, 2016
August 18, 2016
August 18, 2016
August 18, 2016
August 18, 2016
August 18, 2016

Select another date

Within the NSC Project at the construction site the following works are being performed:
- Supply of metal structures to the site;
- Mounting of hydraulic jacks for Arch sliding;
- Mounting of sliding system control module, inspection and assembling of equipment for Arch sliding;
- installation of sealing membrane anchors along the end wall
- Installation of special doors of the Arch;
- Installation of sealing membrane of swing panels;
- Installation of protective shielding of North Garage;
- Pre-assembling and mounting of rolling doors of North Garage;
- Installation of external and internal casing. Progress - 98%;
- Ventilation system (preparing the air ducts for installation, installation of air ducts, installation of supports and scaffolding, preparing the North Ventilation Center (NVC) for installation of ventilation equipment). Progress - 91%;
- preparation for installation and welding of Arch ventilation stack elements.

- Main Cranes System (MCS) installation:
* Adjusting the crane beams and rails;
* Preparing the MCS bridges for rerolling to west side of the Arch;
* Adjusting and connecting MCS control panels.

- 25t crane for MCS Maintenance garage:
* Installation of electrical crane equipment.

- Arrangement of technological building and auxiliary facilities:
* Technological building (TEC) – works relating to polishing, pre-coating, coating and painting of walls and ceilings inside the building, installation of doors, installation of dividing walls of gas blocks, roof sealing. Progress (construction part) - 97%;
* Electrical Equipment Building (EEB) – installation of fire alarm system within premises, mounting of cable supports and trays, installation of supports and pipes of fire-preventive and drinking water supply;
* Access gateway for fire brigades – roof sealing, polishing, pre-coating, coating and painting of walls and ceilings inside the building, installation of doors;
* Fire pump station (FPS) – works relating to pre-coating, coating and painting of walls inside the building;
* Site of diesel power plant for power supply – laying the electrical cables and connecting diesel generators, installation of equipment.

- Arrangement of internal and external space of the NSC:
* Outdoor cable routes;
* Outdoor and underground utility systems;
* Storm water catching basins;
* Construction of roads in Local zone - 23,5%.

Erection of Arch western part steelwork:
Erected in total
– 15,951.41 t

Erection of Arch eastern part steelwork:
Erected in total
– 14,265.62 t

August 11, 2016
August 11, 2016
August 11, 2016
August 11, 2016
August 11, 2016
August 11, 2016

Select another date

Within the NSC Project at the construction site the following works are being performed:
- Supply of metal structures to the site;
- Mounting of hydraulic jacks for Arch sliding;
- Mounting of sliding system control module, inspection and assembling of equipment for Arch sliding;
- Installation of special doors of the Arch;
- Installation of sealing membrane of swing panels;
- Installation of protective shielding of North Garage;
- Pre-assembling and mounting of rolling doors of North Garage;
- Installation of external and internal casing;
- Ventilation system (preparing the air ducts for installation, installation of air ducts, installation of supports and scaffolding, preparing the North Ventilation Center (NVC) for installation of ventilation equipment).

- Main Cranes System (MCS) installation:
* Adjusting the crane beams and rails;
* Preparing the MCS bridges for rerolling to west side of the Arch;
* Adjusting and connecting MCS control panels.

- 25t crane for MCS Maintenance garage:
* Installation of electrical crane equipment.

- Arrangement of technological building and auxiliary facilities:
* Technological building (TEC) – works relating to polishing, pre-coating, coating and painting of walls and ceilings inside the building, installation of doors, installation of dividing walls of gas blocks, roof sealing;
* Electrical Equipment Building (EEB) – installation of fire alarm system within premises, mounting of cable supports and trays, installation of supports and pipes of fire-preventive and drinking water supply;
* Access gateway for fire brigades – roof sealing, polishing, pre-coating, coating and painting of walls and ceilings inside the building, installation of doors;
* Fire pump station (FPS) – works relating to pre-coating, coating and painting of walls inside the building;
* Site of diesel power plant for power supply – laying the electrical cables and connecting diesel generators.

- Arrangement of internal and external space of the NSC:
* Outdoor cable routes;
* Outdoor and underground utility systems;
* Storm water catching basins;
* Construction of roads in Local zone.

Erection of Arch western part steelwork:
Erected in total
– 15,943.61 t

Erection of Arch eastern part steelwork:
Erected in total
– 14,265.62 t

August 04, 2016
August 04, 2016
August 04, 2016
August 04, 2016
August 04, 2016
August 04, 2016