Within the NSC Project at the construction site the following works are being performed:
- Delivery to the site and assembly of main structures of the Western part of Arch;
- Pre-assemble of Arch metal structures;
- Installation of purlines for clading;
- Pre-assemble of steel cladding flooring packages, laying of the first layer of Dachrock, installation of EPDM membrane, installation of support clips;
- Works on technological building and auxiliary facilities arrangement are underway:
* Techological building - installation of formwork and rebars, concreting, concrete curing;
* Electrical device building - installation of formwork and rebars;
- Arrangement of internal and external space of NSC (northern side):
* End walls of the Arch;
* Access airlock for fire units;
* Walls of hinged bearing gallery;
* Storm water catchment basins;
* Outdoor underground services.
Assembly of metal structures of Western part of the Arch:
Metal structures assembled in total – 12,963.87 tons