Within the NSC Project at the construction site the following works are being performed:
- Bolt tightening of West end wall structures;
- Assembly of tilting panel TP-5.1 to the East end wall;
- Completing and assembly of cladding purlins;
- Preliminary erection and assembly of steel plating packages for cladding, as well as laying of heat insulating material, assembly of EPDM membrane, assembly of bearing clip and Kalzip panels;
- Assembly of scaffolding and preparation of air ducts for assembling, assembly of air ducts of the Arch ventilation system;

- Arrangement of technological building and auxiliary facilities:
* Technological building (TB) – walling, roofing and arranging the building columns (assembly of fittings and formwork, concreting, concrete curing);
* Electrical device building – roofing (preparatory works, assembly of fittings and formwork);
* Fire units acces airlock (wall reinforcement, installation of formwork, concreting and concrete curing).

- Arrangement of external and internal space of NSC (northern side):
* Storm and fire extinguishing water catchment basins;
* Outdoor underground services.

Assembly of metal structures of Western part of the Arch:
Metal structures assembled in total – 14,513.124 tons

Assembly of metal structures of Eastern part of the Arch:
Metal structures assembled in total – 14,109.268 tons

June 18, 2015
June 18, 2015
June 18, 2015
June 18, 2015
June 18, 2015
June 18, 2015

Select the another date

Within the NSC Project at the construction site the following works are being performed:
- Bolt tightening of West end wall structures;
- Assembly of tilting panel TP-5.1 to the East end wall;
- Completing and assembly of cladding purlins;
- Preliminary erection and assembly of steel plating packages for cladding, as well as laying of heat insulating material, assembly of EPDM membrane, assembly of bearing clips, profiling of Kalzip panels;
- Assembly of scaffolding and preparation of air ducts for assembling, assembly of air ducts of the Arch ventilation system;

- Arrangement of technological building and auxiliary facilities:
   * Technological building (TB) – walling, roofing and arranging the building columns (assembly of fittings and formwork, concreting, concrete curing);
   * Electrical device building – roofing (assembly of fittings and formwork);
   * Fire units acces airlock (wall reinforcement, installation of formwork, concreting and concrete curing).

- Arrangement of external and internal space of NSC (northern side):
   * Storm and fire extinguishing water catchment basins;
   * Outdoor underground services.

Assembly of metal structures of Western part of the Arch:
Metal structures assembled in total – 14,469.894 tons

Assembly of metal structures of Eastern part of the Arch:
Metal structures assembled in total – 14,099.148 tons

June 11, 2015
June 11, 2015
June 11, 2015
June 11, 2015
June 11, 2015
June 11, 2015
 

Select the another date

Within the NSC Project at the construction site the following works are being performed:
- Bolt tightening of West end wall structures;
- Lifting and assembly of tilting panel TP-5.1 to the East end wall;
- Completing and assembly of cladding purlins;
- Preliminary erection and assembly of steel plating packages for cladding, as well as laying of heat insulating material, assembly of EPDM membrane, assembly of bearing clips, profiling of Kalzip panels;
- Assembly of scaffolding and preparation of air ducts for assembling, assembly of air ducts of the Arch ventilation system;

- Arrangement of technological building and auxiliary facilities:
   * Technological building (TB) – walling, roofing and arranging the building columns (assembly of fittings and formwork, concreting, concrete curing);
   * Electrical device building – roofing (assembly of fittings and formwork);
   * Fire units acces airlock (wall reinforcement, installation of formwork, concreting and concrete curing).

- Arrangement of external and internal space of NSC (northern side):
   * Storm and fire extinguishing water catchment basins;
   * Outdoor underground services.

Assembly of metal structures of Western part of the Arch:
Metal structures assembled in total – 14,449.85 tons

Assembly of metal structures of Eastern part of the Arch:
Metal structures assembled in total – 13,483.53 tons

Select the another date

Within the NSC Project at the construction site the following works are being performed:
- bolt tightening of West end wall structures;
- assembly of external and internal tilting panel TP-5.2 purlins of the East end wall;
- Completing and assembly of cladding purlins;
- Preliminary erection and assembly of steel plating packages for cladding, as well as laying of heat insulating material, assembly of EPDM membrane, assembly of bearing clips, profiling of Kalzip panels;
- Assembly of scaffolding and preparation of air ducts for assembling, assembly of air ducts of the Arch ventilation system;

- Arrangement of technological building and auxiliary facilities:
   * Technological building (TB) – walling, roofing and arranging the building columns (assembly of fittings and formwork, concreting, concrete curing);
   * Electrical device building – roofing (assembly of fittings and formwork);
   * Fire units acces airlock (wall reinforcement, installation of formwork, concreting and concrete curing).

- Arrangement of external and internal space of NSC (northern side):
   * Arch end walls;
   * Storm and fire extinguishing water catchment basins;
   * Outdoor underground services.

Assembly of metal structures of Western part of the Arch:
Metal structures assembled in total – 14,382.26 tons

Assembly of metal structures of Eastern part of the Arch:
Metal structures assembled in total – 13,712.32 tons

Select the another date

Within the NSC Project at the construction site the following works are being performed:
- bolt tightening of West end wall structures;
- Completing and assembly of cladding purlines;
- Preliminary erection and assembly of steel plating packages for cladding, as well as laying of heat insulating material, assembly of EPDM membrane, assembly of bearing clips, profiling of Kalzip panels;
- Assembly of scaffolding and preparation of air ducts for assembling, assembly of air ducts of the Arch ventilation system;

- Arrangement of technological building and auxiliary facilities:
   * Technological building (TB) – walling, roofing and arranging the building columns (assembly of fittings and formwork, concreting, concrete curing);
   * Electrical device building – roofing (assembly of fittings and formwork);
   * Fire units acces airlock (wall reinforcement, installation of formwork, concreting and concrete curing).

- Arrangement of external and internal space of NSC (northern side):
   * Walls of hinged bearing gallery;
   * Storm and fire extinguishing water catchment basins;
   * Outdoor underground services.

Assembly of metal structures of Western part of the Arch:
Metal structures assembled in total – 14,3369.92 tons

Assembly of metal structures of Eastern part of the Arch:
Metal structures assembled in total – 13,712.32 tons

May 21, 2015
May 21, 2015
May 21, 2015
May 21, 2015
May 21, 2015
May 21, 2015