NSC construction progress as of January 22, 2015

Select the another date

Within the NSC Project at the construction site the following works are being performed:
- Delivery to the site and assembly of main structures of the Western part of Arch;
- Pre-assemble of Arch metal structures;
- Installation of purlines for clading;
- Pre-assemble of cladding packages;

- Works on technological building and auxiliary facilities arrangement are underway:
     * Techological building - installation of formwork and rebars, concrete curing;
     * Electrical device building - installation of formwork and rebars, concrete curing;

- Arrangement of internal and external space of NSC (northern side):
     * End walls of the Arch;
     * Walls of hinged bearing gallery;
     * Storm water catchment basins;
     * Fire water catchment basins;
     * Outdoor underground services.

Assembly of metal structures of Western part of the Arch:

Metal structures assembled in total –  12,933.57 tons

January 22, 2015