NSC construction progress as of February 12, 2015

Select the another date

Within the NSC Project at the construction site the following works are being performed:

- Supplies to the site and completing main metal structures of the Arch;
- Total assembly of metal structures of the Arch;
- Assembly of main metal structures of the western part of the Arch;
- Completing and assembly of casing girders;
- Preliminary assembly of steel plating packages for casing, laying of 1 layer of Dachrock, assembly of EPDM membrane, assembly of bearing clips;
- Assembly of scaffolding and preparation of air ducts for assembling, assembling of air ducts of the Arch ventilation system;

- Arrangement of technological building and auxiliary facilities:
   * Technological building (TB) – walling and arranging the building columns (assembly of fittings and formwork, concreting, concrete curing);
   * Electrical device building – building wall arrangement (assembly of fittings and formwork);

- Arrangement of external and internal space of NSC (northern side):
   * End walls of the Arch;
   * Access gateway for fire brigades;
   * Walls of hinged bearing gallery;
   * Storm water catchment basins;
   * Outdoor underground services.

Assembly of metal structures of Western part of the Arch:

Metal structures assembled in total –  13,342.183 tons

February 12, 2015
February 12, 2015
February 12, 2015
February 12, 2015