Within the NSC Project at the construction site the following works are being performed:
- Delivery to the site and assembly of main structures of the Western part of Arch;
- Installation of main metal structures of the Western part of Arch;
- Installation of cladding purlines;
- Installation of internal and external cladding;
- Dismantle of lifting towers;
- Preparation for transportation and removal of Mammoet equipment from the site;
- Delivery and installation of air ducts, preparation for installation;
- Works on technological building and auxiliary facilities arrangement are underway:
* Techological building – assembly of foundation slab and wall reinforcement, installation of formwork for wall arrangement, concreting, concrete curing;
* electrical devices building - walls reinforcement installation, assembling of casing for the walls arrangement, concreting, concrete curing;
* firefighting unit access airlocks - concreting of foundation slab completed, concrete curing.
- Arrangement of internal and external space of NSC:
* End walls of the Arch;
* Walls of hinged bearing gallery;
* Storm water catchment basins;
* Fire water catchment basins;
* Outdoor underground services.
Assembly of metal structures of Western part of the Arch:
Metal structures assembled in total – 12,933.57 tons
Concreting of the Technological building and electrical devices building foundation slab:
Design volume of concrete is 6,542 m3, laid 6,448м3 (98%)
Designedy ammount of reinforcement is 1,375 tons, prodeced 1,333 tons (98%)