Within the NSC Project at the construction site the following works are being performed:
- Supplies to the site and assembly of main structures of the Western part of Arch;
- Installation of main metal structures of the Western part of Arch;
- Installation of internal casing;
- Installation of main beams of the casing;
- Delivery and installation of air ducts, preparation for installation and installation of air ducts and supports in the annular space of the Western and Eastern parts of Arch;
- Works on technological building and auxiliary facilities arrangement are underway:
     * Engineering building – assembly of foundation slab and wall reinforcement, installation of formwork for wall arrangement, concrete curing;
      * electrical devices building - walls reinforcement installation, assembling of casing for the walls arrangement, concreting, concrete curing.
- Arrangement of internal and external space of NSC:
     * End walls of the Arch;
     * Walls of hinged bearing gallery;
     * Storm water catchment basins;
     * Fire water catchment basins;
     * Outdoor underground services.

Assembly of metal structures of Western part of the Arch till 3rd lifting:
Metal structures assembled in total – 11544,113 tons

Concreting of the Technological building and electrical devices building foundation slab:
Design volume of concrete is 6542 m3,  6160  m3 is laid (94%) 
Designed quantity of reinforcement is – 1375 tons, 1333 tons is produced (97,0%)

 

October 30, 2014
October 30, 2014
October 30, 2014
October 30, 2014
October 30, 2014
October 30, 2014

 Select the another date

Within the NSC Project at the construction site the following works are being performed:
- Supplies to the site and assembly of main structures of the Western part of Arch;
- Installation of main metal structures of the Western part of Arch;
- Installation of internal casing;
- Installation of main beams of the casing;
- Installation of tension systems for Arch jacking;
- Delivery and installation of air ducts, preparation for installation and installation of air ducts and supports in the annular space of the Western and Eastern parts of Arch;
- Works on technological building and auxiliary facilities arrangement are underway:
     * Engineering building – assembly of foundation slab and wall reinforcement, installation of formwork for wall arrangement, concrete curing;
      * electrical devices building - walls reinforcement installation, assembling of casing for the walls arrangement, concreting, concrete curing.
- Arrangement of internal and external space of NSC:
     * End walls of the Arch;
     * Walls of hinged bearing gallery;
     * Storm water catchment basins;
     * Fire water catchment basins;
     * Outdoor underground services.

Assembly of metal structures of Western part of the Arch till 3rd lifting:
Metal structures assembled in total – 10.772,654 tons.

Concreting of the Technological building foundation slab:
Design volume of concrete is 6,542 m3, 6,160 m3 is laid (94%)
Designed quantity of reinforcement is 1,375 tons, 1,333 tons is produced (97%)

 Select the another date

Within the NSC Project at the construction site the following works are being performed:
- Supplies to the site and assembly of main structures of the Western part of Arch;
- Installation of main metal structures of the Western part of Arch;
- Installation of external and internal casing;
- Installation of main beams of the casing;
- Installation of tension systems for Arch jacking;
- Delivery and installation of air ducts, preparation for installation and installation of air ducts and supports in the annular space of the Western and Eastern parts of Arch;
- Works on technological building and auxiliary facilities arrangement are underway:
     * Engineering building – assembly of foundation slab and wall reinforcement, installation of formwork for wall arrangement, concrete curing;
      * electrical devices building - walls reinforcement installation, assembling of casing for the walls arrangement, concreting, concrete curing.
- Arrangement of internal and external space of NSC:
     * End walls of the Arch;
     * Walls of hinged bearing gallery;
     * Storm water catchment basins;
     * Fire water catchment basins;
     * Outdoor underground services.

Assembly of metal structures of Western part of the Arch till 3rd lifting:
Metal structures assembled in total – 10761,848 tons.

Concreting of the Technological building foundation slab:
Design volume of concrete is 6542 m3, 6160 m3 is laid (94%)
Designed quantity of reinforcement is 1,375 tons, 1333 tons is produced (97%)

 

October 16, 2014
October 16, 2014
October 16, 2014
October 16, 2014
October 16, 2014
October 16, 2014
 

 Select the another date

Within the NSC Project at the construction site the following works are being performed:
- Supplies to the site and assembly of main structures of the Western part of Arch;
- Installation of main metal structures of the Western part of Arch;
- Installation of external and internal casing;
- Installation of main beams of the casing;
- Revision of containers for the Arch jacking;
- Delivery and installation of air ducts, preparation for installation and installation of air ducts and supports in the annular space of the Western and Eastern parts of Arch;
- Works on technological building and auxiliary facilities arrangement are underway:
     * Engineering building – assembly of foundation slab and wall reinforcement, installation of formwork for wall arrangement, concrete curing;
      * electrical devices building - walls reinforcement installation, assembling of casing for the walls arrangement, concreting, concrete curing.
- Arrangement of internal and external space of NSC:
     * End walls of the Arch;
     * Walls of hinged bearing gallery;
     * Storm water catchment basins;
     * Fire water catchment basins;
     * Outdoor underground services.

Assembly of metal structures of Western part of the Arch till 3rd lifting:
Metal structures assembled in total – 10,721.988 tons.

Concreting of the Technological building foundation slab:
Design volume of concrete is 6,606 m3, 6,170 m3 is laid (93%)
Designed quantity of reinforcement is 1,375 tons, 1,292 tons is produced (94%)

 