NSC construction progress as of January 15, 2015

Select the another date

Within the NSC Project at the construction site the following works are being performed:
- Delivery to the site and assembly of main structures of the Western part of Arch;
- Installation of metal structures of Arch Western part filling;
- Preparation and completion of purlines for clading before installation;
- Dismantle of jacking beams;

- Works on technological building and auxiliary facilities arrangement are underway:
     * Techological building - dismantle of formwork for wall arrangement, snow removal;
     * Electrical device building - dismantle of slab formwork, snow removal;

- Arrangement of internal and external space of NSC (northern side):
     * End walls of the Arch;
     * Storm water catchment basins;
     * Outdoor underground services.

Assembly of metal structures of Western part of the Arch:

Metal structures assembled in total –  12,933.57 tons