Select the another date

Within the NSC Project at the construction site the following works are being performed:

- Supplies to the site and completing main metal structures of the Arch;
- Total assembly of metal structures of the Arch (including tilting panel TP-6);

- Assembly of main metal structures of the western part of the Arch;
- Completing and assembly of casing girders;
- Preliminary assembly of steel plating packages for casing, laying of 1 layer of Dachrock, assembly of EPDM membrane, assembly of bearing clips;
- Assembly of scaffolding and preparation of air ducts for assembling, assembling of air ducts of the Arch ventilation system;

- Arrangement of technological building and auxiliary facilities:
   * Technological building (TB) – walling and arranging the building columns (assembly of fittings and formwork, concreting, concrete curing);
   * Electrical device building – building wall arrangement (assembly of fittings and formwork);

- Arrangement of external and internal space of NSC (northern side):
   * End walls of the Arch;
   * Access gateway for fire brigades;
   * Walls of hinged bearing gallery;
   * Storm water catchment basins;
   * Outdoor underground services.

Assembly of metal structures of Western part of the Arch:
Metal structures assembled in total –  13,555.009 tons

Assembly of metal structures of Eastern part of the Arch:
Metal structures assembled in total –  13,272.22 tons

February 26, 2015
February 26, 2015
February 26, 2015
February 26, 2015
February 26, 2015
February 26, 2015
   

Select the another date

Within the NSC Project at the construction site the following works are being performed:

- Supplies to the site and completing main metal structures of the Arch;
- Total assembly of metal structures of the Arch (including tilting panel TP-6);

- Assembly of main metal structures of the western part of the Arch;
- Completing and assembly of casing girders;
- Preliminary assembly of steel plating packages for casing, laying of 1 layer of Dachrock, assembly of EPDM membrane, assembly of bearing clips;
- Assembly of scaffolding and preparation of air ducts for assembling, assembling of air ducts of the Arch ventilation system;

- Arrangement of technological building and auxiliary facilities:
   * Technological building (TB) – walling and arranging the building columns (assembly of fittings and formwork, concreting, concrete curing);
   * Electrical device building – building wall arrangement (assembly of fittings and formwork);

- Arrangement of external and internal space of NSC (northern side):
   * End walls of the Arch;
   * Access gateway for fire brigades;
   * Walls of hinged bearing gallery;
   * Storm water catchment basins;
   * Outdoor underground services.

Assembly of metal structures of Western part of the Arch:
Metal structures assembled in total –  13,489.060 tons

Assembly of metal structures of Eastern part of the Arch:
Metal structures assembled in total –  13,272.22 tons

February 19, 2015
February 19, 2015
February 19, 2015
February 19, 2015
February 19, 2015
February 19, 2015
 

Select the another date

Within the NSC Project at the construction site the following works are being performed:

- Supplies to the site and completing main metal structures of the Arch;
- Total assembly of metal structures of the Arch;
- Assembly of main metal structures of the western part of the Arch;
- Completing and assembly of casing girders;
- Preliminary assembly of steel plating packages for casing, laying of 1 layer of Dachrock, assembly of EPDM membrane, assembly of bearing clips;
- Assembly of scaffolding and preparation of air ducts for assembling, assembling of air ducts of the Arch ventilation system;

- Arrangement of technological building and auxiliary facilities:
   * Technological building (TB) – walling and arranging the building columns (assembly of fittings and formwork, concreting, concrete curing);
   * Electrical device building – building wall arrangement (assembly of fittings and formwork);

- Arrangement of external and internal space of NSC (northern side):
   * End walls of the Arch;
   * Access gateway for fire brigades;
   * Walls of hinged bearing gallery;
   * Storm water catchment basins;
   * Outdoor underground services.

Assembly of metal structures of Western part of the Arch:

Metal structures assembled in total –  13,342.183 tons

February 12, 2015
February 12, 2015
February 12, 2015
February 12, 2015
 

Select the another date

Within the NSC Project at the construction site the following works are being performed:

- Supplies to the site and completing main metal structures of the Arch;
- Total assembly of metal structures of the Arch;
- Assembly of main metal structures of the western part of the Arch;
- Completing and assembly of casing girders;
- Preliminary assembly of steel plating packages for casing, laying of 1 layer of Dachrock, assembly of EPDM membrane, assembly of bearing clips;
- Assembly of scaffolding and preparation of air ducts for assembling, assembling of air ducts of the Arch ventilation system;

- Arrangement of technological building and auxiliary facilities:
   * Technological building (TB) – walling and arranging the building columns (assembly of fittings and formwork, concreting, concrete curing);
   * Electrical device building – building wall arrangement (assembly of fittings and formwork);

- Arrangement of external and internal space of NSC (northern side):
   * End walls of the Arch;
   * Access gateway for fire brigades;
   * Walls of hinged bearing gallery;
   * Storm water catchment basins;
   * Outdoor underground services.

Assembly of metal structures of Western part of the Arch:

Metal structures assembled in total –  13,129.494 tons

February 05, 2015
February 05, 2015
February 05, 2015
February 05, 2015
February 05, 2015
February 05, 2015
 

Select the another date

Within the NSC Project at the construction site the following works are being performed:
- Delivery to the site and assembly of main structures of the Western part of Arch;
- Pre-assemble of Arch metal structures;
- Installation of purlines for clading;
- Pre-assemble of steel cladding flooring packages, laying of the first layer of Dachrock, installation of EPDM membrane, installation of support clips;

- Works on technological building and auxiliary facilities arrangement are underway:
     * Techological building - installation of formwork and rebars, concreting, concrete curing;
     * Electrical device building - installation of formwork and rebars;

- Arrangement of internal and external space of NSC (northern side):
     * End walls of the Arch;
     * Access airlock for fire units;
     * Walls of hinged bearing gallery;
     * Storm water catchment basins;
     * Outdoor underground services.

Assembly of metal structures of Western part of the Arch:

Metal structures assembled in total –  12,963.87 tons

January 29, 2015
January 29, 2015
January 29, 2015
January 29, 2015
January 29, 2015
January 29, 2015