Within the NSC Project at the construction site the following works are being performed:
- Pre-assembling and installation of Western end wall gangways;
- Installation of cable conduits bearers;
- Installation of Northern ventilation center metal structures;
- Installation of crane beams at East and West halves' connection point;
- Installation of automatic jacks of TP-2 tilting panel;
- Completing and assembly of cladding purlines;
- Preliminary erection and assembly of steel plating packages for cladding, as well as laying of heat insulating material, assembly of EPDM membrane, assembly Kalzip panels;
- Assembly of scaffolding and preparation of air ducts for assembling, assembly of air ducts of the Arch ventilation system;
- Installation of cable ducts for Main Cranes System's power supply;
- Installation of Main Cranes System elements (25-11-2015 jacking of MCS started, 25-11-2015 the West Bridge jacked to 100 mm up, 26-11-2015 the West Bridge jacked to 20 meters up, work is underway).
- Arrangement of technological building and auxiliary facilities:
* Technological building (TB) – walling, roofing (assembly of fittings and formwork, concreting, concrete curing);
* Electrical device building – priming, spackling and painting of walls, floors and ceilings, installation of roof heat insulation;
* Fire units acces airlock - interior finish;
* Fire pumping station (assembly of formwork).
- Arrangement of external and internal space of NSC (northern side):
* Hinged bearers gallery (North strip, wall concreting)
* Outdoor underground services (power supply, water supply, sewer).
Assembly of metal structures of Western half of the Arch:
Metal structures assembled in total – 15,124.58 tons
Assembly of metal structures of Eastern half of the Arch:
Metal structures assembled in total – 14,138.22 tons