Within the NSC Project at the construction site the following works are being performed:
- Delivery to the site and assembly of main structures of the Western part of Arch;
- Installation of metal structures of Arch Western part filling;
- Preparation and completion of purlines for clading before installation;
- Dismantle of jacking beams;
- Works on technological building and auxiliary facilities arrangement are underway:
* Techological building - dismantle of formwork for wall arrangement, snow removal;
* Electrical device building - dismantle of slab formwork, snow removal;
- Arrangement of internal and external space of NSC (northern side):
* End walls of the Arch;
* Storm water catchment basins;
* Outdoor underground services.
Assembly of metal structures of Western part of the Arch:
Metal structures assembled in total – 12,933.57 tons