Within the NSC Project at the construction site the following works are being performed:
- Pre-assembling and installation of Western end wall gangways;
- Completing and assembly of cladding purlines;
- Preliminary erection and assembly of steel plating packages for cladding, as well as laying of heat insulating material, assembly of EPDM membrane, assembly of bearing clip and Kalzip panels;
- Assembly of scaffolding and preparation of air ducts for assembling, assembly of air ducts of the Arch ventilation system;
- Installation of Main Cranes System elements (west bridge, standard trolley, safety trolley)

- Arrangement of technological building and auxiliary facilities:
* Technological building (TB) – walling, roofing and arranging the building columns (assembly of fittings and formwork, concreting, concrete curing);
* Electrical device building – roofing (preparatory works, assembly of fittings and formwork);
* Fire units acces airlock (concrete curing).

- Arrangement of external and internal space of NSC (northern side):
* Storm and fire extinguishing water catchment basins;
* Arch end walls
* Outdoor underground services.

Assembly of metal structures of Western part of the Arch:

Metal structures assembled in total – 14,547.8 tons

Assembly of metal structures of Eastern part of the Arch:

Metal structures assembled in total –  14,109.268 tons

 

Works on joining together the West and the East halves of the Arch were finished on July 24. The main moving of the Arch East half towards the West one up to the minimum gap, between the end parts of main metal structures (20-30 mm), was performed by afternoon of July 23. Adjustment and geodetic survey of the Arch East half’s position was made.

July 23, 2015
July 23, 2015
July 23, 2015
July 23, 2015
July 23, 2015
July 23, 2015

Select the another date

Within the NSC Project at the construction site the following works are being performed:
- Pre-assembling and installation of Western end wall gangways;
- Completing and assembly of cladding purlines;
- Preliminary erection and assembly of steel plating packages for cladding, as well as laying of heat insulating material, assembly of EPDM membrane, assembly of bearing clip and Kalzip panels;
- Assembly of scaffolding and preparation of air ducts for assembling, assembly of air ducts of the Arch ventilation system;
- Installation of Main Cranes System elements (west bridge, standard trolley, safety trolley)

 

- Arrangement of technological building and auxiliary facilities:
* Technological building (TB) – walling, roofing and arranging the building columns (assembly of fittings and formwork, concreting, concrete curing);
* Electrical device building – roofing (preparatory works, assembly of fittings and formwork);
* Fire units acces airlock (wall reinforcement, installation of formwork, concreting and concrete curing).

- Arrangement of external and internal space of NSC (northern side):
* Storm and fire extinguishing water catchment basins;
* Arch end walls
* Outdoor underground services.

 

Assembly of metal structures of Western part of the Arch:

Metal structures assembled in total – 14,541.5 tons

Assembly of metal structures of Eastern part of the Arch:

Metal structures assembled in total –  14,109.268 tons

July 16, 2015
July 16, 2015
July 16, 2015
July 16, 2015
July 16, 2015
July 16, 2015

Select the another date

Within the NSC Project at the construction site the following works are being performed:
- Bolt tightening of West end wall structures;
- Completing and assembly of cladding purlins;
- Preliminary erection and assembly of steel plating packages for cladding, as well as laying of heat insulating material, assembly of EPDM membrane, assembly of bearing clip and Kalzip panels;
- Assembly of scaffolding and preparation of air ducts for assembling, assembly of air ducts of the Arch ventilation system;
- Preparation for installation and installation of Main Cranes System structures

- Arrangement of technological building and auxiliary facilities:
* Technological building (TB) – walling, roofing and arranging the building columns (assembly of fittings and formwork, concreting, concrete curing);
* Electrical device building – roofing (preparatory works, assembly of fittings and formwork);
* Fire units acces airlock (wall reinforcement, installation of formwork, concreting and concrete curing).

- Arrangement of external and internal space of NSC (northern side):
* Storm and fire extinguishing water catchment basins;
* Outdoor underground services.

Assembly of metal structures of Western part of the Arch:

Metal structures assembled in total – 14,534.001 tons

Assembly of metal structures of Eastern part of the Arch:

Metal structures assembled in total – 14,109.268 tons

Select the another date

Within the NSC Project at the construction site the following works are being performed:
- Bolt tightening of West end wall structures;
- Assembly of tilting panel TP-5.1 to the East end wall;
- Completing and assembly of cladding purlins;
- Preliminary erection and assembly of steel plating packages for cladding, as well as laying of heat insulating material, assembly of EPDM membrane, assembly of bearing clip and Kalzip panels;
- Assembly of scaffolding and preparation of air ducts for assembling, assembly of air ducts of the Arch ventilation system;

- Arrangement of technological building and auxiliary facilities:
* Technological building (TB) – walling, roofing and arranging the building columns (assembly of fittings and formwork, concreting, concrete curing);
* Electrical device building – roofing (preparatory works, assembly of fittings and formwork);
* Fire units acces airlock (wall reinforcement, installation of formwork, concreting and concrete curing).

- Arrangement of external and internal space of NSC (northern side):
* Storm and fire extinguishing water catchment basins;
* Outdoor underground services.

Assembly of metal structures of Western part of the Arch:

Metal structures assembled in total – 14,517.501 tons

Assembly of metal structures of Eastern part of the Arch:

Metal structures assembled in total – 14,109.268 tons

July 02, 2015
July 02, 2015
July 02, 2015
July 02, 2015
July 02, 2015
July 02, 2015

Select the another date

Within the NSC Project at the construction site the following works are being performed:
- Bolt tightening of West end wall structures;
- Assembly of tilting panel TP-5.1 to the East end wall;
- Completing and assembly of cladding purlins;
- Preliminary erection and assembly of steel plating packages for cladding, as well as laying of heat insulating material, assembly of EPDM membrane, assembly of bearing clip and Kalzip panels;
- Assembly of scaffolding and preparation of air ducts for assembling, assembly of air ducts of the Arch ventilation system;

- Arrangement of technological building and auxiliary facilities:
* Technological building (TB) – walling, roofing and arranging the building columns (assembly of fittings and formwork, concreting, concrete curing);
* Electrical device building – roofing (preparatory works, assembly of fittings and formwork);
* Fire units acces airlock (wall reinforcement, installation of formwork, concreting and concrete curing).

- Arrangement of external and internal space of NSC (northern side):
* Storm and fire extinguishing water catchment basins;
* Outdoor underground services.

Assembly of metal structures of Western part of the Arch:
Metal structures assembled in total – 14,517.501 tons

Assembly of metal structures of Eastern part of the Arch:
Metal structures assembled in total – 14,109.268 tons