NSC construction progress as of December 18, 2014

Select the another date

Within the NSC Project at the construction site the following works are being performed:
- Delivery to the site and assembly of main structures of the Western part of Arch;
- Installation of main metal structures of the Western part of Arch;
- Installation of cladding purlines;
- Installation of internal and external cladding;
- Dismantle of lifting towers;
- Preparation for transportation and removal of Mammoet equipment from the site;
- Delivery and installation of air ducts, preparation for installation;

- Works on technological building and auxiliary facilities arrangement are underway:
     * Techological building – assembly of foundation slab and wall reinforcement, installation of formwork for wall arrangement, concreting, concrete curing;
      * electrical devices building - walls reinforcement installation, assembling of casing for the walls arrangement, concreting, concrete curing;
      * firefighting unit access airlocks - concreting of foundation slab completed, concrete curing.

- Arrangement of internal and external space of NSC:
     * End walls of the Arch;
     * Walls of hinged bearing gallery;
     * Storm water catchment basins;
     * Fire water catchment basins;
     * Outdoor underground services.

Assembly of metal structures of Western part of the Arch:
Metal structures assembled in total –  12,933.57 tons

Concreting of the Technological building and electrical devices building foundation slab:
Design volume of concrete is 6,542 m3, laid 6,448м3 (98%) 
Designedy ammount of reinforcement is 1,375 tons, prodeced 1,333 tons (98%)

 

December 18, 2014