NSC construction progress as of December 3, 2015

Select another date

Within the NSC Project at the construction site the following works are being performed:
-Pre-assembly and installation of West End Wall gangways;
-Installation of cable conduits bearers;
-Erection of North Ventilation Centre structural steel;
-Installation of the sealing membrane flashing anchor on TP-2 tilting panel;
-Installation of automatic jacks of TP-2 tilting panel;
-Completing and erection of cladding purlins;
-Pre-assembly and erection of steel decking packages for cladding, as well as laying of heat insulating material, installation of EPDM membrane and Kalzip panels;
-Assembly of scaffolding and preparation of air ducts for installation, installation of air ducts of the Arch ventilation system;
-Installation of cable conduits for MCS power supply;
-Installation of the Main Cranes System (28.11.2015 MCS west bridge jacking was completed, work is underway on roller beam installation in the project position).

- Arrangement of technological building and auxiliary facilities:
* Technological building (TEC) – walling, roofing (installation of fittings, formwork, concreting, concrete curing);
* Electrical Equipment Building (EEB) – priming, spackling and painting of walls, floors and ceilings, installation of roof heat insulation;
* Fire Subdivision Access Lock (FSAL) – installation of reinforcement cage and walls fragments formwork;
* Firewater pumping station (FWR) –concrete curing of the foundation.

- Arrangement of external and internal space of NSC:
* Storm water ponds (concrete curing of the monolithic slab);
* Outdoor underground services (power supply, water supply, sewage).

Assembly of metal structures of Western half of the Arch:
Metal structures assembled in total – 15,136.02 tons

Assembly of metal structures of Eastern half of the Arch:
Metal structures assembled in total –  14,138.22 tons

 